Aar Oklahoma, Inc., an Oklahoma Corporation v. McDonnell Douglas Corporation, a Maryland Corporation

1 F.3d 1249, 1993 U.S. App. LEXIS 27953, 1993 WL 298894
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 23, 1993
Docket92-6179
StatusPublished

This text of 1 F.3d 1249 (Aar Oklahoma, Inc., an Oklahoma Corporation v. McDonnell Douglas Corporation, a Maryland Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aar Oklahoma, Inc., an Oklahoma Corporation v. McDonnell Douglas Corporation, a Maryland Corporation, 1 F.3d 1249, 1993 U.S. App. LEXIS 27953, 1993 WL 298894 (10th Cir. 1993).

Opinion

1 F.3d 1249
NOTICE: Although citation of unpublished opinions remains unfavored, unpublished opinions may now be cited if the opinion has persuasive value on a material issue, and a copy is attached to the citing document or, if cited in oral argument, copies are furnished to the Court and all parties. See General Order of November 29, 1993, suspending 10th Cir. Rule 36.3 until December 31, 1995, or further order.

AAR OKLAHOMA, INC., an Oklahoma corporation, Plaintiff-Appellee,
v.
McDONNELL DOUGLAS CORPORATION, a Maryland corporation,
Defendant-Appellant.

No. 92-6179.

United States Court of Appeals, Tenth Circuit.

July 23, 1993.

Before BRORBY, Circuit Judge, McWILLIAMS, Senior Circuit Judge, and EBEL, Circuit Judge.

ORDER AND JUDGMENT*

EBEL, Circuit Judge.

The defendant-appellant, McDonnell Douglas Corporation ("McDonnell"), appeals from the order of the district court finding it liable for the payment of $1,167,160.69 in disputed contract costs. We affirm.

Facts

McDonnell, through a series of purchase and sale agreements, contracted with several entities who are not parties to this litigation to acquire, modify, repair and sell eight used DC-9 aircraft. FAA regulations required that McDonnell certify the airworthiness of the used craft before they could be sold. McDonnell entered into a subcontract with AAR Oklahoma ("AAR") to inspect, modify and repair the planes in order to bring them into compliance with FAA regulations. McDonnell and AAR were able to pre-determine the inspection and modification tasks ("routine work") and to fix prices thereon. However, the repair tasks ("nonroutine work") were contingent on the results of the inspections and could not be determined in advance. Accordingly, the parties agreed to a fixed price labor schedule and agreed that "any nonroutine work or rework must be approved by buyer prior to the initiation of such work."

For each individual aircraft, nonroutine work proceeded as follows: AAR inspectors examined the aircraft for problems and conditions that would require nonroutine work; inspectors would prepare written descriptions of the nonroutine tasks on job cards that would include an estimate of the number of man-hours necessary to complete the task; the job cards would be presented to the McDonnell representatives on site for approval; if approval was granted, the job cards would be used to keep a tally of the man-hours expended on the task.

The dispute in the instant case concerns Nonroutine Series 9000 ours ("Series 9000 hours"). These hours were the tally of leadmen and inspectors who would organize and assist the mechanics in the performance of the nonroutine work. The leadmen and inspectors were generally assigned to a particular plane and would spread their time among several different tasks. The parties dispute whether their hours were meant to be included in the descriptions submitted prior to approval of the nonroutine work. However, it is undisputed that their time was not tallied on the job cards, but rather was recorded in a separate "Nonroutine Series 9000" account. When presented with the invoice for these hours McDonnell refused to pay, claiming that the work was not authorized under the contract or through the time card procedure.

On April 30, 1990, AAR filed suit in the U.S. District Court for the Western District of Oklahoma for payment of disputed invoices and punitive damages.1 On April 7, 1992, a stipulation was submitted to the district court which set forth a single pretrial issue to be determined by the district court.

4. Upon receiving appropriate briefs from the parties, the Court shall make a pretrial ruling:

a. Whether any of the provisions of the Contract (collectively "the provisions") listed in subparagraphs i-iv of this paragraph, as a matter of law impose, as a condition of AAR's right to be compensated under the Contract for Nonroutine Series 9000 hours, a requirement that AAR, before beginning performance of particular items of Nonroutine Work, estimate the amount of such Nonroutine Series 9000 hours that AAR anticipated to incur and charge with respect to each such item and obtain MDC's approval of such estimate:

i. Section XIII of the Schedule (page 6 of 9),

ii. Sections III(G) and III(I) and (IV) of the Statement of Work, Part I-DC-9-33RC (pages 2-5 of 5),

iii. Section [sic] III and IV of the Statement of Work, Part II-DC-9-31 (pages 1-2 of 2),

iv. Attachment D (page 1 of 1);

or,

b. Whether the Court cannot resolve the issue described in paragraph 4.a above as a matter of law because the Court determines that the Provisions are ambiguous on that issue.

Stipulation, Order and Order of Judgment of April 7, 1992, Aplt.Apx. at 13137-38. Essentially, the court was asked to address whether as a matter of law the contract required, as a condition of compensation, that AAR submit an estimate of all nonroutine work hours (including the Series 9000 hours), and receive prior authorization from McDonnell Douglas. On April 21, 1992, the district court entered judgment for AAR finding that the contract was not ambiguous and that none of the relevant provisions required prior approval of Series 9000 hours as a condition precedent to AAR's right to compensation. This appeal followed.

Choice of Law and Standard of Review

Under the "choice of law" provision of the contract, California or federal law may apply depending on whether the work performed was commercial or governmental in nature.2 The parties offer no proof that the disputed Series 9000 hours were to be construed under federal law, and both parties brief the issues as questions of California law. Therefore we will apply California law to the facts of this case.

Under California law, contract interpretation is a question of law. Garcia v. Truck Insurance Exchange, 682 P.2d 1100 (Cal.1984). Accordingly, we review the district court's determinations de novo.

Discussion

By virtue of the stipulation entered by the parties, the only question before the district court was whether the contract required AAR to submit, as a condition of compensation, an estimate of all Series 9000 hours, and receive McDonnell's prior authorization. The district court found that under a plain reading of the contract, and by operation of the California rule of contract interpretation that disfavors conditions precedent, the contract did not contain such a condition.

We find our review of the issues of this case to be severely limited by operation of the stipulation entered into by the parties. Through the stipulation McDonnell has limited its defense to the claim that prior approval of Series 9000 hours is a condition precedent to compensating AAR.

However, under California law, conditions precedent are highly disfavored. Hezel v. Superior Court, 176 Cal.Rptr. 740, 745 (Cal.Ct.App.1981); Pacific Allied v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Gas & Electric Co. v. G. W. Thomas Drayage & Rigging Co.
442 P.2d 641 (California Supreme Court, 1968)
Brubaker v. Beneficial Standard Life Insurance
278 P.2d 966 (California Court of Appeal, 1955)
Pacific Allied v. Century Steel Products, Inc.
327 P.2d 547 (California Court of Appeal, 1958)
Garcia v. Truck Insurance Exchange
682 P.2d 1100 (California Supreme Court, 1984)
Larson v. Thoresen
254 P.2d 656 (California Court of Appeal, 1953)
Alpha Beta Food Markets, Inc. v. Retail Clerks Union Local 770
291 P.2d 433 (California Supreme Court, 1955)
Verdier v. Verdier
284 P.2d 94 (California Court of Appeal, 1955)
Helzel v. Superior Court
123 Cal. App. 3d 652 (California Court of Appeal, 1981)
Wal-Noon Corp. v. Hill
45 Cal. App. 3d 605 (California Court of Appeal, 1975)
Rubin v. Fuchs
459 P.2d 925 (California Supreme Court, 1969)
Berry v. Kettle
256 Cal. App. 2d 252 (California Court of Appeal, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
1 F.3d 1249, 1993 U.S. App. LEXIS 27953, 1993 WL 298894, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aar-oklahoma-inc-an-oklahoma-corporation-v-mcdonne-ca10-1993.