Natare Corp. v. D.S.I., Duraplastec Systems, Inc.

833 N.E.2d 76, 2005 Ind. App. LEXIS 1518, 2005 WL 2030468
CourtIndiana Court of Appeals
DecidedAugust 24, 2005
Docket49A05-0408-CV-430
StatusPublished
Cited by1 cases

This text of 833 N.E.2d 76 (Natare Corp. v. D.S.I., Duraplastec Systems, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natare Corp. v. D.S.I., Duraplastec Systems, Inc., 833 N.E.2d 76, 2005 Ind. App. LEXIS 1518, 2005 WL 2030468 (Ind. Ct. App. 2005).

Opinion

*79 OPINION

RILEY, Judge.

STATEMENT OF THE CASE

Appellant-Claimant, Natare Corporation (Natare), appeals the trial court's Order denying its Motion to Vacate or Modify an arbitrator's award resulting from an arbitration between Natare and Appellees-Re-spondents, Stewart J. Mart (Mart), D.S.I., Duraplastee Systems, Inc. d/b/a D.S.1., and Aquatic Renovation Systems, Inc. d/b/a ARS, ARS Inc., or RenoSys (collectively, RenoSys).

We reverse and remand with instructions.

ISSUE

Natare raises one issue on appeal: whether the trial court erred when it denied its Motion to Vacate or Modify an arbitrator's award, denying it attorney fees.

FACTS AND PROCEDURAL HISTORY

Michael T. Walsh (Walsh) is the president of Natare, a company that manufactures and sells swimming pool liners nationwide. Walsh's competitor, Mart, is the president of D.S.I. and ARS. Walsh and Mart have been involved in protracted litigation since 1989 when Natare sought an injunetion to prohibit Mart from making disparaging remarks about the company. 1 In 1996, further litigation ensued between D.S.I. and Natare. To avoid incurring further costs and expenses as a result of both actions, Walsh and Mart, on behalf of their companies, entered into a settlement agreement in 1998. Pursuant to the terms of the agreement, each party was to refrain from making disparaging remarks about the other. The agreement further stated that any future claims would be submitted to a third party arbitrator who would enter a binding decision "as to whether a breach has occurred, and assessment of damages, if any ...." (Appellant's Appendix p. 98). In the event a breach was established, the non-breaching party was entitled to $5,000 liquidated damages. However, the non-breaching party was permitted to attempt to establish actual damages beyond that amount. The agreement also awarded the non-breaching party reasonable attorney fees incurred in enforcing the agreement.

In March of 2002, the parties first appeared before an arbitrator to present claims that each company had breached the settlement agreement on several different projects. In total, the arbitrator heard evidence concerning fifteen different projects. Following a hearing on March 12 through 15, 2002, the arbitrator concluded that Natare had prevailed on about half of its twelve claims and that RenoSys had prevailed on two of its six claims. The issue of attorney fees was determined at a separate hearing in July of 2002. Thereafter, in its written award, the arbitrator concluded that because Natare had prevailed on six claims and successfully defended against two of RenoSys's claims and that RenoSys had prevailed on two claims and successfully defended against six of Natare's claims, the parties had "prevailed on the same number of projects for which claims were alleged ...." (Appellant's App. p. 185). However, the arbitrator ultimately awarded only Natare attorney fees in the amount of $70,000 because, in the arbi *80 trator's opinion, RenoSys's conduct had been "unquestionably malicious." (Appellant's App. p. 185).

In September of 2002, the parties again entered into arbitration. In its demand for arbitration, Natare claimed that Reno-Sys had indirectly disseminated disparaging statements about Natare and its prod-uets. In particular, Natare claimed that RenoSys's remarks caused Natare to lose a project to renovate a public swimming pool for the City of Longmont, Colorado. Before the arbitration, the parties stipulated that had Natare performed on the contract, it would have been entitled to $45,000 in profits. Natare sought "an award of damages, along with reasonable attorney fees ... incurred in the enforcement of the Settlement Agreement." (Appellant's App. p. 91).

The case was heard before the arbitrator on October 3, 8, and 9, 2008. On January 14, 2004, the arbitrator entered an award in which he concluded that although RenoSys had disseminated disparaging materials concerning the quality of Na-tare's product, its actions did not cause Natare to lose the project. Specifically, the arbitrator concluded that a representative of the engineering consulting firm, which was hired to oversee the renovation project and make recommendations to the City of Longmont, was "heavily biased against [Natare] before any bids were ever solicited." (Appellant's App. p. 114). Therefore, the arbitrator awarded Natare $5,000 under the liquidated damages provision for establishing a breach, but denied Natare $45,000 actual damages on the lost project. The arbitrator also concluded that neither party could recover attorney fees.

On April 13, 2004, Natare filed a motion to vacate or, in the alternative, modify the January 14, 2004 arbitration award because the arbitrator had failed to award it attorney fees after having successfully established a breach. Following a hearing, the trial court denied Natare's Motion.

Natare now appeals Additional facts will be provided as necessary.

DISCUSSION AND DECISION

Natare contends that the trial court erred when it denied its Motion to Vacate or Modify the arbitration award. Indiana's Uniform Arbitration Act allows parties, who have agreed in writing to submit their claims to arbitration, to seek judicial review under limited circumstances. Bopp v. Brames, 677 N.E.2d 629, 631 (Ind.Ct.App.1997). However, in order to preserve the efficacy and finality of the arbitration process, the scope of judicial review is "extremely narrow." Fort Wayne Educ. Ass'n, Inc. v. Bd. of Sch. Tr. of Ft. Wayne Cmty. Schs., 569 N.E.2d 672, 678 (Ind.Ct.App.1991). The trial court is restricted to determining whether a statutory basis for vacating or modifying the award exists. Indianapolis Pub. Transp. Corp. v. Amalgamated Transit Union, Local 1070, 414 N.E.2d 966, 969 (Ind.Ct.App.1981). A party seeking to vacate or modify the award "bears the burden of proving the grounds to set the award aside." Bopp, 677 N.E.2d at 631.

On appeal, as in the trial court, Natare raises two statutory bases for setting aside the arbitrator's award. The first statute on which Natare relies requires a court to vacate an award where "the arbitrators exceeded their powers and the award can not be corrected without affecting the merits of the decision upon the controversy submitted." Ind.Code § 34-57-2-183(a)(8). In the alternative, Natare contends that the arbitrator's award may be modified pursuant to Indiana Code Section 34-57-2-14(a)(2), which provides that an award must be corrected where "the arbitrators have awarded upon a matter not submitted to them and the award may be corrected *81 without affecting the merits of the decision upon the issues submitted."

While relying upon both statutes, Na-tare focuses its argument on Section 13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Natare Corp. v. D.S.I., Duraplastec Systems, Inc.
855 N.E.2d 985 (Indiana Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
833 N.E.2d 76, 2005 Ind. App. LEXIS 1518, 2005 WL 2030468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natare-corp-v-dsi-duraplastec-systems-inc-indctapp-2005.