*457 BRADSHAW, J.,

Pro Tempore.

Plaintiff and defendant entered into an oral agreement whereby plaintiff was to prepare estimates of cost, overhead and profit to be used by defendant in preparing and submitting bids on projects involving installation of utility pipelines. Plaintiff was to supervise the work on projects on which defendant was the successful bidder. Plaintiff had considerable prior experience as a superintendent on installation of such utility lines and in bid preparation of such jobs. The defendant was primarily involved in a general plumbing business and desired to enter the field of utility line installation.

The parties agree in their pleadings that the following provisions were agreed upon:

“(a) MONTGOMERY would prepare bids for LAW & SONS on public and private utility construction projects and by mutual agreement, the parties would decide which jobs would be bid and the amount bid;
"(b) The bids were to be submitted by and in the name of LAW & SONS;
"(c) The bids were to be broken into certain components of labor, material and equipment at projected cost plus an amount to cover LAW & SONS’ overhead and profit;
"(d) Upon a successful bid and the letting of the contract to LAW & SONS, MONTGOMERY agreed to supervise LAW & SONS’ employees, procure necessary materials and equipment for and in the name of LAW & SONS and to complete the work as efficiently and expeditiously as possible;
"(e) Upon completion of a job, LAW & SONS was to keep that portion of the bid price allocated to overhead and profit;
"(f) MONTGOMERY was to share savings realized by LAW & SONS in the bid allocations to labor, materials and equipment.”

Plaintiff seeks to recover certain sums from defendant claimed to be plaintiffs share, pursuant to the agreement, of extraordinary profits over and above *458 costs, overhead and profit referred to as "savings on costs.” The plaintiffs claim is based upon three separate projects or jobs which defendant was successful in bidding on. These three jobs were designated 501, 502-503 and 505. Plaintiff abandoned a claim for money due on a fourth job with the Port of Portland designated job 504.

Defendant denies any money due and owing plaintiff. Defendant claims that the agreement was to allow 17 percent of gross on each job as overhead and profit. Defendant also contends that the agreement provided that plaintiff would participate equally with defendant in any losses incurred on any of the jobs. Defendant, in a cross-complaint of several causes, claims plaintiff was negligent in his bidding analysis and supervisory capacities and, as a result, the combined effect of the aforementioned four jobs and a fifth job was to create a substantial loss to the defendant, and defendant seeks to recover one-half of such total loss from plaintiff.

Proposed findings were submitted to the trial court by each party. The trial court thereupon made findings resulting in a judgment for plaintiff for money due on jobs 501 and 502-503, and denying defendant judgment on any and all counterclaims.

Defendant on appeal alleges error by the trial court in three respects: (1) in determining defendant waived or was estopped to claim 17 percent as an overhead and profit figure, even though the court found that 17 percent was agreed upon; (2) in determining that plaintiff was not to share in losses on any of the jobs; and (3) in finding against defendant upon its counterclaims when there was substantial evidence to support defendant’s counterclaims.

Plaintiff cross-appeals alleging error of the trial court in two respects: (1) in denying plaintiff’s recovery on job 505 in that the uncontroverted evidence showed a "cost saving” at time of plaintiff’s discharge; and (2) that the offset against plaintiffs claims was *459 $2,007.30 rather than $2,587 as found by the trial court.

It is well established, of course, that a general finding of fact by a trial court in an action at law tried without a jury is the equivalent of a jury verdict and cannot be set aside by this court when supported by any substantial evidence. Hawkins v. Teeples and Thatcher, 267 Or 151, 515 P2d 927 (1973); Gordon Creek Farms v. Layne, 230 Or 204, 358 P2d 1062, 368 P2d 737 (1962); Honeywell, Admx., v. Turner, 214 Or 700, 332 P2d 638 (1958).

The trial court did not make a finding that the defendant waived or was estopped from asserting an overhead and profit figure of 17 percent, nor did the trial court make a finding that the 17 percent figure was agreed upon. The only finding made was that "neither bids or billing prices were determined with reference to a 17% overhead and profit figure.”

Defendant’s president as a witness testified that no agreement was ever reached between the parties as to a percentage figure to be used in determining overhead and profit. In making up the written bid estimates plaintiff used a unit dollar amount for overhead and profit. These amounts calculated to be 8 to 10 percent of gross price. Plaintiff’s estimates for bids were presented to defendant, and defendant’s chief estimator then used these estimates to prepare and submit final bids. Defendant had the right to, and did in some instances, alter and modify plaintiffs estimates in making up the final bid price. The trial court in making its findings adopted the percent for overhead and profit that was reflected in plaintiff’s bid estimates as adopted by defendant in preparing the actual bid on the various jobs.

It is difficult to determine the basis for defendant’s claim that the trial court found that the parties agreed upon a 17 percent figure for overhead and profit. If defendant relies on the trial court’s comments at the close of the trial and prior to making written findings, *460 such reliance is without merit. The trial court simply commented that the defendant expected to get 17 percent as a figure for overhead and profit. Moreover, it must be noted that antecedent remarks of the trial court which are not incorporated in the written findings or judgment are not considered to be findings of fact subject to review by this court. Kallstrom v. Kallstrom, 265 Or 481, 509 P2d 1195 (1973); Ferree v. Doric Co., 62 Wash 2d 561, 383 P2d 900 (1963).

The testimony of plaintiff and that of defendant’s president was in direct conflict as to an agreement for the plaintiff to participate in losses which might be incurred on any of the jobs. Defendant, in claiming such an agreement, had the burden of proof. The court’s finding that plaintiff was not to participate in losses is supported by substantial evidence.

Thsere was no competent evidence that the agreement between plaintiff and defendant constituted a joint venture and therefore plaintiff by operation of law was jointly responsible for losses. Plaintiff was an employe of defendant paid at a set wage scale.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gritzbaugh Main Street Properties, LLC v. Greyhound Lines, Inc.
142 P.3d 514 (Court of Appeals of Oregon, 2006)
Conklin v. Conklin
586 N.W.2d 703 (Supreme Court of Iowa, 1998)
Lantz v. Safeco Title Insurance
763 P.2d 744 (Court of Appeals of Oregon, 1988)
Wilson v. Kartes
762 P.2d 1054 (Court of Appeals of Oregon, 1988)
St. Paul Fire & Marine Insurance v. Valley Insurance
762 P.2d 1048 (Court of Appeals of Oregon, 1988)
Bernard v. Vatheuer
737 P.2d 128 (Oregon Supreme Court, 1987)
Pacific First Federal Savings & Loan Ass'n v. Flathead Properties, Inc.
614 P.2d 1210 (Court of Appeals of Oregon, 1980)
Foelker v. Kwake
568 P.2d 1369 (Oregon Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
564 P.2d 703, 278 Or. 455, 1977 Ore. LEXIS 979, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montgomery-v-wadsworth-plumbing-heating-co-or-1977.