Renown, Inc. v. Hensel Phelps Construction Co.

154 Cal. App. 3d 413, 201 Cal. Rptr. 242, 1984 Cal. App. LEXIS 1896
CourtCalifornia Court of Appeal
DecidedApril 12, 1984
DocketA017099
StatusPublished
Cited by8 cases

This text of 154 Cal. App. 3d 413 (Renown, Inc. v. Hensel Phelps Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Renown, Inc. v. Hensel Phelps Construction Co., 154 Cal. App. 3d 413, 201 Cal. Rptr. 242, 1984 Cal. App. LEXIS 1896 (Cal. Ct. App. 1984).

Opinion

Opinion

NEWSOM, J.

In 1972 respondent Schaaf-Jacobs-Vinson 1 (Schaaf) entered into a written contract to provide design, architectural, and engineering services for a winery which appellant Souverain Cellars 2 proposed to build in Sonoma County. In 1973 Souverain entered into a written agreement with respondent Hensel Phelps Construction Company (Hensel) under which Hensel was to construct the winery in accordance with the plans and specifications furnished by Schaaf.

Both the design agreement and the construction agreement contained provisions for arbitration of disputes arising thereunder. However, both agreements expressly prohibited a demand for arbitration being made after the date when institution of legal proceedings on any underlying claim would be barred by the applicable statute of limitations. Furthermore, the construction agreement excepted from arbitration those claims which were deemed waived under the agreement by the making or acceptance of final payment.

Construction of the winery commenced in 1973 and work was substantially completed in 1974. Throughout this period appellants monitored the progress of construction through Jerry Graves, a full-time quality auditor employed by appellants to oversee and inspect the design and construction of the winery. Upon completion of construction, appellants made final payment for all work performed.

In 1976 appellants contracted to sell the winery to real party in interest North Coast Cellars. In connection with this sale, appellants warranted that the real property improvements were structurally sound and agreed that warranty disputes would be arbitrated.

In 1978 North Coast complained to appellants about several problems at the winery, including alleged roof defects. In June of 1980 North Coast *417 obtained a stipulated order for arbitration of its claim that appellants, by virtue of the warranty of structural soundness, were liable for the roof problems. In June of 1981 appellants demanded that respondents Schaaf and Hensel participate in the arbitration to determine whether, as the designer and the builder of the winery, they would be liable to reimburse appellants for such amounts as North Coast might recover. Neither respondent acceded to the arbitration demand.

Appellants thereupon petitioned the trial court for an order compelling respondents to arbitrate and to consolidate the requested arbitration with the existing arbitration proceedings then pending between appellants and North Coast. The trial court dismissed the petition on the grounds that 1) arbitration of the claim against Hensel for roofing defects was waived under the contract by appellants’ making final payment to Hensel; and 2) arbitration of the roofing claims against both Hensel and Schaaf was waived under the contract by appellants’ failure to demand arbitration before the expiration of the applicable statute of limitations. Since either of such findings is alone sufficient to have warranted dismissal as to remaining respondent Hensel, appellants’ burden on appeal is to demonstrate that both are erroneous.

As to the first of the trial court’s grounds for dismissal, appellants contend that, as they were unaware of the roof’s structural defects until North Coast brought them to their attention in 1978, final payment in 1974 did not constitute a knowing and intelligent waiver of arbitration under the contract.

Code of Civil Procedure section 1281.2 provides in pertinent part: “On petition of a party to an arbitration agreement alleging the existence of a written agreement to arbitrate a controversy and that a party thereto refuses to arbitrate such controversy, the court shall order the petitioner and the respondent to arbitrate the controversy if it determines that an agreement to arbitrate the controversy exists, unless it determines that: [¶] (a) The right to compel arbitration has been waived by the petitioner; ...”

Further, “Waiver of a contractual right to arbitration is ordinarily a question of fact and determination of this question, if supported by substantial evidence, is binding on an appellate court. [Citation.] Under the general rule this question is left to the trial court where there is substantial evidence to support it. However, in cases where the record before the trial court establishes a lack of waiver as a matter of law, the appellate court may reverse a finding of waiver made by the trial court. [Citation.]” (Doers v. Golden Gate Bridge etc. Dist. (1979) 23 Cal.3d 180, 185 [151 Cal.Rptr. 837, 588 P.2d 1261].)

*418 In the instant case the construction contract provided that “All claims, disputes, and other matters in question arising out of, or relating to, this Contract . . . except for claims which have been waived by the making or acceptance of final payment as provided by Subparagraphs 9.7.5 and 9.7.6 . . . shall be decided by arbitration. ...” Subparagraph 9.7.5 of that agreement provided that the “making of final payment shall constitute a waiver of all claims by the Owner except those arising from . . . faulty or defective work appearing after Substantial Completion. ...”

The issue is therefore whether the defects complained of were apparent before payment was made (in which case they were waived), or whether they only became so after payment (in which case they were not waived). The trial court, in its statement of decision, found that such defects “were apparent to petitioners upon reasonable inspection and were in fact known to them.” Therefore, the issue on appeal, put slightly differently, is whether substantial evidence appears in the record to support such a finding. We are convinced that it does.

Such evidence centers upon the role of Jerry Graves, the full-time construction quality auditor retained by appellants to monitor construction of the winery roof, as set forth in declarations provided by the architect, the project engineer, and the job coordinator for the roofing subcontractor, as well as in Graves’ own letter to the architect and an internal report in which he described his activities on the project.

These declarations and exhibits reveal Graves to have been a contractor himself for many years with substantial experience overseeing the construction of built-up roofing systems and with considerable expertise in proper roofing practices. He was closely familiar with the plans and specifications for the winery’s roof and, when changes or revisions to them were considered, he was a regular participant in such discussions. On a daily basis, he observed and inspected the methods by which the insulation and roofing materials were applied, devoting approximately 50 “man days” to this task. He regularly devoted substantial time to watching the work and examining and testing the resultant product. He frequently made comments or suggestions concerning the procedures and techniques employed. On one occasion he determined that the type of insulation that was applied to the roof did not bond properly; as a result, work was suspended and the inadequate material was removed from a large portion of the roof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tang v. NBBJ CA2/2
California Court of Appeal, 2014
Brisbane Lodging, L.P. v. Webcor Builders, Inc.
216 Cal. App. 4th 1249 (California Court of Appeal, 2013)
Mills v. Forestex Co.
134 Cal. Rptr. 2d 273 (California Court of Appeal, 2003)
Nash v. MacDonald
112 Cal. Rptr. 2d 230 (California Court of Appeal, 2001)
Geertz v. Ausonio
4 Cal. App. 4th 1363 (California Court of Appeal, 1992)
Winston Square Homeowner's Ass'n v. Centex West, Inc.
213 Cal. App. 3d 282 (California Court of Appeal, 1989)
David Co. v. Jim W. Miller Construction, Inc.
428 N.W.2d 590 (Court of Appeals of Minnesota, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
154 Cal. App. 3d 413, 201 Cal. Rptr. 242, 1984 Cal. App. LEXIS 1896, Counsel Stack Legal Research, https://law.counselstack.com/opinion/renown-inc-v-hensel-phelps-construction-co-calctapp-1984.