Dominion Marble Co. Ex Rel. Scott v. Morrow

100 A. 292, 130 Md. 255, 1917 Md. LEXIS 121
CourtCourt of Appeals of Maryland
DecidedJanuary 31, 1917
StatusPublished
Cited by22 cases

This text of 100 A. 292 (Dominion Marble Co. Ex Rel. Scott v. Morrow) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dominion Marble Co. Ex Rel. Scott v. Morrow, 100 A. 292, 130 Md. 255, 1917 Md. LEXIS 121 (Md. 1917).

Opinion

Burke, J.,

delivered the opinion of the Court.

Caldwell and Drake, a building firm, entered into a contract with the Youngstown Hotel Company to erect and complete an eight-story and basement hotel building in the City of Youngstown, Ohio. The contractors entered into an agreement with the Dominion Marble Company to furnish and complete the marble work for the hotel in accordance with the plans and specifications of the architects, Clinton and Russell, for the sum of twenty .thousand dollars. The eleventh clause of this subcontract is here transcribed: “In view of the fact that the Contractors are under obligation to perform their work with promptness and dispatch and to that end have organized and are maintaining a large staff of salaried employees, valuable machinery and equipment, at a large daily expense, and are devoting their own time, which is of great value, to the enterprise of which this contract forms a part, and delay in completing the work herein undertaken *257 will entail large financial loss, it is recognized and fully understood that delay on tbe part of tbe sub-contractor will be expensive and burdensome, and in order to protect tbe contractors from such known burden and expense it is agreed that if the work herein undertaken shall not be completed on or before December 1st, 1912, the sub-contractor will, as part compensation, for such loss, pay to the contractors the sum of fifty dollars ($50.00) per day as liquidated damages only and not as a penalty, for each and every day thereafter that said work shall remain in, an incompleted condition and such amount as shall accrue hereunder shall at once become due and payable. It, is further recognized that an early completion of the work of the contractors will save them valuable time, and the daily expense of the force organized to carry forward the common enterprise and the completion of the work undertaken by the sub-contractor herein will enure to his financial benefit in consequence,- it is therefore1 agreed that the contractor will pay the sub-contractor, should he complete his part of the work before the first day of December, 1912, and the subcontractor shall receive from the contractors the sum of fifty dollars ($50) per day for every day intervening between such date of actual completion of his part of the work, as certified to by the architects, and tbe datei provided for completion as heretofore stated.” The general contractors, Caldwell and' Drake, assigned all their interest in the contract to Morrow Brothers, the appellees, with the assent and approbation of the subcontractors tbe Dominion Marble Company.

A suit was instituted on July 15th, 1915, in the Superior Court of Baltimore City, against Morrow Brothers to recover for the marble work done in tbe construction of the hotel under the sub-contract and for certain other charges. The amount claimed to he due!, as shown by the account filed with the declaration, was $15,638.28. The general issue and special pleas were filed, and by appropriate pleadings the case was brought to iss-uo. An agreement was entered into to *258 submit the-matters in dispute to arbitration. This agreement recited that: “The parties to the above suit being; desirous to end the same by arbitration, do hereby agree and oblige themselves to submit the same, and -all matters in controversy therein, to the award of Clyde N. Eriz and Josias Pennington together with a third arbitrator, to be first selected by the two arbitrators herein named, who shall decide matters of difference only, and the award and decision of the said arbitrators, or a majority of them, shall be final and binding; and the parties further, agree that this submission shall be made a rule of said Court agreeably to- the provisions of Article 75 * of the Annotated Code of Maryland relating to arbitration' and award; so that the said award shall be made and set down in writing under the hands and seals- of the said arbitrators or of any two of them, and shall be returned to the* clerk of this 'Court on or before March 7th, 1916, to the end that the Court may give judgment on the award in accordance with the provisions of said article. Upon any question of law as to which the arbitrators may desire to be informed or -advised, the said arbitrators are to be permitted to receive the instructions of the presiding judge of this Court. The arbitrators shall administer the usual oath to all witnesses and a stenographer shall take down the testimony.” Provision was made for the conduct of the 'arbitration, the place of holding the sessions of the arbitrators and for the payment of the costs of the proceeding of the arbitration. On .February 5th, 1916, the Court ordered “that the matters in controversy in the above entitled cause be and they are hereby referred under the rule of the Court and by agreement to Clyde N. Friz and Josias Pennington, as arbitrators-, under the terms of the above agreement.” The arbitrators, for the reasons presently to be stated, selected J. Henry Miller as third arbitrator to act in accordance with the terms of the agreement. On the 27th of March, 1916, Messrs. Pennington and Miller filed in Court the following award:

*259 “In pursuance of tbe submission herein mentioned, we, the arbitrators, having taken upon ourselves the burden of said arbitration, and after due notice to the parties, having met on the eighth day of February, the second day of March, and other dates, and having-heard and duly considered the allegations and proofs of the parties, submitted to us by them, respectively, do award that there is due from the defendants to the plaintiff the sum of one hundred and forty-eight and 12/100 dollars ($148,121.
“Witness our hands and seals the twenty-second day of March, 1916.
“Josias Pennington. (Seal)
“J. Henry Miller. (Seal)
“.............. (Seal).”

Mr. E'riz disagreed with the finding' of the other arbitrators and did not sign the: award, but under thei terms: of the submission his signature was not essential to its validity. The plaintiff filed exceptions to the award and moved the Court to set it aside. Nine reasons were assigned for setting aside the award. The Court overruled the exceptions and entered judgment upon the award in favor of the plaintiff and from this action of the Court the plaintiff has brought this appeal. Some of the grounds of the exceptions have been abandoned, and the whole ease of the appellant may be¡ considered under the second ground of exception, viz: “Because the said Josias Pennington undertook to act for and represent the defendants, and altogether failed to exercise judicial and impartial consideration of the issues raised in this case.” There is no dispute as to the law applicable to the case. It is said in 2 Am. & Eng. Ency. of Law 638: “If there be sufficient reason for imputing fraud, corruption or misconduct to the arbitrator, his award will be set aside. An arbitrator’s first duty is to act uprightly and impartially between the parties. But mere suspicion of misconduct will not justify the Court in interfering to set aside the award. An arbitrator is the agent of both parties, and when there are more arbitrators *260

Free access — add to your briefcase to read the full text and ask questions with AI

Related

P.G. Co. v. Police Civilian Emp.
Court of Special Appeals of Maryland, 2014
Prince George's County v. Prince George's County Police Civilian Employees Ass'n
98 A.3d 1094 (Court of Special Appeals of Maryland, 2014)
Downey v. Sharp
51 A.3d 573 (Court of Appeals of Maryland, 2012)
Brendsel v. WINCHESTER CONSTRUCTION CO., INC.
898 A.2d 472 (Court of Appeals of Maryland, 2006)
Baltimore County v. Mayor of Baltimore
621 A.2d 864 (Court of Appeals of Maryland, 1993)
Board of Education v. Prince George's County Educators' Ass'n
522 A.2d 931 (Court of Appeals of Maryland, 1987)
Bd. of Educ. v. PG CO. EDUCATORS'ASS'N
522 A.2d 931 (Court of Appeals of Maryland, 1987)
Amalgamated Transit Union, Division 1300 v. Mass Transit Administration
504 A.2d 1132 (Court of Appeals of Maryland, 1986)
Foley Co. v. Grindsted Products, Inc.
662 P.2d 1254 (Supreme Court of Kansas, 1983)
Litton Bionetics, Inc. v. Glen Construction Co.
437 A.2d 208 (Court of Appeals of Maryland, 1981)
Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc.
320 A.2d 558 (Court of Special Appeals of Maryland, 1974)
Chillum-Adelphi Volunteer Fire Department, Inc. v. Button & Goode, Inc.
219 A.2d 801 (Court of Appeals of Maryland, 1966)
Nelley v. Mayor of Baltimore
166 A.2d 234 (Court of Appeals of Maryland, 1960)
Parr Construction Co. v. Pomer
144 A.2d 69 (Court of Appeals of Maryland, 1958)
Schreiber v. Pacific Coast Fire Insurance
75 A.2d 108 (Court of Appeals of Maryland, 1950)
Continental Milling & Feed Co. v. Doughnut Corp. of America
48 A.2d 447 (Court of Appeals of Maryland, 1946)
Pumphrey v. Pumphrey
191 A. 235 (Court of Appeals of Maryland, 1937)
O'Ferrall v. De Luxe Sign Co.
149 A. 290 (Court of Appeals of Maryland, 1930)
McDonald v. Real Estate Board, Baltimore
142 A. 261 (Court of Appeals of Maryland, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
100 A. 292, 130 Md. 255, 1917 Md. LEXIS 121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dominion-marble-co-ex-rel-scott-v-morrow-md-1917.