Power Construction Company, LLC v. Michels Corporation

2020 IL App (1st) 200084-U
Appellate Court of Illinois·Decided October 30, 2020·No. 1-20-0084·Unpublished

Opinion

2020 IL App (1st) 200084-U

SIXTH DIVISION

October 30, 2020

No. 1-20-0084

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT

POWER CONSTRUCTION COMPANY, LLC, and ) STEADFAST INSURANCE COMPANY, ) Appeal from the ) Circuit Court of

Plaintiffs-Appellees, ) Cook County.

)

v. ) No. 19 L 10874 )

MICHELS CORPORATION, ) Honorable ) Patrick J. Sherlock, Defendant-Appellant. ) Judge Presiding.

PRESIDING JUSTICE MIKVA delivered the judgment of the court.

Justices Harris and Griffin concurred in the judgment.

ORDER

¶1 Held: The judgment of the circuit court confirming the arbitration award in favor of plaintiff is affirmed where defendant failed to establish a gross error on the face of the award.

¶2 In this challenge to an arbitration award resolving construction litigation, Power Construction Company, LLC, the general contractor for a multistory apartment building in Chicago’s River North neighborhood, and its insurer, Steadfast Insurance Company (collectively Power), sued Michels Corporation (Michels), the subcontractor in charge of installing caissons for

the project. Power alleged that Michels failed to complete its work on time, causing a four-month delay in the building’s construction, and that this delay entitled Power to damages under the parties’ contract. Pursuant to that contract, the parties submitted their dispute to binding arbitration.

¶3 The arbitrators agreed with Power that Michels had breached its contract by failing to complete its work on time and, in a 17-page decision, set out in detail their reasons for awarding Power compensatory damages, interest, fees, and costs. Concluding, however, that Michels was entitled to compensation for its completed work on the project, the arbitrators reduced the award in favor of Power from $3.7 million to $2.3 million.

¶4 Power asked the circuit court to affirm the arbitration award and enter judgment in its favor under section 5/11 of the Uniform Arbitration Act (Act) (710 ILCS 5/11 (West 2018)). Michels, in turn, moved to partially vacate the award, claiming the arbitrators exceeded their authority by committing a gross error of law that was apparent on the face of the award. Following briefing and a hearing, the circuit court confirmed the arbitration award and entered judgment for Power.

¶5 On appeal, Michels argues that this court should reverse the circuit court’s judgment and vacate the arbitrators’ award. If we find that outright reversal is not warranted, Michels argues that we should at least vacate the arbitrators’ award of attorney fees and subcontractor acceleration costs.

¶6 For the following reasons, we affirm the judgment of the circuit court.

¶7 I. BACKGROUND

¶8 In 2013, Power began construction on a 35-story residential apartment tower at 845 North State Street in Chicago (the Project). Power was the Project’s general contractor under a contract with its owner, Tower Ten Glades, LCC (Owner). Power entered into a subcontract with Michels for the installation of caissons on the Project. The subcontract consisted of two parts: a Master

Agreement, dated April 30, 2013, governing the overall business and legal relationship between Power and Michels, and a Project Specific Agreement, dated September 4, 2013, through which Power specifically retained Michels to perform the caisson installation.

¶9 The installation of caissons, which are drilled concrete piers and shafts used in the foundations of buildings, was a “critical path activity,” meaning Michels needed to complete it before the Project could proceed. Power hired Michels to install 49 caissons for which it was to be paid $1.4 million, and the parties agreed that Michels would complete its work by October 22, 2013.

¶ 10 While performing its work, however, Michels encountered unexpected obstacles, including underground boulders and hydraulic problems with its drilling rig. After various attempts to proceed despite these challenges, the Project’s geotechnical engineer and structural engineer of record designed a workaround. Instead of installing two of the larger caissons, Michels would install four smaller caissons. During installation of the four smaller caissons, however, it was discovered that the soil in that area had been overly disturbed by the attempts to remove the boulders and proceed without a full workaround. The area would require remediation through a technique called micropiling. Because micropiles of the type required had never been used in the City of Chicago, design and review of the micropiling plan took approximately a month and a half. Power sought proposals for the micropiling, and Michels submitted a bid. Though Michels submitted a lower and more inclusive bid, Power retained another subcontractor that had considerable experience in this area and a history of past work with the City. While this process was ongoing—and with its contracted-for work completed—Michels demobilized from the Project in November 2013. Overall, the issues encountered during caisson construction delayed completion of the Project by four months.

¶ 11 On August 6, 2014, Power sent Michels a letter invoking remedies under the Master Agreement for the delay, stating that the letter was “Power’s formal notice and demand for remedy as Michels ha[d] failed to meet certain performance and financial expectations.” And on June 20, 2017, Power filed a complaint against Michels in the circuit court of Cook County asserting common law claims of breach of contract, equitable subrogation, and equitable contribution.

¶ 12 Michels moved to stay the circuit court proceedings and compel arbitration under Article 14C of the Master Agreement, which provided that the parties agreed to arbitrate any disputes arising between them “in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association.” The Master Agreement also provided that the arbitrators’ award would be final and judgment could be entered upon it “in accordance with applicable law in any court of competent jurisdiction.” Power agreed to arbitrate, the circuit court action was stayed, and the matter proceeded to arbitration.

¶ 13 Central to the parties’ dispute were the following contractual provisions. First, Article 8 of the Master Agreement made clear that timely progress and completion of the Project was of the essence. That article provided:

“Time is of the essence of the Contract. Subcontractor shall begin its Work promptly following reasonable notice from General Contractor, and shall prosecute such Work diligently and in coordination and cooperation with other subcontractors and other Work on the Project, and shall, at all times, expedite its Work so as to permit the earliest completion of the Project. Subcontractor shall perform its Work in strict accordance with any progress schedule prepared and maintained by General Contractor and shall otherwise perform its work in such sequence and at such rate of progress as, in the sole judgment of General Contractor, is necessary to achieve earliest possible completion of the entire

Project with emphasis on those portions of the Project which General Contractor deems most urgent. Subcontractor further agrees that, if it delays the progress of its Work so as to cause any damage or penalty for which General Contractor shall become liable, Subcontractor shall promptly, on demand, reimburse General Contractor for any such amount.”

¶ 14 Article 9, Section B, titled “Progress Schedule,” specifically addressed subcontractor delays:

Free access — add to your briefcase to read the full text and ask questions with AI

Power Construction Company, LLC v. Michels Corporation, 2020 IL App (1st) 200084-U (Ill. Ct. App. 2020).

2020 IL App (1st) 200084-U (Power Construction Company, LLC v. Michels Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Burchell v. Marsh
58 U.S. 344 (Supreme Court, 1855)
Foutch v. O'BRYANT
459 N.E.2d 958 (Illinois Supreme Court, 1984)
American Federation of State, County & Municipal Employees v. State
529 N.E.2d 534 (Illinois Supreme Court, 1988)
Wilcox Co. v. Bouramas
392 N.E.2d 198 (Appellate Court of Illinois, 1979)
Garver v. Ferguson
389 N.E.2d 1181 (Illinois Supreme Court, 1979)
Pioneer Bank & Trust Co. v. Seiko Sporting Goods, U.S.A. Co.
540 N.E.2d 808 (Appellate Court of Illinois, 1989)
Tim Huey Corp. v. Global Boiler & Mechanical, Inc.
649 N.E.2d 1358 (Appellate Court of Illinois, 1995)
Shearson Lehman Brothers, Inc. v. Hedrich
639 N.E.2d 228 (Appellate Court of Illinois, 1994)
Herricane Graphics, Inc. v. Blinderman Construction Co.
820 N.E.2d 619 (Appellate Court of Illinois, 2004)
Rauh v. Rockford Products Corp.
574 N.E.2d 636 (Illinois Supreme Court, 1991)
Advocate Financial Group v. Poulos
2014 IL App (2d) 130670 (Appellate Court of Illinois, 2014)
Sloan Electric v. Professional Realty & Development Corp.
819 N.E.2d 37 (Appellate Court of Illinois, 2004)
Pennymac Corp. v. Jenkins
2018 IL App (1st) 171191 (Appellate Court of Illinois, 2018)
Merritt v. Merritt
11 Ill. 565 (Illinois Supreme Court, 1850)
Darst v. Collier
86 Ill. 96 (Illinois Supreme Court, 1877)