Project Design & Piping, Inc. v. Siemens Industry, Inc.

CourtDistrict Court, N.D. Indiana
DecidedMarch 25, 2025
Docket1:21-cv-00266
StatusUnknown

This text of Project Design & Piping, Inc. v. Siemens Industry, Inc. (Project Design & Piping, Inc. v. Siemens Industry, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Project Design & Piping, Inc. v. Siemens Industry, Inc., (N.D. Ind. 2025).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF INDIANA FORT WAYNE DIVISION

PROJECT DESIGN & PIPING, INC., ) ) Plaintiff, ) ) v. ) CAUSE NO. 1:21-cv-00266-SLC ) SIEMENS INDUSTRY INC., ) ) Defendant. )

OPINION AND ORDER Plaintiff Project Design & Piping, Inc. (“Project Design”), filed this breach of contract action against Defendant Siemens Industry Inc. (“Siemens”), on June 15, 2021, claiming that Siemens failed to perform contractually obligated subcontractor duties in a construction project. (See ECF 3-2).1 Subsequently, on June 22, 2021, Siemens advanced counterclaims of breach of contract and “account stated” against Project Design. (See ECF 8 at 5-8). Now before the Court is Siemens’s motion for summary judgment (ECF 47), a memorandum in support of summary judgment (ECF 47-1), a statement of undisputed material facts (ECF 47-2), and supporting evidence (ECF 47-3 to ECF 47-30) filed on May 20, 2024. Project Design responded with a brief in opposition (ECF 58), along with a response to Siemens’s statement of facts (ECF 59), and supporting evidence (ECF 59-1), on July 29, 2024. Thereafter, Siemens filed a reply brief on August 23, 2024. (ECF 60). Therefore, the motion is now ripe for ruling. For the following reasons, Siemens’s motion for summary judgment will be GRANTED IN PART and DENIED IN PART, and Siemens will be granted leave to file a second summary judgment motion as set forth herein.

1 Subject matter jurisdiction arises under diversity jurisdiction, 28 U.S.C. § 1332. (See ECF 3). Jurisdiction of the undersigned Magistrate Judge is based on 28 U.S.C. § 636(c), all parties consenting. (See ECF 30). A. Statement of Material Facts2 1. The Project Project Design is a mechanical contractor whose business involves installing HVAC systems in large institutional buildings. (See ECF 59-1 at 4). In 2017, Project Design was the mechanical contractor for a construction project (the “Project”) at Parkview Wabash Hospital located in Wabash, Indiana. (See ECF 59 ¶¶ 1, 2). In Project Design’s contract with the general contractor, Project Design was required to substantially complete its work on the Project by April

1, 2018. (See ECF 47-13 at 2, 13). At some point, Siemens submitted a bid to become Project Design’s controls systems subcontractor for the Project. (See ECF 59-1 at 13; see also ECF 47- 28 ¶ 8; ECF 59 ¶ 16). 2. Project Design Sends the Purchase Order to Siemens on or about February 13, 2017 The parties’ communications of record relevant to contract formation, as to the Project, begin in mid-February 2017. (See ECF 59-1 at 12-18). On February 11, 2017, Project Design emailed Siemens stating it had received “Siemens Base Bid[,]” was attaching the general submittal requirements, and that “[t]hey have accepted the change in AHU’s and gone with the TEMTROL revised fanwall units which per your e-mail, is no cost change to you.” (Id. at 13). The email further stated: “Your contract number is 1646-315 and it is being typed up now. Please

get rolling on shop drawings and call if you have any questions.” (Id.). Between February 12 and 14, 2017, the parties further discussed the scope of work. (See id. at 12, 14-18 (discussing a missed revision to the parties’ scope of work, among other topics)). Siemens sent Project Design a proposal, in the form of a five-page memo, dated February 14, 2017, including the scope of work to be completed for the Project. (See id. at 14-18 (“Siemens . . . is pleased to provide this

2 For summary judgment purposes, the facts are recited in the light most favorable to Project Design, the nonmoving party. See Payne v. Pauley, 337 F.3d 767, 770 (7th Cir. 2003). proposal for a new Siemens building automation and temperature control system for the new [Project].”)). On or about February 13, 2017, Project Design issued an unsigned “Purchase Order 1646-315” (the “Purchase Order”) to Siemens for the purpose of Siemens “provid[ing] labor, materials and equipment required to furnish and install all temperature controls, control panels, software, programming, VFD’s, control dampers and miscellaneous control components per plans, specifications, addendums and approved shop drawings” for the Project. (ECF 47-14 at 4; see ECF 47-6 at 38; ECF 59 ¶ 4).3 In short, Siemens was to serve as Project Design’s “control

systems subcontractor” on the Project. (ECF 59 ¶ 16). The agreed upon and reasonable value of the work to be performed was $452,050, pursuant to the Purchase Order. (See ECF 59 ¶ 14; see also ECF 47-14 at 4). Apparently, Project Design cannot locate the Purchase Order it sent to Siemens on or about February 13, 2017. (See ECF 58 at 5; see also ECF 59 ¶¶ 15, 15.a). The only version of the Purchase Order of record is the single-sided one returned by Siemens to Project Design on March 30, 2017, to be discussed infra, which states on its face: “This Agreement is subject to all provisions and conditions on the reverse side, including those limiting warranties . . . .” (ECF 47- 14 at 4 (capitalization omitted); see ECF 3-1 at 11; ECF 3-2 at 5)). As an exhibit to its summary

judgment motion, Siemens filed a single-page terms and conditions form, containing fifteen numbered paragraphs (the “Terms and Conditions”), which Project Design contends would have been included on the reverse side of the Purchase Order sent to Siemens on February 13, 2017. (ECF 47-24; see ECF 59 ¶ 15.e). Project Design indicates that it routinely included the Terms

3 Although the record does not identify the date Project Design actually submitted the Purchase Order to Siemens, (see ECF 47-6 at 34-35 (demonstrating the parties’ uncertainty as to when and how the Purchase Order was delivered to Siemens)), there is no dispute that the Purchase Order is dated February 13, 2017 (see ECF 47-14 at 4). and Conditions on the reverse side of its purchase orders during the relevant period. (See ECF 59 ¶¶ 15, 15.a, 15.e; see also ECF 47-6 at 229-30). 3. The Parties’ Actions from February 14, 2017, to March 30, 2017 On February 14, 2017, Siemens emailed Project Design, stating: “Attached is an updated

scope letter with all the pricing adjustments shown. Looking forward to working with you!” (ECF 59-1 at 12). As previously mentioned, the record includes a five-page memo, dated that same day and issued from Siemens to Project Design, “provid[ing] [a] proposal for a new Siemens building automation and temperature controls system for the [Project.]” (Id. at 14). On February 22, 2017, the parties exchanged emails concerning the submittal process. (ECF 59 ¶ 5.h).4 On March 9, 2017, Siemens sent a request for information to Project Design. (ECF 59 ¶ 5.n).5 On March 10, 2017, Project Design forwarded to Siemens an invitation to a coordination meeting, upon Project Design being told by the general contractor that “any second tier subcontractors that may be involved in any of your low voltage cabling” installations should attend. (ECF 59-1 at 19; see ECF 59 ¶ 5.i).

4 Project Design asserts the following explanation of a submittal in large construction projects:

In large construction projects it is common practice that after a contract (or subcontract) is awarded to a contractor, the contractor will prepare detailed drawings of the work they will perform. The drawings are submitted to the project engineer for approval, and the detailed information provided by the contractor is referred to as a “submittal.”

(Id. ¶ 5.g (citations omitted)).

5 Project Design explains as follows regarding the request for information process:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barbara Payne v. Michael Pauley
337 F.3d 767 (Seventh Circuit, 2003)
Johnson v. Taylor Bldg. Corp.
371 N.E.2d 404 (Indiana Court of Appeals, 1978)
Herald Telephone v. Fatouros
431 N.E.2d 171 (Indiana Court of Appeals, 1982)
Dove v. Rose Acre Farms, Inc.
434 N.E.2d 931 (Indiana Court of Appeals, 1982)
DiMizio v. Romo
756 N.E.2d 1018 (Indiana Court of Appeals, 2001)
Martinez v. Belmonte
765 N.E.2d 180 (Indiana Court of Appeals, 2002)
Uniroyal, Inc. v. Chambers Gasket & Manufacturing Co.
380 N.E.2d 571 (Indiana Court of Appeals, 1978)
Rogier v. American Testing & Engineering Corp.
734 N.E.2d 606 (Indiana Court of Appeals, 2000)
Estate of Mueller v. Karns
873 N.E.2d 652 (Indiana Court of Appeals, 2007)
Indiana Bureau of Motor Vehicles v. Ash, Inc.
895 N.E.2d 359 (Indiana Court of Appeals, 2008)
Insul-Mark Midwest, Inc. v. Modern Materials, Inc.
612 N.E.2d 550 (Indiana Supreme Court, 1993)
Fowler v. Campbell
612 N.E.2d 596 (Indiana Court of Appeals, 1993)
Frazier v. Mellowitz
804 N.E.2d 796 (Indiana Court of Appeals, 2004)
Young v. Bryan
368 N.E.2d 1 (Indiana Court of Appeals, 1977)
Bamcor LLC v. Jupiter Aluminum Corp.
767 F. Supp. 2d 959 (N.D. Indiana, 2011)
Jackson v. Trancik
953 N.E.2d 1087 (Indiana Court of Appeals, 2011)
Janky v. Batistatos
559 F. Supp. 2d 923 (N.D. Indiana, 2008)
AM General LLC v. James A. Armour
46 N.E.3d 436 (Indiana Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Project Design & Piping, Inc. v. Siemens Industry, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/project-design-piping-inc-v-siemens-industry-inc-innd-2025.