Greg Allen Const. Co., Inc. v. Estelle

762 N.E.2d 760, 2002 Ind. App. LEXIS 11, 2002 WL 28009
CourtIndiana Court of Appeals
DecidedJanuary 11, 2002
Docket54A01-0009-CV-300
StatusPublished
Cited by10 cases

This text of 762 N.E.2d 760 (Greg Allen Const. Co., Inc. v. Estelle) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greg Allen Const. Co., Inc. v. Estelle, 762 N.E.2d 760, 2002 Ind. App. LEXIS 11, 2002 WL 28009 (Ind. Ct. App. 2002).

Opinion

OPINION

BAILEY, Judge.

Case Summary

Greg Allen Construction Company, Inc. ("Allen Construction") and Greg Allen, individually ("Allen"), defendants and counter- and cross-claim plaintiffs below, appeal the trial court's separate judgments for Daniel and Sondra Estelle (collectively, "the Estelles"), plaintiffs and counter-claim defendants below, and for Bane One Mortgage Corp. ("BOMC") and Bank One, Indiana ("Bank One"), cross-claim defendants below. In addition, Allen Construetion and Allen, as well as their attorney, James E. Ayers ("Ayers"), in his individual capacity, appeal the trial court's order directing them to pay attorney fees. Finally, the Estelles challenge the trial court's determination that Allen was not personally liable for the Estelles' damages. We affirm in part and reverse in part.

Issues

Allen Construction and Allen identify sixteen issues for our review, and the Es-telles raise two cross-issues. We consolidate, restate and reorder the issues presented as follows:

I. Whether the trial court erred by entering judgment in favor of the Estelles on their claims against Allen and Alien Construction;
II. Whether the trial court erred by failing to hold Greg Allen personally liable for the Estelle's damages;
Whether the trial court's award of damages to the Estelles was supported by the evidence; III.
IV. Whether the trial court's entry of summary judgment in favor of the Estelles on Allen Construction's amended counter-claim to enforce its mechanic's lien should be set aside;
V. Whether the trial court erred by finding that BOMC and Bank One were not liable to Allen Construetion and Allen; and
VI. Whether the trial court's award of attorney fees was improper.

Facts and Procedural History

In 1996, the Estelles decided to renovate a home they owned in Ladoga, Indiana. In August of that year, they went to the Bank One branch office in Crawfordsville to secure financing for the project. They spoke with BOMC employee Chris McGau-ghey, whose office was located within the *766 bank, and on October 18, 1996, they completed an application for a $70,000 loan, to be secured by the real estate. The Es-telles then contacted Allen Construction for an estimate, and on October 22, 1996, Allen furnished a. document denoted "Quote #1101," which projected that the work would cost $53,982.16. On October 25, 1996, Allen presented Sondra Estelle with a document entitled "Work Order #207," which provided that Allen Construction would perform the work outlined in Quote # 1101. The work order further stated that "unless other arrangements are made," the Estelles would pay Allen Construction one-third of the quoted amount of $53,982.16 before Allen Construction began work, one-third when half of the work was completed, and the remaining third when the job was finished. Sondra Estelle expressed her concern that the documents did not fully describe the work she and Allen had discussed. Allen assured her that all of the work was covered under the contract, and Sondra Estelle signed the document. The Estelles, however, had apparently not secured financing, and Allen Construction agreed to accept a down payment of $1,000.00 to begin work. The Estelles paid this amount on November 5, 1996. Allen Construction then provided the Estelles with a document dated November 6, 1996, which referenced Work Order # 207 and further detailed the work to be done at the house.

The Estelles subsequently presented McGaughey of BOMC with a copy of Quote #1101 and Work Order #207 along with its November 6 attachment. McGaughey advised the Estelles that they would not qualify for the loan unless the appraised value of the home including the proposed renovations was at least $100,000.00, and McGaughey arranged for an appraisal. McGaughey also told the Estelles that BOMC would not finance the project under the terms set out in the documents prepared by Allen Construetion. Instead, McGaughey gave the Es-telles a document entitled Contract for Rehabilitation of Dwelling House and advised that the Estelles and Allen Construction needed to execute the document as part of the loan application and approval process. The document recited that it was a contract between the Estelles and Allen Construction, but contained different terms than Work Order #207. For example, rather than providing for three payments with the first due prior to commencement of the work, the BOMC contract stated that Allen Construction would be paid following the completion of an inspection report specifying that the work had been satisfactorily completed. The agreement further provided that periodic partial payment draws might be allowed, again subject to satisfactory inspection reports. (McGaughey advised the Estelles to secure Allen Construction's agreement to accept five equal payments, with each payment to be made as the project progressed an additional twenty percent. At some point, McGaughey gave the Estelles several blank documents entitled "Construction Loan Disbursement Request" and told the Estelles to have Allen Construction fill them out and fax them to McGaughey to request payment. McGau-ghey told the Estelles that the bank would arrange for inspections to confirm that the work had progressed at least twenty percent before releasing each payment to the Estelles to pay Allen Construction. The BOMC contract also provided that Allen Construction would waive any rights it might have to a lien on the property in connection with its work. McGaughey gave the Estelles documents entitled "Waiver of Lien," which reiterated that Allen Construction agreed to waive its lien rights. McGaughey advised the Estelles to give the forms to Allen Construction for *767 completion and submission to McGaughey along with the loan disbursement forms.

On November 19, 1996, McGaughey and the Estelles learned that the value of the property with the proposed renovations would be only $89,000, not enough to qualify for the requested loan. McGaughey helped the Estelles secure alternative financing, and on November 26, 1996, Bank One approved a line of credit for the Es-telles. While this loan came from Bank One and not BOMC, the Estelles understood that McGaughey would administer the line of credit, and that the BOMC contract, and particularly the provisions relating to periodic payment draws and lien waivers, would govern disbursements from the line of credit.

Allen Construction commenced work on December 5, 1996. At this point, Allen Construction had only been paid $1,000.00, and the company, which had not yet been presented with the BOMC contract, remained unsure of the status of the Es-telles's efforts to obtain financing. On December 6, in response to Allen Construction's demands for additional cash to fully begin the project, the Estelles paid Allen Construction an additional $6,000.00, which was not drawn from the Bank One line of credit. Allen Construction continued working. On December 10, 1996, the Estelles presented Greg Allen with a copy of the BOMC contract and told him that they would be unable to obtain funding for the renovations unless he agreed to the terms set out in the document.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
762 N.E.2d 760, 2002 Ind. App. LEXIS 11, 2002 WL 28009, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greg-allen-const-co-inc-v-estelle-indctapp-2002.