No. 2--04--0125
______________________________________________________________________________
IN THE
APPELLATE COURT OF ILLINOIS
SECOND DISTRICT
______________________________________________________________________________
HERRICANE GRAPHICS, INC., ) Appeal from the Circuit Court
) of DeKalb County.
Plaintiff-Appellee and )
Cross-Appellant, )
)
v. ) No. 02--LM--558
BLINDERMAN CONSTRUCTION )
COMPANY, INC., )
) Honorable
Defendant-Appellant and ) Kurt P. Klein,
Cross-Appellee. ) Judge, Presiding.
______________________________________________________________________________
JUSTICE BYRNE delivered the opinion of the court:
Defendant, Blinderman Construction Company, Inc., appeals
the
judgment of
the
circuit court of DeKalb County denying its motion to confirm an arbitration award in its favor
and granting
the
motion of
plaintiff
, Herricane Graphics, Inc.,
to vacate
the
award and enter judgment in its
favor
in the
amount of $47,163
. Defendant contends that
the
trial court exceeded its authority in vacating
the
arbitrator's decision.
Plaintiff cross-appeals
the
trial court's failure to award
plaintiff
interest under
the
State Prompt Payment Act (Payment Act) (30 ILCS 540/0.01
et
seq.
(2002))
and
the
court's failure to compensate
plaintiff
for
the
labor-related component of its work.
We reverse
the
trial court's judgment
and confirm
the
arbitrator's award.
FACTS
Plaintiff and
defendant
entered into contract negotiations for
plaintiff
to furnish and install signs for
defendant
at a construction project at Northern Illinois University (NIU). Defendant was
to be the
general contractor for
the
project, and
plaintiff
was to be
the
subcontractor.
On July 7, 1998,
defendant
faxed
plaintiff
the
initial draft of its subcontract agreement. Plaintiff acknowledged receipt of
the
contract and agreed to
the
terms by letter dated July 9, 1998. However,
plaintiff
never sent
defendant
a signed version of
the
contract or any subsequent contract.
The initial contract contained several terms of importance to
the
proceedings: an arbitration clause and two clauses regarding certified payrolls. The arbitration clause provided, in relevant part, that any controversy or claim arising out of or relating to
the
subcontract, or breach thereof, was to be settled by arbitration.
The clauses regarding certified payrolls provided
, in relevant part:
"Payment will be made once each month equal to 90% of
the
value of
the
work satisfactorily completed as received from
the
Owner. Written request for payment must be in
the
hands of
the
Contractor not later than
the
1st of each month covering work satisfactorily completed during
the
previous month, in a form as required by
the
Contractor. *** The Subcontractor shall furnish to
the
Contractor a breakdown of costs of said Subcontract, showing monetary value of each item of labor and material, in accordance with terms of
the
General Contract, and in a
form acceptable to
the
Contractor.
* * *
Compliance with Applicable Laws[.] *** Subcontractor will submit required compliance reports, including weekly certified payrolls as required by federal law."
T
he
parties modified
the
contract terms between
the
time
defendant
sent
plaintiff
the
initial proposal and August 25, 1998. However,
defendant
alleged that
the arbitration and payroll terms were never revised, amended, or excluded. During the contract modification period,
plaintiff
commenced
installation of
the
signs. A significant portion of
the
work was fully performed prior to receipt of
the
August 25, 1998, contract modification. Plaintiff points out that this contract contains a rider entitled "Instructions For Subcontractors," which provides
the
following
instruction regarding payroll certification and Equal Employment Opportunity reporting requirements:
"You are advised that
the
Owner has a right to order funds withheld from payments equal to
the
amount of
the
labor
expended in
the
event that these records are not completed." (Emphasis added.)
By letters dated September 9, 1998, November 16, 1998, and March 22, 1999,
defendant
acknowledged to
plaintiff
that
the
owner ,NIU, had approved all of
plaintiff
's work and had paid
defendant for that work
. Plaintiff alleged that approximately 90% of that work, or $47,163, represented
the
selling price of hardware and other goods that
plaintiff
had installed at
the
jobsite. Plaintiff alleged that
the
balance, $5,240, represented
the
labor component of
plaintiff
's work.
Plaintiff believed that its performance was based on a bid contract that was accepted by
defendant,
and
plaintiff
objected to
the
execution of
the
August 25, 1998, contract because it did not contain
the
correct scope of work. Plaintiff acknowledged that
defendant
was withholding
the
funds
that defendant
had received from NIU until
defendant
received a certified payroll from
plaintiff
. Plaintiff also acknowledged that
the
execution of
the
contract was a condition of payment
.
Defendant alleged that, during
plaintiff
's performance of
the
contract,
defendant
repeatedly attempted to obtain certified payrolls from
plaintiff
. Defendant also alleged that it repeatedly advised
plaintiff
that payment would be issued only
upon receipt of those certified payrolls. However,
plaintiff
never delivered certified payrolls to
defendant
. As a result,
defendant
refused to pay
plaintiff
.
In December 2002, four years after
the
project was completed,
plaintiff
sued
defendant
for,
inter
alia
, breach of contract to recover
for the
work it performed and
the
material it expended on
the
project. Defendant subsequently filed a motion requesting
the
trial court to stay
the
suit pending arbitration. The trial court granted
defendant
's motion and
the
matter was submitted to arbitration.
The arbitrator entered an award in
defendant
's favor, finding that
the
submission of certified payrolls was a condition of payment and
the
failure to provide
the
certified payrolls prevented
plaintiff
's recovery of any money for either wages or material expended under
the
contract. Neither
plaintiff
nor
defendant
supplied this court with a record of
the
arbitration hearing or
the
memorandum of decision. We note that
the
materials used by
plaintiff
for
the
project constituted 90% of
the
total amount requested for reimbursement.
On September 8, 2003,
defendant
filed a motion with
the
trial court to confirm
the
arbitration award and enter judgment
in
it
s favor. Thereafter,
plaintiff
filed a motion objecting to
the
confirmation of
the
award. Plaintiff sought to vacate
the
award under section 12(a)(3) of
the
Uniform Arbitration Act (Arbitration
Act)
(710 ILCS 5/12(a)(3) (West 2002)), or in
the
alternative, to modify
the
award pursuant to section 13 of
the
Arbitration
Act (710 ILCS 5/13 (West 2002)).
On January 29, 2004,
the
trial court denied
defendant
's motion to confirm
the
award, and granted
plaintiff
's motion to vacate
the
award. The trial court noted in its order that it specifically disagreed with
the
arbitrator's decision with respect to
the
materials furnished on
the
project and found that
the
value of
the
materials furnished by
plaintiff
to
defendant
on
the
construction project was 90% of
the
total amount of
plaintiff
's claim.
Accordingly,
the
trial court entered judgment in
plaintiff
's favor in
the
amount of $47,163, representing 90% of
$52,403 sought by
plaintiff
.
Defendant
timely appeals, contending that
the
trial court exceeded its authority in vacating
the
arbitrator's decision. Plaintiff timely cross-appeals, contending that
the
trial court erroneously failed to award
plaintiff
interest under
the
Payment Act and failed to compensate
plaintiff
for
the
labor-related component of its work.
ANALYSIS
It is well settled that a court's review of an arbitrator's award is extremely limited (
American Federation of State, County & Municipal Employees
v. The Department of Central Management Services
, 173 Ill. 2d 299, 304 (1996)), in fact, more limited than appellate review of a trial court's decision.
Cook County v. American Federation of State, County & Municipal Employees, District Counsel 31, Local 3315
, 294
Ill. App. 3d
985, 988 (1998). Because
the
parties have agreed to have their dispute settled by an arbitrator, it is
the
arbitrator's view that
the
parties have agreed to accept, and
the
court should not overrule an award simply because its interpretation differs from that of
the
arbitrator.
Everen Securities, Inc. v. A.G. Edwards & Sons, Inc.
, 308
Ill. App. 3d
268, 273 (1999).
Furthermore, there is a presumption that
the
arbitrator did not exceed his authority.
Tim Huey Corp. v. Global Boiler & Mechanical Inc.
, 272
Ill. App. 3d
100, 106 (1995).
Thus, a court must construe an award, if possible, so as to uphold its validity.
Everen Securities
,
308
Ill. App. 3d
at 273. A court has no power to determine
the
merits of
the
award simply because it strongly disagrees with
the
arbitrator's contract interpretation.
Canteen Corp. v. Former Foods, Inc.
, 238
Ill. App. 3d
167, 179 (1992). Also, a court cannot overturn an award
on
the
ground that it is illogical or inconsistent.
Perkins Restaurants Operating Co., L.P. v. Van Den Bergh Foods Co.
, 276
Ill. App. 3d
305, 309 (1995). In fact, an arbitrator's award will not even be set aside because of errors in judgment or a mistake of law or fact.
Roubik v. Merrill Lynch, Pierce, Fenner & Smith, Inc.
,
181
Ill. 2d
373, 381 (1998).
The limited circumstances under which we may modify or vacate an arbitration award are set forth in
the
Arbitration
Act (710 ILCS 5/1
et
seq.
(West 2002)). Section 13(a) of
the
Arbitration
Act (710 ILCS 5/13(a) (West 2002)) allows a court to modify or correct an award where: (1) there was an evident miscalculation or an error in a description; (2)
the
arbitrators ruled on a matter not submitted to them, and
the
court is able to correct
the
award without affecting
the
merits of
the
decision upon
the
issues submitted; or (3)
the
award is imperfect in form.
Under section 12(a) of
the
Arbitration
Act (710 ILCS 12(a) (West 2002)), a court can vacate an award in
the
following circumstances: (1) the award was obtained by corruption or fraud; (2)
the
arbitrator was partial; (3)
the
arbitrator
exceeded his powers; (4)
the
arbitrator
unreasonably refused to postpone
the
hearing or hear material evidence; or (5) there was no arbitration agreement.
Although a court cannot vacate an award due to errors in judgment or mistakes of fact or law, a court can vacate an arbitration award where a gross error of law or fact appears on
the
award's face, or where
the
award fails to dispose of all matters properly submitted to
the
arbitrator.
Edward Electric Co. v. Automation, Inc.
, 229
Ill. App. 3d
89, 97-98 (1992).
To vacate an award based on a gross error of law, a reviewing court must be able to conclude, from
the
award's face, that
the
arbitrator was so mistaken as to
the
law that, if apprised of
the
mistake, he would have ruled differently.
Lee B. Stern & Co. v. Zimmerman
, 277
Ill. App. 3d
423, 428 (1995). The burden is placed on
the
challenger to prove by clear and convincing evidence that an award was improper
.
Thomas v. Leyva
, 276
Ill. App. 3d
652, 654 (1995).
On appeal,
defendant
contends that
the
trial court erred in vacating
the
arbitrator's decision. Specifically, defendant asserts that by invading
the
province of
the
arbitrator and substituting its own construction of
the
contract and interpretation of
the
facts
,
the
court failed to apply
the
proper standard of review
. Plaintiff counters that
the
rider to
the
August 25 contract
expressly provides that
defendant
has a right to withhold payments equal to
the
amount of
labor
expended but not
material used, and that the contract cannot be reasonably interpreted to cover amounts beyond labor expended. Plaintiff contends that
the
arbitrator exceeded his jurisdiction in interpreting
the
contract to find that
plaintiff
was not entitled to any
funds expended
.
Therefore,
plaintiff
argues that the
trial court correctly vacated
the
award
. We review
the
trial court's ruling
de
novo
, as only
the
trial court's legal conclusions are at issue.
Hawrelak v. Marine Bank, Springfield
, 316
Ill. App. 3d
175, 179 (2000).
We find that
the
trial court did not have
the
authority to vacate
the
award under section 12(a)(3) of
the
Arbitration Act. In determining
the
proper standard to be applied in construing
section 12(a)(3) of
the
Arbitration
Act,
we have looked to
the
explanation of
the
chairman of
the
committee that drafted
the
Arbitration Act, which Illinois adopted in 1961:
" '[
T]he question for
the
court is whether
the
construction of
the
contract made by
the
arbitrator is a reasonably possible one that can seriously be made in
the
context in which
the
contract was made.
Stated affirmatively, if all fair and reasonable minds would agree that
the
construction of
the
contract made by
the
arbitrator was not possible under a fair interpretation of
the
contract, then
the
court would be bound to vacate or refuse to confirm
the
award.' "
Rauh v. Rockford Products Corp.
, 143
Ill. 2d
377, 391-92 (1991), quoting
M. Pirsig,
Some Comments on Arbitration Legislation and
the
Uniform Act
, 10 Vand. L. Rev. 685, 706 (1957).
Although
the
trial court disagreed with
the
arbitrator's decision, we see no principled way for
the
trial court to inject itself into this case. While
the
record does not include a transcript of
the
arbitration hearing or the memorandum of decision, it is clear that the arbitrator heard
the
testimony, assessed
the
credibility of
the
witnesses, and considered
the
exhibits and evidence presented. The arbitrator then determined whether
the
July or August contract controlled, and which terms applied.
There is no indication that
the
arbitrator acted in bad faith, was guilty of fraud, or chose not to follow
the
law. Perhaps
the
arbitrator concluded that
the
"Instructions for Subcontractor" provision ultimately was waived by
the
parties and, thus, the relevant payroll provisions could be read in such a manner as to sustain the arbitrator's interpretation.
Perhaps
the
arbitrator believed that
the
parties, by their actions, interpreted
the
payment and payroll provisions as expecting
full
payment to be issued only upon receipt of certified payrolls.
We find that
the
arbitrator's interpretation of
the
parties' contract is potentially reasonable in light of
the
context of
the
contract.
Even if, as
plaintiff
asserts,
the
arbitrator misinterpreted
the
instruction provision regarding deducting only labor and not materials,
the
court's interpretation fails to meet
the
test in
Garver v. Ferguson
, 76
Ill. 2d
1 (1979), for vacating an award. Gross errors in judgment or gross mistakes of law or fact are not grounds for vacating an award unless
the
errors are apparent upon
the
face of
the
award.
Garver
, 76
Ill. 2d
at 7-8.
Further,
the
parties bargained for
the
arbitrator's interpretation of
the
ir final agreement, and a court must not impose its own view.
As
the
Garver
court succinctly quoted:
" 'Arbitrators are judges chosen by the parties to decide the matters submitted to them, finally and without appeal. As a mode of settling disputes it should receive every encouragement from courts of equity. If the award is within the submission, and contains the honest decision of the arbitrators, after a full and fair hearing of the parties, a court of equity will not set it aside for error either in law or fact.
A contrary course would be a substitution of
the
judgment of
the
Chancellor in place of
the
judges chosen by
the
parties, and would make an award
the
commencement, not
the
end, of
the
litigation.' "
Garver
, 76
Ill. 2d
at 9, quoting
Burchell v. Marsh
, 58 U.S. (17 How.)
344, 349, 15 L. Ed. 96, 99 (1854).
See also
Hawrelak
, 316
Ill. App. 3d
at 181 ("Once parties bargain to submit their disputes to
the
arbitration system (a system essentially structured without due process, rules of procedure, rules of evidence, or any appellate procedure), we are disinclined to save them from themselves").
Since we do not find any gross errors in judgment or gross mistakes of law or fact on the face of the award, and for the other reasons stated above, we find no grounds for vacating the arbitrator's award.
Accordingly,
the
arbitrator in this case did not exceed his authority and
the
trial court erred in vacating his decision. As such,
the
award should be reinstated.
In
plaintiff
's cross-appeal, it contends that
the
trial court erred in failing to award
plaintiff
interest under
the
Payment Act
and
in failing to compensate
plaintiff
for
the
labor-related component of its work. We note that
plaintiff
first raised the issue that it was entitled to interest under
the
Payment
Act
in its motion to
the
trial court to vacate or modify
the
arbitrator's award
. However, after
the
trial court issued its opinion vacating
the
arbitrator's award,
plaintiff
never requested
the
trial court to render an opinion regarding whether
plaintiff
was entitled to interest under
the
Payment
Act. The party filing a motion has the responsibility to bring it to the trial court's attention.
Prather v. McGrady
, 261 Ill. App. 3d 880, 885 (1994), citing
Gordon v. Bauer
, 177 Ill. App. 3d 1073, 1085 (1988). Unless circumstances indicate otherwise, where no ruling appears to have been made on a motion, the presumption is that the motion was waived or abandoned.
Prather
, 261 Ill. App. 3d at 885, citing
City National Bank v. Langley
, 161 Ill. App. 3d 266, 274 (1987).
Even without waiver, we reject
both of plaintiff
's arguments on cross-appeal. Section 7 of
the
Payment
Act provides that if a contractor, without reasonable cause, fails to make any payment to his subcontractor within 15 days after receipt of payment under
a
public construction contract,
the
contractor shall pay to his subcontractor, in addition to
the
payment due, interest in
the
amount of 2% per month. 30 ILCS 540/7 (West 2002). The arbitrator held that
defendant
withheld payment because
plaintiff
materially breached
the
contract, and therefore,
the
contractor had reasonable cause to withhold payment. Because
defendant
withheld payment for reasonable cause,
plaintiff
has no basis for recovery under
section 7 of the
Payment
Act.
Similarly, because
the
arbitrator found that
plaintiff
's breach of
the
contract did not entitle it to any recovery,
plaintiff
has no basis to argue that
the
trial court erred in failing to award it
the
labor-related component of its work.
Accordingly, based on the foregoing, the judgment of the circuit court of DeKalb County is reversed and
the
arbitrator's decision is reinstated and confirmed.
Reversed.
KAPALA and GILLERAN JOHNSON, JJ., concur.