Project Design & Piping, Inc. v. Siemens Industry, Inc.

District Court, N.D. Indiana·Decided September 4, 2025·No. 1:21-cv-00266·Unknown

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF INDIANA FORT WAYNE DIVISION

PROJECT DESIGN & PIPING, INC., ) ) Plaintiff, ) ) v. ) CAUSE NO. 1:21-cv-00266-ALT ) SIEMENS INDUSTRY INC., ) ) Defendant. )

OPINION AND ORDER This case stems from Plaintiff Project Design & Piping, Inc.’s (“Project Design”) breach of contract claim against Defendant Siemens Industry Inc. (“Siemens”). (See ECF 3-2). Before the Court is Siemens’s second motion for summary judgment seeking the dismissal of Project Design’s claims (ECF 64-1), prefaced by a notice filing (ECF 64), filed on May 7, 2025. For the following reasons, the motion for summary judgment will be granted. A. Relevant Factual and Procedural History The Court will not recite the material facts underlying the claims in this case here, given they have previously been discussed at length in the Court’s March 25, 2025, Opinion and Order on Siemens’s first summary judgment motion. (See ECF 61). Instead, only the facts that are of most relevance now will be stated. On March 25, 2025, the Court granted in part and denied in part Siemens’s first summary judgment motion. (Id.; see ECF 47). In that Opinion and Order, the Court agreed with Siemens that a one-page addendum (the “Addendum”) serves as part of the parties’ contractual agreement, which, in sum, includes a purchase order, terms and conditions, and the Addendum (the “Agreement”); the Court, however, declined to interpret how the Addendum impacted Plaintiff’s claims absent further briefing by the parties. (See ECF 61 at 14-19).1 Therefore, Siemens was granted leave to file a second summary judgment motion concerning the extent to which the Agreement precludes or limits Project Design’s claims and damages in this case. (See id. at 19, 28).

Siemens filed its second motion for summary judgment, including a notice filing, on May 7, 2025. (ECF 64, 64-1). Project Design filed its response brief on May 30, 2025, and Siemens followed with its reply on June 13, 2025. (ECF 65, 66). Accordingly, this motion is now ripe for the Court’s adjudication. B. Legal Standard: Contract Interpretation “The ultimate goal of any contract interpretation is to determine the intent of the parties at the time that they made the agreement.” Citimortgage, Inc. v. Barabas, 975 N.E.2d 805, 813 (Ind. 2012) (citation omitted).2 “Interpretation and construction of contract provisions are questions of law. As such, cases involving contract interpretation are particularly appropriate for summary judgment.” Panther Brands, LLC v. Indy Racing League, LLC, 126 N.E.3d 898, 904

(Ind. Ct. App. 2019) (citations omitted). “If contract language is unambiguous, this court may not look to extrinsic evidence to expand, vary, or explain the instrument but must determine the parties’ intent from the four corners of the instrument.” Id. at 905 (citation omitted). In doing, so the Court should generally give the terms within those four corners their ordinary meaning. See Am. States Ins. v. Kiger, 662 N.E.2d 945, 947 (Ind. 1996).

1 The Court further denied Siemens’s first motion for summary judgment as to whether Siemens or Project Design breached the Agreement, citing material disputes of fact between the parties. (See id. at 25-28).

2 As explained in the Court’s March 25, 2025, Opinion and Order, the parties apparently agree that their contractual dispute is governed substantively by Indiana law given their reliance on Indiana cases in the briefs. (ECF 61 at 10 (citing ECF 47-1, 58, 60); see also ECF 64-1 at 3; ECF 65 at 2-3). C. Discussion: Exculpation of Damages Siemens argues that paragraph 16 of the Addendum exculpates or releases it from damages associated with Project Design’s breach of contract claim. (ECF 64-1 at 7). In support of this argument, Siemens explains that exculpatory clauses3 are looked upon favorably by

Indiana courts—with some exceptions of which this case does not involve. (See id. at 6-7). Paragraph 16 of the Addendum states as follows: 16 . . . : “NOTWITHSTANDING ANYTHING IN THIS AGREEMENT TO THE CONTRARY, SUBCONTRACTOR/SUPPLIER IS NOT LIABLE, WHETHER BASED IN CONTRACT, WARRANTY, TORT (INCLUDING NEGLIGENCE), STRICT LIABILITY, INDEMNITY OR ANY OTHER LEGAL OR EQUITABLE THEORY, FOR: LOSS OF USE, REVENUE, SAVINGS, PROFIT, INTEREST, GOODWILL OR OPPORTUNITY, LOSS OF PRODUCTION, COSTS OF CAPITAL, COSTS OF REPLACEMENT OR SUBSTITUTE USE OR PERFORMANCE, LOSS OF INFORMATION AND DATA, LOSS OF POWER, VOLTAGE IRREGULARITIES OR FREQUENCY FLUCTUATION, CLAIMS ARISING FROM PROJECT DESIGN AND PIPING INC. THIRD PARTY CONTRACTS, OR FOR ANY TYPE OF INDIRECT, SPECIAL, LIQUIDATED, PUNITIVE, EXEMPLARY, COLLATERAL, INCIDENTAL, OR CONSEQUENTIAL DAMAGES OR FOR ANY OTHER LOSS OR COST OF A SIMILAR TYPE.”

(ECF 47-14 (bold font omitted)). Siemens identifies several portions of paragraph 16 that it believes should preclude Project Design from prevailing on its breach of contract claim. (See generally ECF 64-1 at 7-16). First, Siemens contends that Project Design supplanted Siemens with Innovative Control Systems (“ICS”), qualifying ICS as a replacement or substitute subcontractor as referenced in paragraph 16. (Id. at 8-9). Siemens further states that Project Design claims entitlement to damages because of its termination of Siemens and subsequent hiring of its replacement

3 “An exculpatory clause covers the risk of harm sustained by the exculpator . . . that might be caused by the exculpatee . . . . By releasing the exculpatee from liability for such harm, an exculpatory clause deprives the exculpator of its right to recover damages . . . .” Morris v. McDonald's Corp., 650 N.E.2d 1219, 1222 (Ind. Ct. App. 1995) (citations omitted). subcontractors, including ICS. (See id. at 8-11). Consequently, Siemens asserts that it is exculpated from Project Design’s expenses associated with hiring ICS, or any other replacement contractor. (See id.; see also ECF 47-14 (“subcontractor/supplier is not liable . . . for . . . costs of replacement or substitute use or performance . . . .” (bold font and capitalization omitted)).

Siemens also asserts that it is not liable for Project Design’s third-party contracts because they are barred under paragraph 16. (ECF 64-1 at 12 (“[Project Design] cannot establish any damages in support of its Breach of Contract claim against Siemens, because the costs purportedly incurred by [Project Design’s] third-party contracts with other subcontractors are barred pursuant to Paragraph 16 of the Addendum.”); ECF 47-14 (“subcontractor/supplier is not liable . . . for . . . claims arising from [Project Design’s] third party contracts . . . .” (bold font and capitalization omitted)). Each of these arguments will be discussed.4 1. Replacement or Substitute Subcontractors Siemens’s first argument is that paragraph 16 of the Addendum precludes Project Design from recovering damages related to “costs of replacement or substitute use or performance[,]”

including ICS and other subcontractors that Project Design used in place of Siemens. (ECF 64-1 at 9 (quoting ECF 47-14)). The terms in this clause are undefined in the Addendum, however, the Supreme Court of Indiana has inferred that courts may observe Black’s Law Dictionary to determine the plain meaning of undefined contract terms. See Reuille v. E.E. Brandenberger Const., Inc., 888 N.E.2d 770, 771 (Ind.

Free access — add to your briefcase to read the full text and ask questions with AI

Project Design & Piping, Inc. v. Siemens Industry, Inc., (N.D. Ind. 2025).

Project Design & Piping, Inc. v. Siemens Industry, Inc. (Project Design & Piping, Inc. v. Siemens Industry, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Reuille v. E.E. Brandenberger Construction, Inc.
888 N.E.2d 770 (Indiana Supreme Court, 2008)
Rheem Manufacturing Co. v. Phelps Heating & Air Conditioning, Inc.
746 N.E.2d 941 (Indiana Supreme Court, 2001)
General Bargain Center v. American Alarm Co.
430 N.E.2d 407 (Indiana Court of Appeals, 1982)
American States Insurance Co. v. Kiger
662 N.E.2d 945 (Indiana Supreme Court, 1996)
Security Bank & Trust Co. v. Bogard
494 N.E.2d 965 (Indiana Court of Appeals, 1986)
Indiana Department of Transportation v. Shelly & Sands, Inc.
756 N.E.2d 1063 (Indiana Court of Appeals, 2001)
Pinnacle Computer Services, Inc. v. Ameritech Publishing, Inc.
642 N.E.2d 1011 (Indiana Court of Appeals, 1994)
Morris v. McDonald's Corp.
650 N.E.2d 1219 (Indiana Court of Appeals, 1995)
Whitaker v. Brunner
814 N.E.2d 288 (Indiana Court of Appeals, 2004)
Wabash County Young Men's Christian Ass'n v. Thompson ex rel. Thompson
975 N.E.2d 362 (Indiana Court of Appeals, 2012)