Herricane Graphics, Inc. v. Blinderman Construction Co.

CourtAppellate Court of Illinois
DecidedDecember 13, 2004
Docket2-04-0125 Rel
StatusPublished

This text of Herricane Graphics, Inc. v. Blinderman Construction Co. (Herricane Graphics, Inc. v. Blinderman Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herricane Graphics, Inc. v. Blinderman Construction Co., (Ill. Ct. App. 2004).

Opinion

No. 2--04--0125

______________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT

______________________________________________________________________________

HERRICANE GRAPHICS, INC., ) Appeal from the Circuit Court

) of DeKalb County.

Plaintiff-Appellee and )

Cross-Appellant, )

)

v. ) No. 02--LM--558

BLINDERMAN CONSTRUCTION )

COMPANY, INC., )

) Honorable

Defendant-Appellant and ) Kurt P. Klein,

Cross-Appellee. ) Judge, Presiding.

______________________________________________________________________________

JUSTICE BYRNE delivered the opinion of the court:

Defendant, Blinderman Construction Company, Inc., appeals the judgment of the circuit court of DeKalb County denying its motion to confirm an arbitration award in its favor and granting the motion of plaintiff , Herricane Graphics, Inc., to vacate the award and enter judgment in its favor in the amount of $47,163 .  Defendant contends that the trial court exceeded its authority in vacating the arbitrator's decision. Plaintiff cross-appeals the trial court's failure to award plaintiff interest under the State Prompt Payment Act (Payment Act) (30 ILCS 540/0.01 et seq. (2002)) and the court's failure to compensate plaintiff for the labor-related component of its work.   We reverse the trial court's judgment and confirm the arbitrator's award.

FACTS

Plaintiff and defendant entered into contract negotiations for plaintiff to furnish and install signs for defendant at a construction project at Northern Illinois University (NIU).  Defendant was to be the general contractor for the project, and plaintiff was to be the subcontractor.

On July 7, 1998, defendant faxed plaintiff the initial draft of its subcontract agreement.  Plaintiff acknowledged receipt of the contract and agreed to the terms by letter dated July 9, 1998.  However, plaintiff never sent defendant a signed version of the contract or any subsequent contract.   The initial contract contained several terms of importance to the proceedings:  an arbitration clause and two clauses regarding certified payrolls.  The arbitration clause provided, in relevant part, that any controversy or claim arising out of or relating to the subcontract, or breach thereof, was to be settled by arbitration.   The clauses regarding certified payrolls provided , in relevant part:

"Payment will be made once each month equal to 90% of the value of the work satisfactorily completed as received from the Owner.  Written request for payment must be in the hands of the Contractor not later than the 1st of each month covering work satisfactorily completed during the previous month, in a form as required by the Contractor.  ***  The Subcontractor shall furnish to the Contractor a breakdown of costs of said Subcontract, showing monetary value of each item of labor and material, in accordance with terms of the General Contract, and in a form acceptable to the Contractor.

* * *

Compliance with Applicable Laws[.]  ***  Subcontractor will submit required compliance reports, including weekly certified payrolls as required by federal law."

T he parties modified the contract terms between the time defendant sent plaintiff the initial proposal and August 25, 1998.  However, defendant alleged that the arbitration and payroll terms were never revised, amended, or excluded.  During the contract modification period, plaintiff commenced installation of the signs.  A significant portion of the work was fully performed prior to receipt of the August 25, 1998, contract modification.  Plaintiff points out that this contract contains a rider entitled "Instructions For Subcontractors," which provides the following instruction regarding payroll certification and Equal Employment Opportunity reporting requirements:

"You are advised that the Owner has a right to order funds withheld from payments equal to the amount of the labor expended in the event that these records are not completed."  (Emphasis added.)

By letters dated September 9, 1998, November 16, 1998, and March 22, 1999, defendant acknowledged to plaintiff that the owner ,NIU, had approved all of plaintiff 's work and had paid defendant for that work .  Plaintiff alleged that approximately 90% of that work, or $47,163, represented the selling price of hardware and other goods that plaintiff had installed at the jobsite.  Plaintiff alleged that the balance, $5,240, represented the labor component of plaintiff 's work.

Plaintiff believed that its performance was based on a bid contract that was accepted by defendant, and plaintiff objected to the execution of the August 25, 1998, contract because it did not contain the correct scope of work.  Plaintiff acknowledged that defendant was withholding the funds that defendant

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burchell v. Marsh
58 U.S. 344 (Supreme Court, 1855)
Thomas v. Leyva
659 N.E.2d 24 (Appellate Court of Illinois, 1995)
City National Bank v. Langley
514 N.E.2d 508 (Appellate Court of Illinois, 1987)
Lee B. Stern & Co. v. Zimmerman
660 N.E.2d 170 (Appellate Court of Illinois, 1995)
Edward Electric Co. v. Automation, Inc.
593 N.E.2d 833 (Appellate Court of Illinois, 1992)
Gordon v. Bauer
532 N.E.2d 855 (Appellate Court of Illinois, 1988)
Canteen Corp. v. Former Foods, Inc.
606 N.E.2d 174 (Appellate Court of Illinois, 1992)
Perkins Restaurants Operating Co. v. Van Den Bergh Foods Co.
657 N.E.2d 1085 (Appellate Court of Illinois, 1995)
Everen Securities, Inc. v. A.G. Edwards & Sons, Inc.
719 N.E.2d 312 (Appellate Court of Illinois, 1999)
Roubik v. Merrill Lynch, Pierce, Fenner & Smith, Inc.
692 N.E.2d 1167 (Illinois Supreme Court, 1998)
Hawrelak v. Marine Bank
735 N.E.2d 1066 (Appellate Court of Illinois, 2000)
Garver v. Ferguson
389 N.E.2d 1181 (Illinois Supreme Court, 1979)
Tim Huey Corp. v. Global Boiler & Mechanical, Inc.
649 N.E.2d 1358 (Appellate Court of Illinois, 1995)
Cook County v. American Federation of State, County & Municipal Employees
691 N.E.2d 777 (Appellate Court of Illinois, 1998)
Rauh v. Rockford Products Corp.
574 N.E.2d 636 (Illinois Supreme Court, 1991)
Prather v. McGrady
634 N.E.2d 299 (Appellate Court of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Herricane Graphics, Inc. v. Blinderman Construction Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/herricane-graphics-inc-v-blinderman-construction-c-illappct-2004.