WISCONSIN AVIATION FOUR LAKES, INC. v. Berryman

2004 WI App 167, 686 N.W.2d 455, 276 Wis. 2d 308, 2004 Wisc. App. LEXIS 565
CourtCourt of Appeals of Wisconsin
DecidedJuly 8, 2004
Docket03-1029
StatusPublished

This text of 2004 WI App 167 (WISCONSIN AVIATION FOUR LAKES, INC. v. Berryman) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WISCONSIN AVIATION FOUR LAKES, INC. v. Berryman, 2004 WI App 167, 686 N.W.2d 455, 276 Wis. 2d 308, 2004 Wisc. App. LEXIS 565 (Wis. Ct. App. 2004).

Opinion

Wisconsin Aviation Four Lakes, Inc., Plaintiff-Appellant,
v.
Frank W. Berryman, Defendant-Respondent.

No. 03-1029.

Court of Appeals of Wisconsin.

Opinion Filed: July 8, 2004.

Before Deininger, P.J., Vergeront and Higginbotham, JJ.

¶ 1 DEININGER, P.J.

Wisconsin Aviation Four Lakes, Inc. appeals an order that dismissed its claim against Frank Berryman for payment of a bill for aircraft inspection and related services it rendered to Berryman. The trial court disallowed Wisconsin Aviation's claim because it found that an estimate for repair work that followed the inspection was "not worth the money that is charged." Wisconsin Aviation claims the trial court erred in dismissing its claim for the inspection and related services it performed because Berryman was contractually bound to pay for the work it actually performed, notwithstanding the alleged unreasonableness of its estimate for additional work on Berryman's airplane. We agree and reverse the appealed order in part. We direct that, on remand, judgment be entered against Berryman in the amount of $561.68, plus allowable costs.

BACKGROUND

¶ 2 Berryman owns an airplane that he stored with Wisconsin Aviation. After about two years of outside storage, Berryman asked Wisconsin Aviation to perform an "annual inspection" of the plane, as is apparently required by the Federal Aviation Administration in order for a plane to be certified for flight. Berryman also asked Wisconsin Aviation to remove the seats from the aircraft. Wisconsin Aviation began the inspection of the plane, performed routine maintenance on the engine in order to start it as required for the inspection, and removed its seats.

¶ 3 A Wisconsin Aviation employee testified that, after beginning the annual inspection and finding numerous problems with the aircraft that would require repairs, he stopped the inspection. A maintenance manager prepared an estimate of the cost of repairing the plane. He then met with Berryman and went over the estimate with him, discussing the problems found and the action required or recommended to repair each problem. The total amount of the estimate was $18,624.79. After receiving the estimate, Berryman told Wisconsin Aviation to stop all work on the plane while he considered his options, explaining that he would give further instructions regarding the plane in the future.

¶ 4 Berryman then contacted two other aircraft repair facilities who provided estimates for repairing the plane so that it could be certified to fly. He hired one of them, Seagull Aviation, to do the necessary work. Seagull Aviation estimated that it would cost $2,639.00 to complete an annual inspection and repair Berryman's plane. Most of the minor repairs identified by Wisconsin Aviation were performed by Seagull, but Seagull's service manager did not feel that four major repairs cited by Wisconsin Aviation were necessary. (Seagull ultimately billed Berryman more than $17,000 for all work it performed on his plane, most of which was for cosmetic and other improvements approved by Berryman that were not included in either Wisconsin Aviation's or Seagull's repair estimates.)

¶ 5 Wisconsin Aviation billed Berryman $385 for the partial inspection (8.75 hours @ $44 per hour), $77 for the work in getting the engine started (1.75 hours), and $70.40 for removing the seats (1.6 hours), plus sales tax, for a total invoice of $561.68. Berryman did not pay, and Wisconsin Aviation sued him in small claims court for $904.17.[1] Berryman counterclaimed, requesting damages in excess of $5,000 for intentional misrepresentation, negligent performance of inspection, and breach of contract. Because the counterclaim exceeded the small claims jurisdictional limit, the case ultimately proceeded to a bench trial before the Dane County Circuit Court.

¶ 6 The vast majority of the trial testimony, exhibits, and argument focused on Berryman's counterclaims and whether Wisconsin Aviation had or had not correctly identified four major repair items allegedly needed to render the plane airworthy. Berryman acknowledged that he had requested Wisconsin Aviation to remove the seats and conduct the inspection, and that he knew that the inspection would involve getting the plane's engine started. His counsel argued, however, that Berryman should not have to pay for the work that was done because of Wisconsin Aviation's intentional or negligent inclusion in the repair estimate of the four major items that Berryman maintained were not required to be done, which he asserted to be "70% of the ... estimate."[2]

¶ 7 In an oral ruling following post-trial briefing, the trial court first determined that there "just isn't enough evidence for me to find that there is some sort of an intentional fraudulent misrepresentation on the part of Wisconsin Aviation." It reached a similar conclusion regarding Wisconsin Aviation's alleged negligence in preparing the estimate of repairs. The court found, however, that the estimate was unreasonably high in that "a lot less than that [$18,000] would have gotten the job done," and concluded that "I just can't find that on an implied breach of contract claim that the estimate was worth the $900 [see footnote 1] that is being charged here," explaining further:

[G]iven what work actually needed to be done and the number of big dollar things that apparently if they might have been advisable they certainly weren't necessary, and the implication of the estimate is that they were necessary, I find that that estimate was not worth the money that is charged, and I decline to enforce the plaintiff's demand for $904.17.

¶ 8 Based on these findings and conclusions, the court dismissed Wisconsin Aviation's claim against Berryman, as well as Berryman's counterclaims. Both parties moved for reconsideration, which the court denied. Wisconsin Aviation appeals the order denying reconsideration of the dismissal of its claim.[3]

ANALYSIS

¶ 9 As we have described, Berryman concedes that the invoiced work was performed at his request, and he raises no issue as to the reasonableness of Wisconsin Aviation's charges for commencing the inspection, starting the plane's engine and removing its seats. He argues, however, that Wisconsin Aviation did not "substantially perform" the annual inspection he requested because an annual inspection encompasses not only inspection services, but the making of necessary repairs and "certification for a return to service." He also maintains that the court correctly found that the Wisconsin Aviation repair estimate was grossly inflated, and therefore properly concluded that Wisconsin Aviation had not substantially performed its contract with him.

¶ 10 Wisconsin Aviation, of course, takes issue with the court's findings regarding the excessiveness of its repair estimate, but more to the point, argues that the accuracy of the estimate is irrelevant to the issue of whether it is entitled to be paid for the services performed at Berryman's request. Wisconsin Aviation maintains that its estimate was merely a "recommendation" of work it believed needed to be done in order for the plane to safely return to the air, which Berryman was free to reject, as ultimately he did. It points out that Berryman testified at trial that he told Wisconsin Aviation to "stop all work" on the plane and that he did not "want to spend any more money" on the plane while he considered his "options." In Wisconsin Aviation's view, the fact that Berryman rejected the repair work it recommended and found a competitor willing to do fewer repairs and certify the plane for flight does not justify Berryman's nonpayment for the inspection and other services he requested the company to perform on his plane.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kreyer v. Driscoll
159 N.W.2d 680 (Wisconsin Supreme Court, 1968)
Hartford Elevator, Inc. v. Lauer
289 N.W.2d 280 (Wisconsin Supreme Court, 1980)
Plante v. Jacobs
103 N.W.2d 296 (Wisconsin Supreme Court, 1960)
State v. Darcy N. K.
581 N.W.2d 567 (Court of Appeals of Wisconsin, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
2004 WI App 167, 686 N.W.2d 455, 276 Wis. 2d 308, 2004 Wisc. App. LEXIS 565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-aviation-four-lakes-inc-v-berryman-wisctapp-2004.