City of Lenexa v. C. L. Fairley Construction Co.

805 P.2d 507, 15 Kan. App. 2d 207, 1991 Kan. App. LEXIS 47
CourtCourt of Appeals of Kansas
DecidedFebruary 1, 1991
Docket65,231
StatusPublished
Cited by5 cases

This text of 805 P.2d 507 (City of Lenexa v. C. L. Fairley Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Lenexa v. C. L. Fairley Construction Co., 805 P.2d 507, 15 Kan. App. 2d 207, 1991 Kan. App. LEXIS 47 (kanctapp 1991).

Opinion

Elliott, J.:

C.L. Fairley Construction Company, Inc., (Fairley) appeals from a district court order vacating an arbitration award in Fairley’s favor. We reverse.

*208 In June 1984, Fairley entered into a construction contract with the City of Lenexa. The contract contained three provisions relevant to this appeal. First, under paragraph 9.9 of the contract, an independent project engineer was the interpreter of contract requirements and the judge of performance. All claims, disputes, or other matters relating to the performance of the contract were to be referred to the project engineer for decision. Second, paragraph 9.10 stated that either Lenexa or Fairley could demand arbitration of any claim or dispute that had been submitted to the project engineer. The demand had to be made within 30 days of the project engineer’s written decision on the dispute or claim, and the failure to demand arbitration within this 30-day period resulted in the project engineer’s decision being final and binding on Fairley and Lenexa. Third, paragraph 14.16 of the contract stated that acceptance of final payment by Fairley would constitute a waiver of all claims by Fairley against Lenexa “other than those previously made in writing and still unsettled.”

During the course of the project, a dispute arose concerning $9,000 in liquidated damages and $4,268.16 in back charges. Fairley, Lenexa, and the project engineer exchanged a series of letters concerning the correct amount of Fairley’s final payment. Fairley and Lenexa disagree over which of these letters properly submitted the dispute to the project engineer and which represented the project engineer’s final decision. Lenexa also contends that Fairley waived all claims except the $13,268.16 originally in dispute by acceptance of final payment.

Fairley filed a demand for arbitration with the American Arbitration Association, seeking recovery of liquidated damages, improper back charges, and increased costs due to delays. The day after arbitration began, Lenexa filed a petition to stay the proceedings pursuant to K.S.A. 5-402. Lenexa alleged that the claims were not the subject of an arbitration agreement between the parties, were not timely filed, and were not previously decided by the project engineer as required by the contract. The district court denied the petition, but preserved Lenexa’s right to appeal those issues Lenexa claimed were not subject to arbitration and directed the arbitrator to “consider the liquidated damages issues separately from the non-liquidated damage issues.”

*209 The arbitrator awarded Fairley $21,434.53 in damages, ordered Lenexa to pay all costs and fees, and stated simply that “[t]his award is in full settlement of all claims and counterclaims submitted to this arbitration.” Lenexa filed a motion for clarification of the award, which the arbitrator denied.

Fairley filed a motion for confirmation of the award. The district court denied the motion, finding that the arbitration agreement in the contract was nonbinding. Fairley appealed, and we reversed in case No. 62,002, an unpublished opinion filed October 28, 1988. On review, the Supreme Court affirmed the judgment of the Court of Appeals and remanded the case to the district court. City of Lenexa v. C.L. Fairley Construction Company, Inc., 245 Kan. 316, 777 P.2d 851 (1989).

On remand, the district court found that Fairley waived all claims except $13,268.16 for delays and costs when it accepted final payment. The court further found that Fairley’s demand for arbitration was not filed within 30 days of the project engineer’s final decision on the dispute. Accordingly, the court found “it abundantly clear that the arbitrator chose to ignore the contractual provisions agreed upon by the parties, or, in the alternative, the arbitrator construed the contract provisions in a manner totally and absolutely inconsistent with a plain reading of the contract provisions.” Finding these errors were jurisdictional in nature, the court concluded that the “arbitrator exceeded his powers by considering matters not properly submitted to him for determination.” Since the arbitrator made no specific findings, the court found the award could not be modified and thus vacated the entire award pursuant to K.S.A. 5-412.

The sole issue before this court is whether the arbitrator exceeded his powers.

Arbitration agreements are enforced under the Kansas version of the Uniform Arbitration Act. K.S.A. 5-401 et seq. This act provides that the court may vacate an award in five specific circumstances, including where the arbitrator exceeded his powers. K.S.A. 5-412(a)(3).

The district court’s scope of review is quite limited. An award is presumed valid unless one of the specific grounds in K.S.A. 5-412(a) is proven. “Nothing in the award relating to the merits of the controversy, even though incorrectly decided, is grounds *210 for setting aside the award in the absence of fraud, misconduct, or other valid objections.” Jackson Trak Group, Inc. v. Mid States Port Authority, 242 Kan. 683, 689, 751 P.2d 122 (1988). The court may not consider evidence presented to the arbitrators, and an award will not be revised unless it is “tainted or based on an irrational interpretation of the contract.” Jackson Trak Group, Inc., 242 Kan. at 689.

On remand, the district court reviewed the documentary evidence and found that Fairley did not follow the time and notice procedures set forth in the contract for bringing a claim to arbitration. While the district court’s interpretation of the relevant contract provisions apparently conflicted with that of the arbitrator, this is irrelevant if the subject matter of the decision was properly within the domain of the arbitrator. “ ‘The general rule is that errors of law and fact, or an erroneous decision of matters submitted to the judgment of the arbitrators, are insuflicient to invalidate an award fairly and honestly made.’ ” Rural Water Dist. No. 6 v. Ziegler Corp., 9 Kan. App. 2d 305, 308, 677 P.2d 573, rev. denied 235 Kan. 1042 (1984).

Although Kansas case law has not specifically addressed the issue, case law from other jurisdictions indicates that procedural matters such as time and notice provisions are properly before the arbitrator. In Denhardt v. Trailways, Inc., 767 F.2d 687 (10th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neighbors Construction Co. v. Woodland Park at Soldier Creek, LLC
284 P.3d 1057 (Court of Appeals of Kansas, 2012)
Griffith v. McGovern
141 P.3d 516 (Court of Appeals of Kansas, 2006)
City of Lubbock v. Hancock
940 S.W.2d 123 (Court of Appeals of Texas, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
805 P.2d 507, 15 Kan. App. 2d 207, 1991 Kan. App. LEXIS 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-lenexa-v-c-l-fairley-construction-co-kanctapp-1991.