Fowler v. Campbell

612 N.E.2d 596, 1993 Ind. App. LEXIS 427, 1993 WL 126528
CourtIndiana Court of Appeals
DecidedApril 26, 1993
Docket41A01-9205-CV-146
StatusPublished
Cited by89 cases

This text of 612 N.E.2d 596 (Fowler v. Campbell) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fowler v. Campbell, 612 N.E.2d 596, 1993 Ind. App. LEXIS 427, 1993 WL 126528 (Ind. Ct. App. 1993).

Opinion

NAJAM, Judge.

STATEMENT OF THE CASE

This is an appeal from an action for breach of a contract to install a septic system. Elesmolee Fowler d/b/a Fowler Construction ("Fowler") appeals from a judgment in favor of Michael G. Campbell and Diane K. Campbell ("Campbells"). We affirm. 1

ISSUES

We restate the issues presented on appeal as follows:

1. Did Fowler breach his contract to install a septic system in the Campbells' new house?

2. Did the Campbells establish that it was Fowler's breach of contract which caused their damages?

3. Did the trial court, in effect, reform the contract when it entered judgment?

4. Were the damages the trial court awarded excessive and unsupported by the evidence?

FACTS

The Campbells owned property on the lakefront of Lamb Lake in Johnson County. On March 2, 1988, the Campbells and Fowler executed a contract ("Contract") for Fowler to build a custom built house for the Campbells on this property ("'House"), which included a septic system.

As lot owners on Lamb Lake, the Camp-bells were members of the Lamb Lake Estates Lot Owners Association ("Association") and were bound by the Association's rules and regulations. Those rules and regulations required that the Association's Architectural Control Committee ("Committee") review and approve plans for a septic system and that the Committee inspect and approve the system during installation. The Johnson County Department of Health ("'Department") imposed similar requirements.

Before their Contract with Fowler was executed, the Campbells had consulted with the Committee and with the Department regarding their plans for the House and septic system ("Plans"). The Campbells employed a professional, Robert Etter of MAJ Civil Engineering ("MAJ"), who prepared a plot plan and a septic system design, and the Campbells then submitted these Plans to the Department and to the Committee for approval. The Committee did not approve the original plot plan as submitted. After making field measurements, the Committee revised the Plans by making changes in the location of the finger system to accommodate the actual distances and topography. The revised plot plan was signed by the Campbells and approved by the Committee on October 28, 1987.

The Department issued a septic system installation permit to the Campbells, dated November 6, 1987. The permit approved "minimum requirements" and installation "as shown on engineered plot." Record at 81. Thus, the permit incorporated by reference the Plans which MAJ had prepared. The Association approved the Plans for the *599 House and septic system on December 12, 1987.

The Contract stated that the Campbells would furnish the Plans, that the House would be built according to the Plans and that Fowler would furnish a "complete septic system according to Johnson County Health Dept. and Lamb Lake Association." Record at 17. The Contract provided that "[all materials and labor will be furnished by Fowler Construction to meet building codes of Johnson County and Lamb Lake Association." Record at 17.

During installation, the Association and the Department inspected the septic system to make certain that the system satisfied their requirements. With the apparent approval of the Committee, but not of MAJ or the Campbells, Fowler moved the septic tank from below the House toward the lake, where it was located on the plot plan, to an entirely different location up on the hill. No further changes in the septic system's design were approved by the Committee. After the septic system was completely installed, the Department made a final inspection so that an occupancy permit could be issued. Upon the final inspection at the Campbells' property, the Association returned the Campbellis' $500.00 performance deposit. 2

It was shortly after Fowler completed construction of the House and within thirty (80) days after the Campbells had moved into the House on April 1, 1989, that the first sewage water back- up occurred. Fowler testified that he discovered cloths, plastic bags, and other debris in the septic pump which had caused it to lock up and to cease pumping. Fowler advised the Camp-bells that the septic pump had been damaged because of the debris which was introduced into the system. Fowler cleaned out the pump and it began functioning again.

Several weeks later, another back-up occurred. Again, Fowler found debris in the septic pump. He notified the Campbells that these objects placed in the septic system were preventing it from functioning properly. Fowler told the Campbells that the septic pump was damaged and that a new one should be installed.

A third back-up occurred beginning in June of 1989. Also, during the summer months, sewage seeped out of the finger system onto the Campbells' driveway and yard. Fowler again visited the property, and on that visit Fowler took members of the Association and Department with him to observe the septic system's condition. The septic pump had again stopped working because foreign objects had become clogged in it. The Department official who accompanied Fowler to the Campbells home told the Campbells that the problems they were having were not caused by any deficiency in the septic system's design, but rather were "due to the apparent misuse of the system." See Record at 377.

The Campbells contend that it was not until after this third back-up that they first learned, in October of 1989, that the septic system had not been installed according to the original Plans. Thereafter, Fowler installed a new septic pump, another 1,000 gallon septic tank and a warning light at a cost of $2,200.00, and the Campbells agreed to this new installation although they paid nothing for it. After the new pump was installed, no further sewage water backups occurred in the Campbells' home, although sewage water continued to seep through the fingers of the septic system onto the Campbells' driveway and yard. The warning light stayed on continuously, and in November of 1989, the pump again stopped working. When the Campbells uncovered the pump station, sewage ran out of the pump, down their yard, and into the lake. The Campbells claim that they tried again to contact Fowler but that he never responded.

During the winter of 1989-1990, the pump was not working. In May of 1990, the Campbells hired Jack Justice, a licensed electrician ("Justice"), who examined the pump and found numerous electrical code violations. Justice found that sewage wa *600 ter had entered the pump housing and "burnt the pump up." Record at 45. Justice replaced the pump and rewired the pump station. The Campbells paid Justice $1,249.57 for his labor and materials in making these repairs.

On May 9, 1990, the Campbells filed a complaint for breach of contract against Fowler. After a bench trial, on October 15, 1991, the trial court entered judgment in favor of the Campbells and awarded them $12,199.57 in damages. This appeal followed. We will state other relevant facts in our discussion of the issues.

DISCUSSION AND DECISION

Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holcim (US) Inc. v. ACMS Group, Inc.
Indiana Court of Appeals, 2025
MercAsia USA, LTD v. Zhu
N.D. Indiana, 2020

Cite This Page — Counsel Stack

Bluebook (online)
612 N.E.2d 596, 1993 Ind. App. LEXIS 427, 1993 WL 126528, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fowler-v-campbell-indctapp-1993.