John Sayre v. Lee Trost

Indiana Court of Appeals·Decided February 11, 2026·No. 25A-PL-01007·Published·Judge Brown

Opinion

FILED

Feb 11 2026, 9:52 am

CLERK

Indiana Supreme Court

Court of Appeals

and Tax Court

IN THE

Court of Appeals of Indiana John Sayre and Sam the Concrete Man, Appellants-Defendants

v.

Lee Trost,

Appellee-Plaintiff

February 11, 2026

Court of Appeals Case No.

25A-PL-1007

Appeal from the Hamilton Superior Court The Honorable Darren J. Murphy, Judge Trial Court Cause No.

29D07-2302-PL-001958

Opinion by Judge Brown

Judge Scheele concurs.

Judge Felix dissents with separate opinion.

Brown, Judge.

[1] John Sayre and Sam the Concrete Man (collectively, “Contractors”) appeal the judgment of the trial court in favor of Lee Trost. We affirm.

Facts and Procedural History [2] On June 15, 2022, Contractors and Trost entered into a contract via email

pursuant to which Trost agreed to pay $14,850 to Contractors for installing a 795-square-foot concrete patio at Trost’s Carmel, Indiana, residence. The email indicates that the patio was supposed to have a base color as well as “Bluestone Texture and release color.” Exhibits Volume IV at 116. The email does not elaborate on the colors and textures the parties agreed upon, the materials to be used, or a start and finish date for the project. The contract itself does not provide any of these details, but it does state that the project “should be completed within 3 to 5 days.” Id. at 120.

[3] On June 27, Contractors installed the north side of the patio and two sets of stairs. Due to a scheduling error with the concrete trucks, the south side of the patio could not be installed the same day. On July 11, Contractors installed the south side of the patio. The north and south sides of the patio turned out to be different colors, with the north side having a beige tone and the south side having a grey tone. From there, the parties engaged in a months-long back and forth about potential solutions before finally agreeing to have Contractors repour the south side of the patio, which occurred on October 31. This fix proved to be more of a problem than the original color issue. The layout of the south end was not confirmed before the new work began, the corners of the south end of the patio were repoured incorrectly, and the control joints did not line up with the north end. To make matters worse, the color issue remained.

[4] On December 6, Contractors repoured the north side of the patio and steps. Two days later, Contractors removed some sealant splatter and told Trost that they would return at a later date to finish removing it. On December 29, Contractors removed more of the splatter, and Trost emailed Contractors with a list of defects, including that the corners were poured incorrectly, and a ¼-inch height difference between the north and south sides, the finish on the stairs was sloppy at the edges and patchy, the patio had mismatched colors, a drain had been damaged in the yard, and there was still splatter on the fence and sealant on the residence. On January 3, 2023, Contractors informed Trost that he had not notified them of these defects within five days of the date they completed work on his patio. On January 27, Contractors filed a lien on Trost’s real estate for $7,425, of which Trost received notice three days later. On February 27, Trost sued Contractors for breach of contract, negligence, and violations of Indiana’s Home Improvement Contracts Act. 1

1 Ind. Code §§ 24-5-11-1 to -14.

[5] On March 1, 2024, the court held a bench trial. Both Trost and Sayre testified, and the trial court determined that Trost’s testimony and evidence was more credible than Sayre’s. The court concluded that Contractors were liable to Trost based on the breach of contract and negligence claims but not under the Home Improvement Contracts Act. The court awarded Trost $19,961 in damages. Contractors filed a motion to correct error, which the court denied. This appeal ensued.2

Discussion [6] We will find the trial court’s decision to be clearly erroneous if the facts do not

support the findings or the court applies the wrong legal standard. In re R.L., 144 N.E.3d 686, 689 (Ind. 2020). We will not reweigh the evidence or judge witness credibility, and we consider only the evidence and reasonable inferences that support the trial court’s decision. In re Ma.H., 134 N.E.3d 41, 45 (Ind. 2019), cert. denied, 140 S. Ct. 2835 (2020). For issues not covered by the findings, we apply our general judgment standard, meaning we should affirm based on any legal theory supported by the evidence. Dep’t of Nat. Res. v. Leonard, 226 N.E.3d 198, 202 (Ind. 2024).

2 Both parties fail to include all relevant facts in the Statement of Facts section of their briefs, as required by Ind. Appellate Rule 46(A)(6). Not only did the parties not include all relevant facts in their Statements of Facts, but they also did not include some relevant facts in their briefs at all. The trial court’s thorough order in this case filled in many of the gaps left by the parties’ briefing. We remind both parties that the purpose of our appellate rules—especially Appellate Rule 46 governing the content of briefs—“is to aid and expedite review and to relieve the appellate court of the burden of searching the record and briefing the case.” Miller v. Patel, 212 N.E.3d 639, 657 (Ind. 2023) (emphasis added) (quoting Dridi v. Cole Kline LLC, 172 N.E.3d 361, 364 (Ind. Ct. App. 2021)).

Court of Appeals of Indiana | Opinion 25A-PL-1007 | February 11, 2026 Page 4 of 17

[7] Contractors argue that the trial court’s conclusions are contrary to law and against the weight of evidence, that, “[w]here the source of a party’s duty to another arises from a contract, ‘tort law should not interfere,’” Appellant’s Brief at 7-8 (citing JPMCC 2006-CIBC14 Eads Parkway, LLC v. DBL Axel, LLC, 977 N.E.2d 354, 364 (Ind. Ct. App. 2012) (quoting Greg Allen Const. Co. v. Estelle, 798 N.E.2d 171, 175 (Ind. 2003), reh’g denied), reh’g denied, trans. denied), and that, “even if Trost could point to some deficiency in his concrete patio, it makes no logical sense to award an essentially double to treble damage award to fund a ‘tear-out-and-replace’ when the concrete patio is usable to the homeowner and the homeowner is enjoying utility value from at least having a patio.” Id. at 8. They also argue the court applied an incorrect measure of damages and Trost is not entitled to be placed in a better position than he would have been had the contract not been broken.

[8] The trial court found:

Trost contends he was damaged by [Contractors’] breaches of the exercise of reasonable care while preforming [sic] home improvements in the amounts of $7,425 for the deposit, $200 for pressur[e] washing and drain replacement, $836.00 for removal of the concrete, [and] $11,500 to replace the concrete. A tear out is the only way to fix. An overlay will not bond correctly. Staining won’t work or last. The concrete has to be removed and replaced.

Appellant’s Appendix Volume II at 36. The court also found, “Trost’s property is devalued because the work needs to be redone at a higher cost.” Id. at 41.

[9] Generally, when parties have arranged their respective risks of loss, tort law should not interfere. Greg Allen, 798 N.E.2d at 175. However, the Indiana Supreme Court has held:

In Greg Allen, we noted . . . that “[While] [t]he issue is . . .

sometimes framed as whether the [tort] duty arises solely from contract[,] . . . [p]utting the issue in terms of the source of the duties . . . is largely tautological.” 798 N.E.2d at 174-175. Rather, “[a]

defendant’s exposure to tort liability is best framed in terms of what the defendant did. . . . To the extent that a plaintiff’s interests have been invaded beyond mere failure to fulfill contractual obligations, a tort remedy should be available.” Id. at 173.

U.S. Bank, N.A. v. Integrity Land Title Corp., 929 N.E.2d 742, 748 (Ind. 2010).

Free access — add to your briefcase to read the full text and ask questions with AI

John Sayre v. Lee Trost, (Ind. Ct. App. 2026).

John Sayre v. Lee Trost (John Sayre v. Lee Trost) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

U.S. Bank, N.A. v. Integrity Land Title Corp.
929 N.E.2d 742 (Indiana Supreme Court, 2010)
Greg Allen Const. Co., Inc. v. Estelle
798 N.E.2d 171 (Indiana Supreme Court, 2003)
Bader v. Johnson
732 N.E.2d 1212 (Indiana Supreme Court, 2000)
Johnson v. Scandia Associates, Inc.
717 N.E.2d 24 (Indiana Supreme Court, 1999)
Jay Clutter Custom Digging v. English
393 N.E.2d 230 (Indiana Court of Appeals, 1979)
Crider & Crider, Inc. v. Downen
873 N.E.2d 1115 (Indiana Court of Appeals, 2007)
Indiana Bureau of Motor Vehicles v. Ash, Inc.
895 N.E.2d 359 (Indiana Court of Appeals, 2008)
Fowler v. Campbell
612 N.E.2d 596 (Indiana Court of Appeals, 1993)
Orto v. Jackson
413 N.E.2d 273 (Indiana Court of Appeals, 1980)
INS Investigations Bureau, Inc. v. Lee
784 N.E.2d 566 (Indiana Court of Appeals, 2003)
L.H. Controls, Inc. v. Custom Conveyor, Inc.
974 N.E.2d 1031 (Indiana Court of Appeals, 2012)
Western Union Telegraph Co. v. Biggerstaff
97 N.E. 531 (Indiana Supreme Court, 1912)
JPMCC 2006-CIBC14 Eads Parkway, LLC v. DBL Axel, LLC
977 N.E.2d 354 (Indiana Court of Appeals, 2012)