Hawkins v. Teeples and Thatcher, Inc.

515 P.2d 927, 267 Or. 151, 1973 Ore. LEXIS 283
CourtOregon Supreme Court
DecidedNovember 15, 1973
StatusPublished
Cited by16 cases

This text of 515 P.2d 927 (Hawkins v. Teeples and Thatcher, Inc.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hawkins v. Teeples and Thatcher, Inc., 515 P.2d 927, 267 Or. 151, 1973 Ore. LEXIS 283 (Or. 1973).

Opinions

TONGUE, J.

This is an action by a subcontractor against a general contractor for breach of a contract on a construction job, with a counterclaim by the general contractor against the subcontractor for breach of the same contract. The case was tried before the court, without a jury. The trial court found for plaintiffs on their complaint in the sum of $6,636.27- — -the full amount prayed for — and then found for the defendant on its counterclaim in the sum of $11,501.19. The court then entered judgment in favor of defendant and against plaintiffs for the difference, in the sum of $4,864.92. Plaintiffs appeal.

The facts.

Defendant was the general contractor for the construction of a sewage treatment plant for the City of North Bend. Because of the low elevation and the high water table of the plant site and the need for the “excavation hole” to be dry, defendant entered into a subcontract with plaintiffs to “dewater” the plant site. This was to be accomplished by “jetting” into the ground a series of 70 vertical “well point” pipes in a pattern on all four sides of the plant site and then connecting the tops of such pipes to a horizontal “header pipe,” to be connected with a pump. The subcontract, on a printed form provided by defendant, and dated July 23, 1971, had no fixed date for completion of the “dewatering” operation, but specified a fixed [154]*154contract price of $6,686 and included the following provisions, as Article IX:

“Should the SUBCONTEACTOE, in any respect, fail to prosecute the work with promptness and diligence, or fail to carry on the work in the manner provided in this contract, the CONTEACTOE shall be at liberty, after two (2) days notice to thé SUBCONTEACTOE to remedy such defects or breach, to declare the contract to be in default, and to take over the completion of the work contracted for, and, in that event, the SUBCONTEACTOE shall not be entitled to receive any further payment until the said work be wholly finished,, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred in finishing this work, such excess shall be paid to the SUBCONTEACTOE, but if such expense shall exceed such unpaid balance, the SUBCONTEACTOE SHALL PAT THE DIFFEEENCE TO THE CONTEACTOE.”

On July 26, 1971, defendant “authorized” plaintiffs to start work “immediately.” Plaintiffs then “jetted in” the “well points,” connected the “header pipe” and started pumping on August 15, 1971. The next day, according to the plaintiffs, the water level was dropping in a satisfactory manner and they informed defendant that it could move in equipment and start excavation.

According to defendant’s witnesses, however, plaintiffs’ pumps did not discharge any significant amount of water and it was evident that plaintiffs’ “dewatering” system was not and could not “dewater” the excavation area in a satisfactory manner.

On the morning of August 16, 1971, after plaintiffs had been pumping for some 12 hours, defendant delivered a written note to plaintiffs stating that if the system “is not in full operational condition by the end [155]*155of the work day, today, Aug. 16, 1971, they will have to declare you as being unable to fulfill your subcontract agreement with them” and that, in such an event, defendant would take over the work and charge plaintiffs with any resulting costs. Plaintiffs admitted that “they had told us they wanted us to do it as fast as we could and they said that they wanted us to get started immediately, and they asked us two or three times why we hadn’t.” They testified, however, that this was the first “complaint,” at least about the manner in which the work was being done or one that charged the system as installed by them with being defective in any way.

The next morning, on August 17, 1971, plaintiffs were dismissed from the job. Defendant then engaged another subcontractor, who installed a similar “dewatering” system in four days, but with a different type of “well points,” packed in gravel, and with a larger “header pipe” and a different type of pump. That system operated successfully and six or seven days later defendant started its excavation. Plaintiffs’ “well points” were removed and, according to defendant’s witnesses, they were found to be clogged with sand. This was denied by plaintiffs.

The pleadings.

Plaintiffs’ complaint, after alleging the contract, alleged that plaintiffs “performed all the work required by the contract,” but that “defendant terminated plaintiffs’ work, without cause, and in violation of the contract” and breached the contract in three respects: by terminating plaintiffs’ work “without giving two days’ notice as required by Article IX,” by doing so “without causes as described in Article IX,” and by failing to pay plaintiffs as required by the contract.

[156]*156Defendant’s answer denied these allegations and alleged, as a counterclaim, that the parties entered into the contract; that defendant “has performed its obligation” under the contract, bnt “was required to declare the contract to be in default” and that:

“Hauser [sic] has breached said subcontract agreement, in that Hauser [sic] failed and refused to provide, furnish or install a well point system to provide a dry excavation hole, failed to remove such apparatus as was installed, and failed to furnish materials and installation which complied with the specifications of the agreement, all as required by the aforesaid subcontract agreement.”

Defendant then alleged that it had been damaged in the sum of $18,212 and prayed for judgment in that amount.

These allegations were denied in plaintiffs’ reply.

The findings and judgment of the trial court.

At the conclusion of the trial, the trial judge stated that:

“* * * [T]he Court finds for the plaintiffs on Plaintiffs’ Complaint on the basis, principally, that the contract, which was provided and written by the defendant, provides for a two-day notice, and that notice was not given him.
“The defendant got anxious and couldn’t wait the extra 24 hours. If the defendant had waited until the 18th before terminating him, it might have been all right, but when they jumped in there and give him notice on the 16th and then threw him off the job on the 17th they breached the contract, and it was their own contract. They were the ones that drew the contract, and on their own printed form according to their evidence.”

Next, with reference to the counterclaim, the trial judge stated:

“The counterclaim — I am afraid the Court must find in favor of the defendant there.
[157]*157“There is no question — it appears, at least, when all the evidence is in — particularly the evidence in support of the counterclaim — that there was a breach here on behalf of the plaintiffs, that the plaintiffs could not produce a working system and did not, and it is very questionable as to whether they could have had they been given an extra 24 hours. I can’t actually say whether they could or couldn’t. * * *”

The court then entered a judgment which stated that :

“The court finds in favor of plaintiffs on their complaint in the sum of $6,636.27. The court further finds for defendant on its counterclaim in the sum of $11,501.19.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fostveit v. Poplin
301 P.3d 915 (Court of Appeals of Oregon, 2013)
City of Eugene v. Monaco
17 P.3d 544 (Court of Appeals of Oregon, 2000)
Johnson Farms v. McEnroe
2000 ND 137 (North Dakota Supreme Court, 2000)
Seal Rock Water District v. City of Toledo
712 P.2d 174 (Court of Appeals of Oregon, 1986)
Ierulli v. Lutz Development Co.
698 P.2d 504 (Court of Appeals of Oregon, 1985)
Temple v. Temple
365 N.W.2d 561 (South Dakota Supreme Court, 1985)
Deering v. Erpelding Construction Co.
636 P.2d 429 (Court of Appeals of Oregon, 1981)
BW Feed Co., Inc. v. General Equipment Co.
605 P.2d 1205 (Court of Appeals of Oregon, 1980)
Smejkal v. Rice
582 P.2d 2 (Oregon Supreme Court, 1978)
Wickham v. Famco Services, Inc.
350 So. 2d 1159 (District Court of Appeal of Florida, 1977)
Helmer v. Transamerica Title Insurance
569 P.2d 10 (Oregon Supreme Court, 1977)
Montgomery v. Wadsworth Plumbing & Heating Co.
564 P.2d 703 (Oregon Supreme Court, 1977)
Hassan v. Guyer
532 P.2d 227 (Oregon Supreme Court, 1975)
Hawkins v. Teeples and Thatcher, Inc.
515 P.2d 927 (Oregon Supreme Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
515 P.2d 927, 267 Or. 151, 1973 Ore. LEXIS 283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hawkins-v-teeples-and-thatcher-inc-or-1973.