Pierce v. Drees

607 N.E.2d 726, 1993 Ind. App. LEXIS 46, 1993 WL 15244
CourtIndiana Court of Appeals
DecidedJanuary 28, 1993
Docket45A03-9112-CV-364
StatusPublished
Cited by11 cases

This text of 607 N.E.2d 726 (Pierce v. Drees) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pierce v. Drees, 607 N.E.2d 726, 1993 Ind. App. LEXIS 46, 1993 WL 15244 (Ind. Ct. App. 1993).

Opinion

STATON, Judge.

J.E. Pierce, d/b/a Pierce Builders Inc. ("Pierce"), appeals the judgment of the trial court in favor of Richard and Arlene Drees ("the Dreeses"). The trial court awarded the Dreeses $26,682.77 in damages for Pierce's breach of contract and breach of implied warranties resulting from the construction of a garage. Four issues are presented for our review, which we consolidate and restate as follows:

1. Whether the trial court applied the proper measure of damages?
2. Whether the trial court erred in denying the Dreeses attorney fees pursuant to Indiana's Deceptive Sales Act?
We reverse and remand.

The evidence most favorable to the judgment reveals that the Dreeses and Pierce executed a construction contract pursuant to which Pierce was to demolish the Drees-es' existing garage, build a new garage on the same site, and pour a concrete patio next to the Dreeses' home. The total price for the contracted work was $8,158.00. The Dreeses paid $8,844.00 to Pierce toward the total price. Upon completion of the garage, the Dreeses instituted a suit against Pierce alleging improper performance of the construction contract. Pierce filed a counterclaim against the Dreeses requesting thé balance of the contract price.

At trial, the evidence revealed that substantial defects became apparent soon after Pierce began construction. Concrete splat terings from the pouring of the patio dented both the aluminum siding and storm door on the Dreeses' home. Pierce failed to place a required expansion joint between the newly poured concrete pad and the Dreeses' home, and no reinforcing rod or wire was used in the concrete pour. Additionally, the garage was not supported by an adequate footing.

The structure itself was also fraught with construction defects. Pierce failed to use pressure-treated wood as required by industry standards, and his use of anchor bolts similarly did not comply. The plywood on the roof was improperly laid and was not of the same dimension as agreed upon by the parties. Further, the caulking began to fail within one year of construction, causing the siding to pull away from the garage. Based on these and other defects, the Dreeses' expert testified that the cost of repairs would exceed the cost of demolishing and reconstructing the garage, the concrete foundation and the patio.

Following a bench trial, the trial court entered findings of fact and conclusions of law sua sponte. When a party *728 has requested specific findings of fact and conclusions of law under Ind.Trial Rule 52(A), the reviewing court cannot affirm the judgment on any legal basis; rather, this Court must determine whether the trial court's findings are sufficient to support the judgment. - Vanderburgh County Board of Commissioners v. Rittenhouse (1991), Ind.App., 575 N.E.2d 663, 665, trans. denied. In reviewing the judgment, we must first determine whether the evidence supports the findings and second, whether the findings support the judgment. Id. The judgment will be reversed only when clearly erroneous, i.e., when the judgment is unsupported by the findings of fact and conclusions of law entered on the findings. DeHaan v. DeHaan (1991), Ind.App., 572 N.E.2d 1315, 1320, trans. denied. Findings of fact are clearly erroneous when the record lacks any evidence or reasonable inferences from the evidence to support them. Id. To determine whether the findings or judgment are clearly erroneous, we consider only the evidence favorable to the judgment and all reasonable inferences flowing therefrom, and we will not reweigh the evidence or assess witness credibility. Id.

This same standard of review applies when the trial court gratuitously enters specific findings of fact and conclusions of law, with one notable exception. When the trial court enters such findings sua sponte, the specific findings control only as to the issues they cover, while a general judgment standard applies to any issue upon which the court has not found. In re Marriage of Snemis (1991), Ind.App., 575 N.E.2d 650, 652. We may affirm a general judgment on any theory supported by the evidence adduced at trial Id.

I.

Damages

Pierce argues the trial court did not apply the proper measure of damages when it awarded the Dreeses $26,682.77. On appeal, a damage award will not be reversed if it is within the scope of the evidence. When reviewing the evidence, we may not reweigh the evidence or judge the credibility of the witnesses. Dunn v. Cadiente (1987), Ind., 516 N.E.2d 52, 54, reh. denied.

The damage award was based on the following relevant findings and conclusions:

106. Given the number of substantial defects in the garage as constructed by the defendant, the structure should be demolished, the existing concrete broken out and a new structure erect ed in compliance with the contract....
* * * * * u
17. Pierce is entitled to recover nothing on its counterclaim for the contract price because of its breaches of contract.
* # % * * *
21. The plaintiffs should recover judgment for the following damages which flow from the defendant's breach of contract:
a. $3,844.00 paid to the defendant toward the contract price.
b. The $767.81 cost to replace the damaged siding and storm door on the plaintiffs' home.
c. The $987.70 cost to remove and re-pour the concrete pad with an expansion joint.
d. The cost of tarpaulins in the sum of $45.00. 1
e. Damage to personal property in the sum of $250.00.
f. The $11,894.00 cost to remove existing concrete and to demolish the existing garage and construct a new garage pursuant to the contract....
These sums total $17,788.51.
22. The plaintiffs should be awarded prejudgment interest at the rate of 8% per annum from May 1, 1985 to the *729 date hereof, that amount totaling $8,894.26.

Record, pp. 675, 677-78.

In breach of construction contract cases where compliance with the contract would require reconstruction of a substantial portion of the building, the proper measure of damages is the difference between the fair market value of the work as performed and the fair market value of the work if performed in accordance with contract specifications. Gough Const. Co. v. Tri-State Supply Co. (1986), Ind.App., 493 N.E.2d 1283, 1285.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McGrath v. Everest National Insurance
668 F. Supp. 2d 1085 (N.D. Indiana, 2010)
Greg Allen Const. Co., Inc. v. Estelle
762 N.E.2d 760 (Indiana Court of Appeals, 2002)
Couchman v. Restoration Contractors, Inc.
743 N.E.2d 346 (Indiana Court of Appeals, 2001)
McKinney v. State
693 N.E.2d 65 (Indiana Supreme Court, 1998)
Nelson v. Marchand
691 N.E.2d 1264 (Indiana Court of Appeals, 1998)
Parke State Bank v. Akers
645 N.E.2d 1096 (Indiana Court of Appeals, 1995)
J.L.L. v. Madison County Department of Public Welfare
628 N.E.2d 1223 (Indiana Court of Appeals, 1994)
G. Cowser Construction, Inc. v. Nicksic
622 N.E.2d 1007 (Indiana Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
607 N.E.2d 726, 1993 Ind. App. LEXIS 46, 1993 WL 15244, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pierce-v-drees-indctapp-1993.