Holcim (US) Inc. v. ACMS Group, Inc.

Indiana Court of Appeals·Decided July 10, 2025·No. 24A-PL-02458·Published

Opinion

IN THE

Court of Appeals of Indiana FILED

Jul 10 2025, 8:40 am

Holcim (US) Inc.,

CLERK

Appellant/Defendant Indiana Supreme Court Court of Appeals

and Tax Court

v.

ACMS Group, Inc.,

Appellee/Plaintiff

July 10, 2025

Court of Appeals Case No.

24A-PL-2458

Appeal from the Lake Superior Court The Honorable John M. Sedia, Judge Trial Court Cause No.

45D01-2202-PL-163

Opinion by Judge Bradford Judges May and Mathias concur.

Bradford, Judge.

Case Summary [1] ACMS Group, Inc., contracted to rebuild a manufacturing apparatus called a

slag granulator for Holcim (US) Inc., in East Chicago (“the Project”). The slag granulator is located in a steel mill (“the Mill”) owned by Cleveland-Cliffs. As part of the contract between ACMS and Holcim (“the Agreement”), Holcim agreed to clean the jobsite so that ACMS could perform its work. When ACMS arrived on the start date, however, the cleaning had not been completed, causing costly delays. When ACMS billed Holcim for expenses related to the delay, Holcim declined to pay. ACMS brought suit against Holcim, alleging, among other things, breach of the Agreement, seeking direct and consequential damages. After a bench trial, the trial court concluded that Holcim had breached the Agreement and awarded ACMS direct and consequential damages, prejudgment interest, and attorney’s fees totaling almost six million dollars. Holcim contends that the trial court clearly erred in finding that it had breached the Agreement and, in the alternative, challenges several aspects of the trial court’s findings regarding direct and consequential damages. We affirm.

Facts and Procedural History [2] In August of 1902, the Mill was constructed in East Chicago for the purpose of

steel production. The production of steel involves heating raw iron ore to high temperatures in a blast furnace, generating a byproduct called slag. In 2001, a company that is now part of Holcim negotiated with the former owner of the Mill to process the slag produced by blast furnace number seven (“No. 7”) with a machine called a slag granulator for use in cement production. Holcim currently leases part of the Mill from Cleveland-Cliffs and operates the slag granulator to that end.

[3] From time to time, it is necessary to rebuild the slag granulator and associated machinery, and Holcim planned such a reconstruction to occur in September of 2021 to coincide with a scheduled shutdown of No. 7. Holcim awarded the reconstruction project to ACMS, and the Agreement was executed on August 5, 2021. The Agreement provides, in relevant part, as follows:

Services, as such term is used in the Agreement, shall mean the following:

This project shall consist of the construction services associated with the demolishing and replacement of the receiving hopper and two (2) granulation basins and associated work at the slag granulator. Additional work at the blowing boxes, cold runners, dewatering area, structural and piping is also included. Services necessary to complete this task order includes providing all licenses, permits, labor, materials, equipment supervision and management to complete the project. Area specific details are included on the drawings. Accuracy of these drawings needs to be confirmed, and [Holcim] is not responsible for the accuracy of any drawings provided. All material supplied by [Holcim] must be onsite prior to the scheduled installation date on the provided schedule.

[….]

4. Any required material for refractory and structural repairs above and beyond the budget will be billed as T&M. Any and all surplus money for Cold Runner repair material will be discounted upon discovery.

5. Cleaning will be performed by [Holcim] prior to the beginning of the work, including but not limited to the Hopper Tank Basement, Receiving Hopper surrounding, Granulator surrounding, and cold runners. [ACMS] has excluded cleaning, and all cleaning will be performed by [Holcim] at [ACMS]’s direction.

Appellant’s App. Vol. II pp. 125–26 (emphasis added). For convenience, we

will refer to the emphasized language as “Paragraph 5.”

[4] When ACMS arrived as scheduled at the Mill to begin rebuilding the slag granulator, it found that it could not begin work because Holcim had done little cleaning to the relevant areas, which caused delay and additional expense to ACMS. Working with Holcim, ACMS managed to complete the rebuilding process, but not within the thirty-five days originally contemplated. ACMS billed its additional expenses to Holcim as “T&M,” i.e., “time and materials,” which Holcim declined to pay. Findings of Fact p. 4. As of December 9, 2021, Holcim had paid ACMS $3,049,000.00 pursuant to the Agreement, leaving a contract balance of $649,000.00 plus T&M amounts ACMS had billed for additional work. In February of 2022, ACMS executed and recorded a mechanic’s lien notice for the amounts that allegedly remained unpaid, plus interest and attorney’s fees.

[5] On February 22, 2022, ACMS brought suit against Holcim, seeking foreclosure of its mechanic’s lien, damages for breach of the Agreement, and recovery under a theory of quantum meruit. On April 22, 2022, Holcim responded and counterclaimed, alleging that ACMS had breached the Agreement. On February 3, 2023, ACMS moved to add a fourth count, seeking consequential damages resulting from its failure to timely pay various taxes and union benefits.

[6] On December 29, 2023, both parties moved for summary judgment, and, on February 23, 2024, the trial court granted ACMS’s motion in part, ruling that its mechanic’s lien had been perfected. The trial court also entered summary judgment in favor of Holcim on ACMS’s quantum meruit claim. On April 5 and 8, 2024, the parties and judge held a judicial settlement conference, which resulted in several claims being settled and Holcim’s counterclaim being dismissed with prejudice.

[7] The remaining issues were tried to the bench between April 9 and 16, 2024. Among other things, ACMS offered into evidence its trial exhibit one, an itemized list of alleged direct damages attributable to Holcim’s failure to clean:

[10%]

Subcontract

EWO Extra Work Orders Hours labor$ Equipment$ materials$ Markup Final Price $

(F+G+H)

Refractory Materials

ex01 420 $39,860.84 $30,600.00 $158,831.00 $18,943.10 $248,234.94 over bid amount

Crane: Additional Stack

weight/ Lafarge

ex02 $508,480.19 $50,848.02 $559,328.21 Deliveries/ Cleaning

efforts

Additional Scope:

ex03 Cladding for Cold 360.25 $39,401.56 $20,424.60 $2,042.46 $61,868.62 Runner

ex04 Cleaning Delays 1462 $146,981.85 $146,981.82

receiving hopper

EX05 additional assembly & 1075 $123,149.75 $3,972.46 $40,325.00 $2,899.25 $4,719.67 $175,066.13 Internals

stack Internal seal welds EX06 94.5 $9,259.09 $15,666.21 $1,177.00 $1,684.32 $27,786.62 scaffolding

Stack Belly Band due to

EX07 misfabrication of spool 144 $14,322.65 $1,274.48 $47,362.00 $6,848.00 $5,548.45 $75,355.58 piece

load and transport scrap

EX08 pieces from Jobsite to $48,234.72 $4,823.47 $53,058.19 laydown

East Basin Insert

EX09 287.5 $29,051.15 $6,929.32 $692.93 $36,673.40 Misfabrication

ACMS Labor Support

EX10 1096.1 $121,504.17 $24,612.99 $2,461.30 $148,578.46 for cleaning efforts

Compression of Schedule

EX11 - Modularization of Rec $41,382.68 $80,232.50 $38,413.00 $16,002.82 $176,031.00 Hopper Install

Additional water line

EX12 47.5 $5,724.42 - $5,724.42 demo

Court of Appeals of Indiana | Opinion 24A-PL-2458 | July 10, 2025 Page 5 of 27

Additional Rigging for

EX13 60 $6,930.37 $30,355.88 $15,973.73 $4,632.96 $57,892.94 over-weight Rec Hopper

Additional Overtime and

Additional Labor to

EX14 accelerate schedule 6177.3 $758,169.64 $10,436.07 $1,043.61 $769,649.32 because of lack of

cleaning

Rec Hopper Demo due

EX15 to over weight/ 564.4 $64,565.13 $13,560.27 $15,973.73 $10,201.38 $3,973.54 $108,274.05 additional anchoring

Expansion Joint Added

EX16 282 $19,563.78 $3,972.46 $18,382.00 $2,235.45 $44,153.69 Scope

Scaffolding Additional /

EX17 Rework Due to lack of $56,398.36 $5,639.84 $62,038.20 cleaning

Faulk PLI - Pipe

EX18 $10,924.25 $1,092.43 $12,016.68 Elevation Check

Free access — add to your briefcase to read the full text and ask questions with AI

Holcim (US) Inc. v. ACMS Group, Inc., (Ind. Ct. App. 2025).

Holcim (US) Inc. v. ACMS Group, Inc. (Holcim (US) Inc. v. ACMS Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

S.C. Nestel, Inc. v. Future Construction Inc.
836 N.E.2d 445 (Indiana Court of Appeals, 2005)
Parke State Bank v. Akers
659 N.E.2d 1031 (Indiana Supreme Court, 1995)
Bob Anderson Pontiac, Inc. v. Davidson
293 N.E.2d 232 (Indiana Court of Appeals, 1973)
Colonial Penn Insurance v. Guzorek
690 N.E.2d 664 (Indiana Supreme Court, 1997)
Rogier v. American Testing & Engineering Corp.
734 N.E.2d 606 (Indiana Court of Appeals, 2000)
Adams v. Reinaker
808 N.E.2d 192 (Indiana Court of Appeals, 2004)
Fowler v. Campbell
612 N.E.2d 596 (Indiana Court of Appeals, 1993)
Indianapolis City Market Corp. v. MAV, INC.
915 N.E.2d 1013 (Indiana Court of Appeals, 2009)
Hopper v. Colonial Motel Properties, Inc.
762 N.E.2d 181 (Indiana Court of Appeals, 2002)
Asc Corporation v. First Nat. Bank, Etc.
167 N.E.2d 460 (Indiana Supreme Court, 1960)
Berkel & Co. Contractors, Inc. v. Palm & Assoc., Inc.
814 N.E.2d 649 (Indiana Court of Appeals, 2004)
Wells v. Stone City Bank
691 N.E.2d 1246 (Indiana Court of Appeals, 1998)
Gold v. CEDARVIEW MANAGEMENT CORP.
950 N.E.2d 739 (Indiana Court of Appeals, 2011)
Claire's Boutiques, Inc. v. Brownsburg Station Partners LLC
997 N.E.2d 1093 (Indiana Court of Appeals, 2013)
Belle City Amusements, Inc. v. Doorway Promotions, Inc.
936 N.E.2d 243 (Indiana Court of Appeals, 2010)