Holcim (US) Inc. v. ACMS Group, Inc.

CourtIndiana Court of Appeals
DecidedJuly 10, 2025
Docket24A-PL-02458
StatusPublished

This text of Holcim (US) Inc. v. ACMS Group, Inc. (Holcim (US) Inc. v. ACMS Group, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holcim (US) Inc. v. ACMS Group, Inc., (Ind. Ct. App. 2025).

Opinion

IN THE

Court of Appeals of Indiana FILED Jul 10 2025, 8:40 am Holcim (US) Inc., CLERK Appellant/Defendant Indiana Supreme Court Court of Appeals and Tax Court

v.

ACMS Group, Inc., Appellee/Plaintiff

July 10, 2025 Court of Appeals Case No. 24A-PL-2458 Appeal from the Lake Superior Court The Honorable John M. Sedia, Judge Trial Court Cause No. 45D01-2202-PL-163

Opinion by Judge Bradford Judges May and Mathias concur.

Bradford, Judge.

Court of Appeals of Indiana | Opinion 24A-PL-2458 | July 10, 2025 Page 1 of 27 Case Summary [1] ACMS Group, Inc., contracted to rebuild a manufacturing apparatus called a

slag granulator for Holcim (US) Inc., in East Chicago (“the Project”). The slag

granulator is located in a steel mill (“the Mill”) owned by Cleveland-Cliffs. As

part of the contract between ACMS and Holcim (“the Agreement”), Holcim

agreed to clean the jobsite so that ACMS could perform its work. When

ACMS arrived on the start date, however, the cleaning had not been completed,

causing costly delays. When ACMS billed Holcim for expenses related to the

delay, Holcim declined to pay. ACMS brought suit against Holcim, alleging,

among other things, breach of the Agreement, seeking direct and consequential

damages. After a bench trial, the trial court concluded that Holcim had

breached the Agreement and awarded ACMS direct and consequential

damages, prejudgment interest, and attorney’s fees totaling almost six million

dollars. Holcim contends that the trial court clearly erred in finding that it had

breached the Agreement and, in the alternative, challenges several aspects of

the trial court’s findings regarding direct and consequential damages. We

affirm.

Facts and Procedural History [2] In August of 1902, the Mill was constructed in East Chicago for the purpose of

steel production. The production of steel involves heating raw iron ore to high

temperatures in a blast furnace, generating a byproduct called slag. In 2001, a

company that is now part of Holcim negotiated with the former owner of the

Mill to process the slag produced by blast furnace number seven (“No. 7”) with

Court of Appeals of Indiana | Opinion 24A-PL-2458 | July 10, 2025 Page 2 of 27 a machine called a slag granulator for use in cement production. Holcim

currently leases part of the Mill from Cleveland-Cliffs and operates the slag

granulator to that end.

[3] From time to time, it is necessary to rebuild the slag granulator and associated

machinery, and Holcim planned such a reconstruction to occur in September of

2021 to coincide with a scheduled shutdown of No. 7. Holcim awarded the

reconstruction project to ACMS, and the Agreement was executed on August

5, 2021. The Agreement provides, in relevant part, as follows:

Services, as such term is used in the Agreement, shall mean the following:

This project shall consist of the construction services associated with the demolishing and replacement of the receiving hopper and two (2) granulation basins and associated work at the slag granulator. Additional work at the blowing boxes, cold runners, dewatering area, structural and piping is also included. Services necessary to complete this task order includes providing all licenses, permits, labor, materials, equipment supervision and management to complete the project. Area specific details are included on the drawings. Accuracy of these drawings needs to be confirmed, and [Holcim] is not responsible for the accuracy of any drawings provided. All material supplied by [Holcim] must be onsite prior to the scheduled installation date on the provided schedule. [….] 4. Any required material for refractory and structural repairs above and beyond the budget will be billed as T&M. Any and all surplus money for Cold Runner repair material will be discounted upon discovery. 5. Cleaning will be performed by [Holcim] prior to the beginning of the work, including but not limited to the Hopper Tank Basement, Receiving Hopper surrounding, Granulator surrounding, and cold Court of Appeals of Indiana | Opinion 24A-PL-2458 | July 10, 2025 Page 3 of 27 runners. [ACMS] has excluded cleaning, and all cleaning will be performed by [Holcim] at [ACMS]’s direction. Appellant’s App. Vol. II pp. 125–26 (emphasis added). For convenience, we

will refer to the emphasized language as “Paragraph 5.”

[4] When ACMS arrived as scheduled at the Mill to begin rebuilding the slag

granulator, it found that it could not begin work because Holcim had done little

cleaning to the relevant areas, which caused delay and additional expense to

ACMS. Working with Holcim, ACMS managed to complete the rebuilding

process, but not within the thirty-five days originally contemplated. ACMS

billed its additional expenses to Holcim as “T&M,” i.e., “time and materials,”

which Holcim declined to pay. Findings of Fact p. 4. As of December 9, 2021,

Holcim had paid ACMS $3,049,000.00 pursuant to the Agreement, leaving a

contract balance of $649,000.00 plus T&M amounts ACMS had billed for

additional work. In February of 2022, ACMS executed and recorded a

mechanic’s lien notice for the amounts that allegedly remained unpaid, plus

interest and attorney’s fees.

[5] On February 22, 2022, ACMS brought suit against Holcim, seeking foreclosure

of its mechanic’s lien, damages for breach of the Agreement, and recovery

under a theory of quantum meruit. On April 22, 2022, Holcim responded and

counterclaimed, alleging that ACMS had breached the Agreement. On

February 3, 2023, ACMS moved to add a fourth count, seeking consequential

damages resulting from its failure to timely pay various taxes and union

benefits.

Court of Appeals of Indiana | Opinion 24A-PL-2458 | July 10, 2025 Page 4 of 27 [6] On December 29, 2023, both parties moved for summary judgment, and, on

February 23, 2024, the trial court granted ACMS’s motion in part, ruling that

its mechanic’s lien had been perfected. The trial court also entered summary

judgment in favor of Holcim on ACMS’s quantum meruit claim. On April 5

and 8, 2024, the parties and judge held a judicial settlement conference, which

resulted in several claims being settled and Holcim’s counterclaim being

dismissed with prejudice.

[7] The remaining issues were tried to the bench between April 9 and 16, 2024.

Among other things, ACMS offered into evidence its trial exhibit one, an

itemized list of alleged direct damages attributable to Holcim’s failure to clean:

[10%] Subcontract EWO Extra Work Orders Hours labor$ Equipment$ materials$ Markup Final Price $ (F+G+H)

Refractory Materials ex01 420 $39,860.84 $30,600.00 $158,831.00 $18,943.10 $248,234.94 over bid amount

Crane: Additional Stack weight/ Lafarge ex02 $508,480.19 $50,848.02 $559,328.21 Deliveries/ Cleaning efforts

Additional Scope: ex03 Cladding for Cold 360.25 $39,401.56 $20,424.60 $2,042.46 $61,868.62 Runner

ex04 Cleaning Delays 1462 $146,981.85 $146,981.82

receiving hopper EX05 additional assembly & 1075 $123,149.75 $3,972.46 $40,325.00 $2,899.25 $4,719.67 $175,066.13 Internals

stack Internal seal welds EX06 94.5 $9,259.09 $15,666.21 $1,177.00 $1,684.32 $27,786.62 scaffolding

Stack Belly Band due to EX07 misfabrication of spool 144 $14,322.65 $1,274.48 $47,362.00 $6,848.00 $5,548.45 $75,355.58 piece

load and transport scrap EX08 pieces from Jobsite to $48,234.72 $4,823.47 $53,058.19 laydown

East Basin Insert EX09 287.5 $29,051.15 $6,929.32 $692.93 $36,673.40 Misfabrication

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S.C. Nestel, Inc. v. Future Construction Inc.
836 N.E.2d 445 (Indiana Court of Appeals, 2005)
Parke State Bank v. Akers
659 N.E.2d 1031 (Indiana Supreme Court, 1995)
Bob Anderson Pontiac, Inc. v. Davidson
293 N.E.2d 232 (Indiana Court of Appeals, 1973)
Colonial Penn Insurance v. Guzorek
690 N.E.2d 664 (Indiana Supreme Court, 1997)
Rogier v. American Testing & Engineering Corp.
734 N.E.2d 606 (Indiana Court of Appeals, 2000)
Adams v. Reinaker
808 N.E.2d 192 (Indiana Court of Appeals, 2004)
Fowler v. Campbell
612 N.E.2d 596 (Indiana Court of Appeals, 1993)
Indianapolis City Market Corp. v. MAV, INC.
915 N.E.2d 1013 (Indiana Court of Appeals, 2009)
Hopper v. Colonial Motel Properties, Inc.
762 N.E.2d 181 (Indiana Court of Appeals, 2002)
Asc Corporation v. First Nat. Bank, Etc.
167 N.E.2d 460 (Indiana Supreme Court, 1960)
Berkel & Co. Contractors, Inc. v. Palm & Assoc., Inc.
814 N.E.2d 649 (Indiana Court of Appeals, 2004)
Wells v. Stone City Bank
691 N.E.2d 1246 (Indiana Court of Appeals, 1998)
Gold v. CEDARVIEW MANAGEMENT CORP.
950 N.E.2d 739 (Indiana Court of Appeals, 2011)
Claire's Boutiques, Inc. v. Brownsburg Station Partners LLC
997 N.E.2d 1093 (Indiana Court of Appeals, 2013)
Belle City Amusements, Inc. v. Doorway Promotions, Inc.
936 N.E.2d 243 (Indiana Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Holcim (US) Inc. v. ACMS Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/holcim-us-inc-v-acms-group-inc-indctapp-2025.