Accent Builders Co. v. Southwest Concrete Systems, Inc.

679 S.W.2d 106, 1984 Tex. App. LEXIS 6599
CourtCourt of Appeals of Texas
DecidedAugust 28, 1984
Docket05-82-01478-CV
StatusPublished
Cited by31 cases

This text of 679 S.W.2d 106 (Accent Builders Co. v. Southwest Concrete Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Accent Builders Co. v. Southwest Concrete Systems, Inc., 679 S.W.2d 106, 1984 Tex. App. LEXIS 6599 (Tex. Ct. App. 1984).

Opinion

STOREY, Justice.

Accent Builders Company, Inc., a general contractor, terminated its subcontract with Southwest Concrete Systems, Inc., relying on a provision in the subcontract which authorized termination for convenience, that is, without cause. Accent later announced to Southwest, and at trial asserted by way of defense, that the termination was for cause, that is, failure to perform in a good and workmanlike manner. The question presented on appeal is whether Accent is bound by and limited to its first announced reason for the termination. We hold that it is not so limited, and, consequently, that the part of the case dealing with this issue was erroneously submitted. We hold further that Southwest’s conversion claim against Accent was fully developed and properly submitted. We therefore reverse and remand in part and affirm in part.

THE CONTRACT CLAIM

Accent was the general contractor for the construction of a banking complex in Dallas. The concrete work on the complex was subcontracted to Southwest. During the course of construction, several disputes arose between Accent and Southwest as to the quality of some of Southwest’s work. With knowledge of certain claimed defects in the concrete work and of claimed failure to follow plans and specifications by Southwest, Accent nevertheless terminated the subcontract initially for its convenience rather than for cause. The termination was by letter dated January 19, 1982, in which Accent announced that the termination was for its convenience as authorized by article 8 of the subcontract. The next day, January 20, 1982, Accent sent Southwest a letter explaining that Accent was not confining itself to termination under the terms of article 8 and that Accent’s *109 reasons for terminating the contract included Southwest’s failure to perform the concrete work in a good and workmanlike manner.

The precise question presented here has not been addressed by Texas courts. In urging affirmance, Southwest argues that Accent made an election to terminate under article 8 of the contract, authorizing it to terminate for convenience, and, having made the election, Accent should be limited to the remedies provided by the contract. Alternatively, Southwest contends that article 8 sets forth an option granted by it to Accent and, having exercised the option to terminate under the contract, Accent was limited to the remedies afforded by article 8. Under the circumstances here presented, we cannot agree with either of these contentions.

Article 8 is an inartfully drawn provision more closely related to a manufacturing and sales enterprise than to a construction project. Article 8 states:

8. TERMINATION: Buyer may terminate this purchase order for its convenience at any time in whole or in part as to undelivered products, in which event Buyer and Seller will negotiate an equitable settlement payment for the terminated portion consisting of Seller’s cost to date of termination, including an allowance for obsolescence, rework or scrap-page, but only for materials in process within Seller’s ordinary manufacturing cycle required to meet the delivery schedule plus a reasonable profit thereon, less any value hereof to Seller, but in no event shall such payment exceed the amount which would have been payable hereunder for such terminated portion, if this order had not been so terminated. Buyer shall have the right to acquire any inventory relating to this order in the hands of Seller at the time of termination.

Neither party claims the language to be ambiguous, however, and its effect on this transaction seems clear. By terminating for convenience, Accent freed itself from exposure to damages which might arise out of a wrongful termination. The article anticipated that, upon termination, the parties would “negotiate an equitable settlement” limited to Southwest’s costs for labor and materials actually expended plus a reasonable profit less an allowance for rework. No allowance was made for cost of completion. Southwest’s suit against Accent sought recovery of its costs plus a reasonable profit.

Accent defended the action on the theory that it had terminated for cause, and thereby placed in issue the matter of substantial performance and the resulting question of alternative damages set down in Turner, Collie and Braden, Inc. v. Brook Hollow, Inc., 642 S.W.2d 160 (Tex. 1982). Accent justified its theory of defense by its letter sent the next day after its first letter of termination when it notified Southwest that the contract was terminated for cause.

The case was submitted to the jury in terms of the article 8 termination for convenience and, in accordance with jury findings, Southwest recovered its costs expended plus a reasonable profit less certain rework expenses. No issue was submitted regarding the cost of completion. We conclude that the case was erroneously submitted, albeit there was a jury finding that Accent intended to terminate for convenience.

It appears to be well settled that upon breach of a contract a party may pursue any remedy which the law affords in addition to the remedy provided in the contract. The fact that the contract provides a particular remedy does not mean that remedy is exclusive unless it is declared to be or it is clearly indicated. Vandergriff Chevrolet Company, Inc. v. Forum Bank, 613 S.W.2d 68, 70 (Tex.Civ. App.—Fort Worth 1981, no writ); Tabor v. Ragle, 526 S.W.2d 670, 676 (Tex.Civ.App.— Fort Worth 1975, writ ref’d n.r.e.); see Nunn v. Brillhart, 242 S.W. 459, 461 (1922). Here there is no contention that article 8 was or was intended to be an exclusive remedy. We perceive no rationale favoring a different rule merely be *110 cause the party has announced his reliance upon one remedy and later relies upon another. This, of course, assumes that the terminating party has not acted in bad faith and also that the terminated party has not changed its position in reliance upon the first announced remedy or reason. This is the rule adopted by the RESTATEMENT (SECOND) OF CONTRACTS, § 248 (1979).

In illustrating the effect of the rule, the Restatement recites facts identical to those presented the Supreme Judicial Court of Massachusetts in New England Structures, Inc. v. Loranger, 354 Mass. 62, 234 N.E.2d 888 (1968). There the court held, as we do, that absent bad faith or a change of position a party is “not prevented from relying upon one good defense among others urged simply because he has not always put it forward.” Id. 234 N.E.2d at 892.

Thus under our holding the question for the jury was not whether Accent intended to terminate for convenience, but instead whether it acted in bad faith or whether Southwest changed its position in reliance. Absent a finding on one or both of these issues, Accent was entitled as a matter of law to its issues pertaining to termination for cause. Accordingly, we reverse and remand this case for retrial of the contract claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arbor Windsor Court, LTD v. Weekley Homes, LP
Court of Appeals of Texas, 2015
Public Building Authority v. St. Paul Fire & Marine Insurance
80 So. 3d 171 (Supreme Court of Alabama, 2010)
Roof Systems, Inc. v. Johns-Manville Corp.
130 S.W.3d 430 (Court of Appeals of Texas, 2004)
4N International, Inc. v. Metropolitan Transit Authority
56 S.W.3d 860 (Court of Appeals of Texas, 2001)
Burleson State Bank v. Plunkett
27 S.W.3d 605 (Court of Appeals of Texas, 2000)
Fletcher v. Edwards
26 S.W.3d 66 (Court of Appeals of Texas, 2000)
Azima v. State Farm Mutual Automobile Insurance Co.
884 S.W.2d 900 (Court of Appeals of Texas, 1994)
Rodgers v. RAB Investments, Ltd.
816 S.W.2d 543 (Court of Appeals of Texas, 1991)
Ramos v. Frito-Lay, Inc.
784 S.W.2d 667 (Texas Supreme Court, 1990)
Lachalet International, Inc. v. Nowik
787 S.W.2d 101 (Court of Appeals of Texas, 1990)
Tripp Village Joint Venture v. MBank Lincoln Centre, N.A.
774 S.W.2d 746 (Court of Appeals of Texas, 1989)
Security State Bank v. Valley Wide Electric Supply Co.
752 S.W.2d 661 (Court of Appeals of Texas, 1988)
Speed v. Eluma International, Inc.
757 S.W.2d 794 (Court of Appeals of Texas, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
679 S.W.2d 106, 1984 Tex. App. LEXIS 6599, Counsel Stack Legal Research, https://law.counselstack.com/opinion/accent-builders-co-v-southwest-concrete-systems-inc-texapp-1984.