Triple "A" MacHine Shop, Inc., a Corporation v. United States

235 F.2d 626, 1956 U.S. App. LEXIS 4708
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 25, 1956
Docket20-35002
StatusPublished
Cited by2 cases

This text of 235 F.2d 626 (Triple "A" MacHine Shop, Inc., a Corporation v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triple "A" MacHine Shop, Inc., a Corporation v. United States, 235 F.2d 626, 1956 U.S. App. LEXIS 4708 (9th Cir. 1956).

Opinion

JAMES M. CARTER, District Judge.

The ease grows out of a government contract for the repair and reconditioning of five life boats. It was agreed at the trial that the reasonable value of the labor and materials for which recovery was sought, was $6040.00. The question is whether the labor and materials were supplied as part of the contract price, or whether they were extras for which recovery may be had.

A master contract was entered into on February 10, 1950, between the United States, acting through the Military Sea Transport Service, Pacific (hereafter Sea Transport), the Triple “A” Machine Shop, Inc., libelant below and other contractors. This contract did not provide for the work in question but for the so *627 licitation by Sea Transport of bids for work and services, and upon acceptance, the performing of the work under job orders issued by the contracting officer.

About September 20, 1950, Specification M.S.T.S.P. No. 51-64 was issued by Sea Transport for work on five life boats and on September 21, 1950, by Invitation to Bid No. P 51-36, Sea Transport solicited bids from parties to the master contract. The Invitation to Bid advised bidders of the location of the life boats and their availability for inspection, and that the specification which accompanied the invitation would become part of the job order upon issuance thereof.

The specifications provided, “It is the intent of these specifications to provide for the complete repair and reconditioning, both mechanically and structurally, of five (5) life boats, all as necessary to place the boats in first class operating condition and ready for use. The work shall include, but shall not be limited to, any detailed specifications which follow.”

The specifications, in addition to the general clause above quoted, contained a listing of only “Category A” items. 1 No category B or C appeared. However, in the specifications was the clause, “Replacements of deteriorated tanks shall be accomplished only on a written field order.” This, all parties agree, referred to extra work and in fact a change order was later issued and Triple “A” was paid an additional $9,490 for this work. This item is not in dispute.

To continue with the chain of events, Triple “A” on September 29, 1950, made its bid, apparently on a legal form supplied with the Invitation to Bid. The substance of the bid follows:

“The undersigned Triple ‘A’ * * * offers and agrees if this bid be accepted * * * to accept a Job order issued under a master contract from M.S.T.S. —19 (1-50) and to furnish any and all the items of supplies or services described on the reverse side of this bid at the price set opposite each item * * * ” [Emphasis supplied]

The reverse side contained

Under the Category A section, Triple “A” placed its bid of $3775.00 as total price.

On October 2, 1950, Sea Transport issued its Job order No. 10 which provided in part:

“1. Work: The contractor shall furnish the supplies and service required to perform the work described in the attached plans and specifications made a part hereof and designated as follows: Repairs to five (5) life boats, specification No. M.S.T.S.P. 51-64.” 2
“2. Price........$3,775.00.” Below appears “Accepted. Date: October 11, 1950. Triple ‘A’ Machine Shop, Inc. (contractor) by /&/ A. Engel, Pres.”

Triple “A” commenced its work under the contract and thereafter an inspector from Sea Transport determined that certain work was necessary to make the boats seaworthy. On October 16, 1950, Triple “A” was directed to furnish certain materials and labor to accomplish the repair and reconditioning of the boats *628 and was advised that the Contracting Officer considered the above work to be fully covered in the specifications No. M.S.T.S.P. 51-64, and that no additional payment would be made for the work. This work was described as “renewing all bands for securing tanks; renew 12 shell plates and 1 shell doubler chafing plate; renew two sockets for propelling units; renew inboard margin boards on 4 life boats; renew all floors in 4 life boats; renew 2 thwarts.”

The major portion of this work, in dollar terms, involved the shell plates, approximately 298 sq. ft. for which in the libel filed there was originally claimed $3600 and the renewing of the floors in 4 life boats for which there was claimed $1000.

Triple “A” advised Sea Transport that it expected extra compensation for the above work, but was informally advised by the Contracting Officer that the matter was considered to be fully covered by the specifications and job order and no additional compensation would be paid. The contract provided both in Art. 5 and Art. 14, discussed hereafter, that the contractor should in any event “proceed diligently with the performance” of the work. Triple “A” proceeded with the work under written protest and wifjp. notice to the Contracting Officer it would require payment for the reasonable value of the additional work and materials.

On November 2, in response to written demand for further compensation for the work ordered, the Contracting Officer made a formal determination that the specifications and job order required Triple “A” to do the work necessary to completely repair and recondition the life boats, and that the work and materials were not extra, but were within the terms of the contract, and denied the claim for additional payment. This was communicated to Triple “A”.

Triple “A” appealed the Contracting Officer’s decision to the Commander M.S.T.S., Washington, D. C., the appeal being taken pursuant to both Articles 5(j) and 14 of the Master Contract. 3 The dispute was referred by the Commander M.S.T.S. to the Contract Advisory Board for decision. That Board determined that the dispute concerned a question arising out of the interpretation of plans and specifications and therefore came within Art. 5(j) of the Master Contract. The Board held that the specifications and job order fully covered all work and services required of Triple “A” and that there was accordingly no right to extra compensation.

Triple “A” then filed its libel below. Triple “A” has been paid the contract price of $3775.00 and the $9490.00 provided for in change order No. 1. It claims $6040.00 additional as extras. The United States contends this work and labor was within the contract price. The case was tried on the merits and decree entered in favor of the United States.

Triple “A” states in its brief, “The case raised only one question of law to be determined by the Court, namely, what constituted the contract of the parties? It is obvious that Libelant would not be entitled to judgment for the reasonable value of the above listed repairs if, under its contract, Libelant was bound to furnish said extra repairs without any additional compensation therefor.”

Triple “A” argues the question of offer and acceptance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George R. Hoffmann v. United States
276 F.2d 199 (Tenth Circuit, 1960)
United States v. F. C. Hathaway
242 F.2d 897 (Ninth Circuit, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
235 F.2d 626, 1956 U.S. App. LEXIS 4708, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triple-a-machine-shop-inc-a-corporation-v-united-states-ca9-1956.