Orto v. Jackson

413 N.E.2d 273, 1980 Ind. App. LEXIS 1816
CourtIndiana Court of Appeals
DecidedDecember 4, 1980
Docket3-180A12
StatusPublished
Cited by21 cases

This text of 413 N.E.2d 273 (Orto v. Jackson) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orto v. Jackson, 413 N.E.2d 273, 1980 Ind. App. LEXIS 1816 (Ind. Ct. App. 1980).

Opinion

CHIPMAN, Judge.

Andrew Orto and James Stewart, d/b/a Corn-Lux Builders contracted to build a house for Hubert and Violet Jackson. The home contained numerous defects and the Jacksons refused to pay the builders the agreed contract price. The builders brought suit to foreclose their mechanic’s lien and the Jacksons counterclaimed for damages. The trial court ordered a foreclosure but also awarded various damages to the Jacksons and the builders appeal. We affirm.

The builders have raised the following issues: Whether the trial court erred when it found:

1. The builders liable for rent the Jack-sons paid due to the house not being completed within the agreed time;

2. The builders liable for breach of an express guarantee, implied warranty of habitability, and negligent construction;

3. The builders liable for the defective septic system; and

4. The builders liable for compensatory damages.

FACTS

In June 1976 the builders agreed to build Jacksons’ home for $46,550.00. The contract prepared by the builders, was signed by the parties and contained the following provisions:

“7. The Seller [builders] agrees to diligently prosecute the construction to a conclusion, unless prevented by acts of the Buyer [Jacksons] or his agents, acts of God, including, without limitation, inclement weather, strikes, boycotts, fire of incendary origin or otherwise, war or national emergency and by scarcity of labor and building materials.
11. Seller guarantees all materials and workmanship for a period of one year from the acceptance by the Buyer, normal wear and tear, acts of God and negligent acts of the Buyer exempted.
13. Sellers agree to complete construction 90 days after start of construction.” (This provision was handwritten into the contract at the request of Mr. Jackson.)

Construction began on the Jacksons’ house in early August 1976. In November 1976 the Jacksons sold the home in which they were living. Their new home was not substantially completed until late April of 1977, and they moved into it in early May. The trial court found the Jacksons sold their home in reliance upon paragraph 13 above and also upon an oral promise made in early November by Stewart that the Jacksons would be in their home before Thanksgiving or he would reimburse them for their rental expenses. The trial court awarded the Jacksons $1,548.00 in damages for rent they paid on their house. The rent was $258.00 per month from November of 1976 to April of 1977 inclusive.

Inclement weather did not occur until after the 90 day construction time period mentioned in paragraph 13 had expired. Although no finding was made as to the *275 reason for the construction delay, Orto testified he had a full time job at Inland Steel and therefore he did not work full time on the Jacksons’ house.

A few days after the Jacksons moved into their new home, they experienced numerous plumbing leaks and sewage from the septic system leaked into the basement. A problem also arose concerning the basement wall buckling in, but this was satisfactorily remedied by the builders. The plumbing leaks were fixed but the septic problem was never solved. After being contacted by the Jacksons, Orto came out and attempted to correct the problem. He had a plumber connect the septic system to the house, which had never been done, and had the septic tank pumped out twice. Finally Orto had a hole dug in the back yard near one of the drainage laterals and filled it with two truck loads of stone in an attempt to relieve some of the pressure on the system. At trial Orto admitted this merely removed the sewage problem from the basement and transferred it to the back yard where a cesspool quickly formed on the surface of the yard.

In June of 1977, the builders and Jack-sons met in the builders’ attorney’s office where Orto was informed the sewage problem still existed, the evidence is not clear whether the Jacksons asked Orto to correct other defects they had discovered but the evidence is undisputed that Orto never returned to remedy the septic problem.

On July 26, 1977, the builders filed this foreclosure action and the Jacksons counterclaimed. (The additional parties named as defendants were other lien holders who were dismissed prior to trial.) After the suit was filed, communication ceased between the parties as each side instructed the other to “see my attorney.”

Between May and October of 1977 the Jacksons experienced additional problems with the house. The trusses used to support the floor were faulty which caused the interior of the house to sag and separated some of the walls from the ceiling. The roof and basement both leaked and the gutters fell off the house in the spring of 1978.

The Jacksons paid most of the subcontractors bills and were given credit for these payments by the trial court which found the Jacksons owed the builders $14,-884.80 plus $3,560.00 in attorney’s fees and ordered a foreclosure. Additionally the court found the builders owed the Jacksons $1,548.00 for rent paid by the Jacksons, $3,500.00 to replace the septic system, $1,500.00 to repair the defective trusses and the resulting damage, and $3,500.00 as compensation for the substantial aggravation and inconvenience they were caused by the numerous defects. The court found the builders breached their express guarantee, their implied warranty of habitability, and constructed the house in a negligent manner.

I. RENT

The builders argue they should not have been found liable for rent paid by the Jacksons since the construction contract did not specifically make time of the essence and since the contract did not set forth any penalty provisions for failure to meet the 90 day provision. In effect the builders are asking the court to ignore the 90 day contract provision. Instead, they contend the court should look to the intention of the parties at the time the contract was signed and argue the Jacksons were then under no obligation to sell their house. The builders cite Burnett Coal Mining Co. v. Schrepferman, (1929) 77 Ind.App. 45, 133 N.E. 34 for the proposition time is not regarded as being of the essence to a contract unless it is affirmatively so stated. In Burnett, one of the parties was seeking an injunction and the court said at page 38, “time was not made [of] the essence of the contract, and in equity, unless it affirmatively appears that it was so regarded by the parties, the court will not so regard it.” (emphasis added)

The Jacksons respond by distinguishing Burnett from their action at law for breach of contract by arguing in the latter type of action, time is to be considered of the essence, citing Ohio Valley Buggy Co. v. An *276 derson Forging Co., (1907) 168 Ind. 593, 81 N.E. 574, 577.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Sayre v. Lee Trost
Indiana Court of Appeals, 2026
I.C.C. Protective Coatings, Inc. v. A.E. Staley Manufacturing Co.
695 N.E.2d 1030 (Indiana Court of Appeals, 1998)
ICC PROT. COAT., INC. v. AE Staley Mfg. Co.
695 N.E.2d 1030 (Indiana Court of Appeals, 1998)
Nelson v. Marchand
691 N.E.2d 1264 (Indiana Court of Appeals, 1998)
Kokomo Tube Co. v. Dayton Equipment Services Co.
123 F.3d 616 (Seventh Circuit, 1997)
Johnson v. Scandia Associates, Inc.
641 N.E.2d 51 (Indiana Court of Appeals, 1995)
Parke State Bank v. Akers
645 N.E.2d 1096 (Indiana Court of Appeals, 1995)
Clark's Pork Farms v. Sand Livestock Systems, Inc.
563 N.E.2d 1292 (Indiana Court of Appeals, 1990)
Burleson v. Illinois Farmers Insurance
725 F. Supp. 1489 (S.D. Indiana, 1989)
Indiana & Michigan Electric Co. v. Terre Haute Industries, Inc.
507 N.E.2d 588 (Indiana Court of Appeals, 1987)
Indiana Port Commission v. Bethlehem Steel Corp.
653 F. Supp. 604 (N.D. Indiana, 1987)
Liberty Mutual Insurance Co. v. Parkinson
487 N.E.2d 162 (Indiana Court of Appeals, 1985)
Burras v. Canal Construction & Design Co.
470 N.E.2d 1362 (Indiana Court of Appeals, 1984)
Marshall County Redi-Mix, Inc. v. Matthew
447 N.E.2d 1165 (Indiana Court of Appeals, 1983)
Peltz Construction Co. v. Dunham
436 N.E.2d 892 (Indiana Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
413 N.E.2d 273, 1980 Ind. App. LEXIS 1816, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orto-v-jackson-indctapp-1980.