Power Construction Company, LLC v. Michels Corporation

2020 IL App (1st) 200084-U
CourtAppellate Court of Illinois
DecidedOctober 30, 2020
Docket1-20-0084
StatusUnpublished

This text of 2020 IL App (1st) 200084-U (Power Construction Company, LLC v. Michels Corporation) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Power Construction Company, LLC v. Michels Corporation, 2020 IL App (1st) 200084-U (Ill. Ct. App. 2020).

Opinion

2020 IL App (1st) 200084-U

SIXTH DIVISION October 30, 2020

No. 1-20-0084

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1).

IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT

POWER CONSTRUCTION COMPANY, LLC, and ) STEADFAST INSURANCE COMPANY, ) Appeal from the ) Circuit Court of Plaintiffs-Appellees, ) Cook County. ) v. ) No. 19 L 10874 ) MICHELS CORPORATION, ) Honorable ) Patrick J. Sherlock, Defendant-Appellant. ) Judge Presiding.

PRESIDING JUSTICE MIKVA delivered the judgment of the court. Justices Harris and Griffin concurred in the judgment.

ORDER ¶1 Held: The judgment of the circuit court confirming the arbitration award in favor of plaintiff is affirmed where defendant failed to establish a gross error on the face of the award.

¶2 In this challenge to an arbitration award resolving construction litigation, Power

Construction Company, LLC, the general contractor for a multistory apartment building in

Chicago’s River North neighborhood, and its insurer, Steadfast Insurance Company (collectively

Power), sued Michels Corporation (Michels), the subcontractor in charge of installing caissons for No. 1-20-0084

the project. Power alleged that Michels failed to complete its work on time, causing a four-month

delay in the building’s construction, and that this delay entitled Power to damages under the

parties’ contract. Pursuant to that contract, the parties submitted their dispute to binding arbitration.

¶3 The arbitrators agreed with Power that Michels had breached its contract by failing to

complete its work on time and, in a 17-page decision, set out in detail their reasons for awarding

Power compensatory damages, interest, fees, and costs. Concluding, however, that Michels was

entitled to compensation for its completed work on the project, the arbitrators reduced the award

in favor of Power from $3.7 million to $2.3 million.

¶4 Power asked the circuit court to affirm the arbitration award and enter judgment in its favor

under section 5/11 of the Uniform Arbitration Act (Act) (710 ILCS 5/11 (West 2018)). Michels,

in turn, moved to partially vacate the award, claiming the arbitrators exceeded their authority by

committing a gross error of law that was apparent on the face of the award. Following briefing and

a hearing, the circuit court confirmed the arbitration award and entered judgment for Power.

¶5 On appeal, Michels argues that this court should reverse the circuit court’s judgment and

vacate the arbitrators’ award. If we find that outright reversal is not warranted, Michels argues that

we should at least vacate the arbitrators’ award of attorney fees and subcontractor acceleration

costs.

¶6 For the following reasons, we affirm the judgment of the circuit court.

¶7 I. BACKGROUND

¶8 In 2013, Power began construction on a 35-story residential apartment tower at 845 North

State Street in Chicago (the Project). Power was the Project’s general contractor under a contract

with its owner, Tower Ten Glades, LCC (Owner). Power entered into a subcontract with Michels

for the installation of caissons on the Project. The subcontract consisted of two parts: a Master

2 No. 1-20-0084

Agreement, dated April 30, 2013, governing the overall business and legal relationship between

Power and Michels, and a Project Specific Agreement, dated September 4, 2013, through which

Power specifically retained Michels to perform the caisson installation.

¶9 The installation of caissons, which are drilled concrete piers and shafts used in the

foundations of buildings, was a “critical path activity,” meaning Michels needed to complete it

before the Project could proceed. Power hired Michels to install 49 caissons for which it was to be

paid $1.4 million, and the parties agreed that Michels would complete its work by October 22,

2013.

¶ 10 While performing its work, however, Michels encountered unexpected obstacles, including

underground boulders and hydraulic problems with its drilling rig. After various attempts to

proceed despite these challenges, the Project’s geotechnical engineer and structural engineer of

record designed a workaround. Instead of installing two of the larger caissons, Michels would

install four smaller caissons. During installation of the four smaller caissons, however, it was

discovered that the soil in that area had been overly disturbed by the attempts to remove the

boulders and proceed without a full workaround. The area would require remediation through a

technique called micropiling. Because micropiles of the type required had never been used in the

City of Chicago, design and review of the micropiling plan took approximately a month and a half.

Power sought proposals for the micropiling, and Michels submitted a bid. Though Michels

submitted a lower and more inclusive bid, Power retained another subcontractor that had

considerable experience in this area and a history of past work with the City. While this process

was ongoing—and with its contracted-for work completed—Michels demobilized from the Project

in November 2013. Overall, the issues encountered during caisson construction delayed

completion of the Project by four months.

3 No. 1-20-0084

¶ 11 On August 6, 2014, Power sent Michels a letter invoking remedies under the Master

Agreement for the delay, stating that the letter was “Power’s formal notice and demand for remedy

as Michels ha[d] failed to meet certain performance and financial expectations.” And on June 20,

2017, Power filed a complaint against Michels in the circuit court of Cook County asserting

common law claims of breach of contract, equitable subrogation, and equitable contribution.

¶ 12 Michels moved to stay the circuit court proceedings and compel arbitration under Article

14C of the Master Agreement, which provided that the parties agreed to arbitrate any disputes

arising between them “in accordance with the Construction Industry Arbitration Rules of the

American Arbitration Association.” The Master Agreement also provided that the arbitrators’

award would be final and judgment could be entered upon it “in accordance with applicable law

in any court of competent jurisdiction.” Power agreed to arbitrate, the circuit court action was

stayed, and the matter proceeded to arbitration.

¶ 13 Central to the parties’ dispute were the following contractual provisions. First, Article 8 of

the Master Agreement made clear that timely progress and completion of the Project was of the

essence. That article provided:

“Time is of the essence of the Contract. Subcontractor shall begin its Work promptly

following reasonable notice from General Contractor, and shall prosecute such Work

diligently and in coordination and cooperation with other subcontractors and other Work

on the Project, and shall, at all times, expedite its Work so as to permit the earliest

completion of the Project. Subcontractor shall perform its Work in strict accordance with

any progress schedule prepared and maintained by General Contractor and shall otherwise

perform its work in such sequence and at such rate of progress as, in the sole judgment of

General Contractor, is necessary to achieve earliest possible completion of the entire

4 No. 1-20-0084

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burchell v. Marsh
58 U.S. 344 (Supreme Court, 1855)
Foutch v. O'BRYANT
459 N.E.2d 958 (Illinois Supreme Court, 1984)
American Federation of State, County & Municipal Employees v. State
529 N.E.2d 534 (Illinois Supreme Court, 1988)
Wilcox Co. v. Bouramas
392 N.E.2d 198 (Appellate Court of Illinois, 1979)
Garver v. Ferguson
389 N.E.2d 1181 (Illinois Supreme Court, 1979)
Pioneer Bank & Trust Co. v. Seiko Sporting Goods, U.S.A. Co.
540 N.E.2d 808 (Appellate Court of Illinois, 1989)
Tim Huey Corp. v. Global Boiler & Mechanical, Inc.
649 N.E.2d 1358 (Appellate Court of Illinois, 1995)
Shearson Lehman Brothers, Inc. v. Hedrich
639 N.E.2d 228 (Appellate Court of Illinois, 1994)
Herricane Graphics, Inc. v. Blinderman Construction Co.
820 N.E.2d 619 (Appellate Court of Illinois, 2004)
Rauh v. Rockford Products Corp.
574 N.E.2d 636 (Illinois Supreme Court, 1991)
Advocate Financial Group v. Poulos
2014 IL App (2d) 130670 (Appellate Court of Illinois, 2014)
Sloan Electric v. Professional Realty & Development Corp.
819 N.E.2d 37 (Appellate Court of Illinois, 2004)
Pennymac Corp. v. Jenkins
2018 IL App (1st) 171191 (Appellate Court of Illinois, 2018)
Merritt v. Merritt
11 Ill. 565 (Illinois Supreme Court, 1850)
Darst v. Collier
86 Ill. 96 (Illinois Supreme Court, 1877)

Cite This Page — Counsel Stack

Bluebook (online)
2020 IL App (1st) 200084-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/power-construction-company-llc-v-michels-corporation-illappct-2020.