Foley Co. v. Grindsted Products, Inc.

662 P.2d 1254, 233 Kan. 339, 1983 Kan. LEXIS 310
CourtSupreme Court of Kansas
DecidedApril 29, 1983
Docket54,594
StatusPublished
Cited by10 cases

This text of 662 P.2d 1254 (Foley Co. v. Grindsted Products, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foley Co. v. Grindsted Products, Inc., 662 P.2d 1254, 233 Kan. 339, 1983 Kan. LEXIS 310 (kan 1983).

Opinion

The opinion of the court was delivered by

McFarland, J.:

This is a dispute between plaintiff subcontractor, Foley Company, and defendant general contractor, Niro Atomizer, Inc., concerning the confirmation of an arbitration award by the district court. Defendant Niro appeals from the judgment of the district court confirming and refusing to vacate the arbitration award entered in favor of plaintiff Foley.

Niro entered into a general construction contract with defendant Grindsted Products, Inc. (which is not a party to this appeal), whereby Niro was to construct a chemical processing facility on premises located in Olathe, Johnson County, Kansas, and leased to Grindsted by defendant Johnson County Airport Commission (also not a party to this appeal). Subsequently on July 5, 1979, Niro entered into a subcontract with Foley whereby Foley was to perform various piping and pipeline portions of the general *340 contract. Foley completed performance of the subcontract on June 9, 1980. Foley then billed Niro for $437,386.85. Niro refused to pay the same and on August 29, 1980, Foley filed a mechanic’s lien statement on the premises. On October 2, 1980, in Johnson County District Court, this action was commenced by Foley to foreclose the mechanic’s lien.

On November 18, 1980, Niro filed its motion to stay the mechanic’s lien foreclosure action and to compel arbitration of the dispute pursuant to article XII of the contract which provides:

“XII. ARBITRATION:
“The Contractor and the Subcontractor agree to attempt to resolve by negotiation any controversy or claim arising out of or relating to this Subcontract or any alleged breach thereof or default thereunder; however, if any such dispute cannot be resolved by negotiation, then such controversy or claim shall be settled by arbitration. Each of the parties shall designate an arbitrator, and the arbitrators so designated shall in turn select a third. The ruling of a majority of such arbitrators will be binding upon all parties. If the parties agree, the dispute may be submitted to an arbitrator mutually agreeable to both parties. Any arbitrator shall be selected from those individuals having expertise in the area of dispute. Such arbitrator shall be required to agree that he will keep confidential any information furnished by the parties hereto which qualifies as confidential information under the terms of this Subcontract. The rules and regulations of the American Arbitration Association shall govern, except to the extent that the arbitrators designated hereunder by a majority decision, shall determine otherwise. In the event the parties cannot agree upon arbitrators, as herein provided, then such arbitration shall be had pursuant to the rules and regulations of the American Arbitration Association. Any judgment or award rendered pursuant to arbitration as herein provided shall be final and binding in all respects upon the parties. It is expressly agreed by the parties that the arbitrators shall apply to each dispute the law of the State of Maryland, and the party not requesting arbitration shall choose the forum where arbitration will occur.”

On February 26, 1981, the district court granted Niro’s motion for a stay and ordered the controversy be submitted to arbitration, the forum thereof to be chosen by Foley in accordance with the contractual agreement of the parties. Foley selected Kansas City, Missouri, as the arbitration hearing site.

Foley and Niro each selected an arbitrator and the two men, so-designated, agreed upon who should serve as the neutral third arbitrator. All three arbitrators were knowledgeable in the area of mechanical construction involved in the dispute. On August 31 and September 1, 1981, the arbitrators held their arbitration *341 hearing wherein Foley and Niro presented their evidence. The arbitrators met again on September 22, 1981, to consider the evidence and unanimously agreed Foley should be awarded $247,980 plus predecision interest of $44,233 and post-decision interest on the total arbitration award from September 1, 1981, at the rate of 1 lh% per month until the award was satisfied. The award was formalized and entered on October 16, 1981, at which time Mr. Gardner, the arbitrator chosen by Niro, declined to join therein.

On November 6, 1981, Foley sought confirmation of the arbitration award in the original Johnson County District Court action herein. Niro sought vacation of the award. On February 23,1982, the district court refused to vacate the arbitration award and confirmed the same. Niro appeals from said judgment.

Before proceeding to the issues one preliminary matter warrants attention. The arbitration article (article XII) in the contract herein specifies “the arbitrators shall apply to each dispute the law of the State of Maryland.” Further, subsection C of article XIII of the contract provides: “This Subcontract shall be interpreted and governed by the laws of the State of Maryland.” The arbitration clause further provides: “The rules and regulations of the American Arbitration Association shall govern . . . .” A literal reading of these three cited contractual provisions could well be interpreted to mean the law of Maryland is to be applied by the arbitrators in determining the merits of the controversy, and the arbitration procedures themselves are to be governed by the AAA rules. However, throughout this proceeding the parties have interpreted the “law of the State of Maryland” provision in the arbitration clause to encompass the entire arbitration proceeding, including confirmation and vacation of the arbitration award, with the AAA rules supplemental thereto. Inasmuch as this is the contract construction agreed upon by the parties, this court will proceed on that basis in determining the issues in this case.

Both Maryland and Kansas have adopted the Uniform Arbitration Act. Md. Cts. & Jud. Proc. Code Ann. § 3-201 et seq. (T980), K.S.A. 5-401 et seq. The Maryland and Kansas statutory arbitration provisions applicable here are predominately the same, though variations in the format of the Act as published by the two states complicate cross-citations. We have concluded it would be *342 of value to this opinion to cite the relevant Kansas sections of the Act with cross-citations to the comparable portions of the Maryland law.

The primary statute with which we are involved is K.S.A. 5-412 (Md. Cts. & Jud. Proc. Code Ann. § 3-224 [1980]), which provides:

“(a) Upon application of a party, the court shall vacate an award where:'
“(1) The award was procured by corruption, fraud or other undue means;
“(2) There was evident partiality by an arbitrator appointed as a neutral or corruption in any of the arbitrators or misconduct prejudicing the rights of any party;
“(3) The arbitrators exceeded their powers;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heartland Surgical Specialty Hospital, LLC v. Reed
287 P.3d 933 (Court of Appeals of Kansas, 2012)
Neighbors Construction Co. v. Woodland Park at Soldier Creek, LLC
284 P.3d 1057 (Court of Appeals of Kansas, 2012)
Alexander v. Everhart
7 P.3d 1282 (Court of Appeals of Kansas, 2000)
Professional Builders, Inc. v. Sedan Floral, Inc.
819 P.2d 1254 (Court of Appeals of Kansas, 1991)
City of Lenexa v. C. L. Fairley Construction Co.
805 P.2d 507 (Court of Appeals of Kansas, 1991)
Alphagraphics Franchising, Inc. v. Reeder
776 P.2d 805 (Court of Appeals of Arizona, 1989)
State Ex Rel. Hooten Construction Co. v. Borsberry Construction Co.
769 P.2d 726 (New Mexico Supreme Court, 1989)
Thomas J. Davis, Inc. v. Micronesian Hotel Corp.
2 N. Mar. I. Commw. 198 (Northern Mariana Islands, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
662 P.2d 1254, 233 Kan. 339, 1983 Kan. LEXIS 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foley-co-v-grindsted-products-inc-kan-1983.