Fort Wayne Bank Building, Inc. v. Bank Building & Equipment Corp. of America

309 N.E.2d 464, 160 Ind. App. 26, 1974 Ind. App. LEXIS 1005
CourtIndiana Court of Appeals
DecidedApril 15, 1974
Docket3-1272A92
StatusPublished
Cited by35 cases

This text of 309 N.E.2d 464 (Fort Wayne Bank Building, Inc. v. Bank Building & Equipment Corp. of America) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fort Wayne Bank Building, Inc. v. Bank Building & Equipment Corp. of America, 309 N.E.2d 464, 160 Ind. App. 26, 1974 Ind. App. LEXIS 1005 (Ind. Ct. App. 1974).

Opinion

*28 Hoffman, C.J.

— This is an appeal from a judgment against Fort Wayne Bank Building, Inc. and Thomas Marshall (Owner) for the cost of materials and labor used in the Fort Wayne National Bank Building. The building was partially constructed by appellee Bank Building and Equipment Corporation of America (Contractor) who obtained the materials and labor in issue from a subcontractor.

After the Contractor stopped work on the building, it reached a settlement with the Owner as to compensation for the work it completed, and obtained a release from further obligations under their contract. Under the terms of this “settlement agreement” executed by the parties, the Owner agreed to present to the Contractor releases from all subcontractors used by the Contractor on the project, agreed to pay an amount of money to the Contractor, and assumed “full and complete responsibility to pay all amounts due * * * subcontractors” used by the Contractor. And, the Owner agreed to indemnify the Contractor from any claims against it arising out of the construction of the building. One witness was allowed to testify that the indemnification provision was inserted because this arrangement assured the Contractor that it would not later be held liable for subcontract work ordered by the Owner, which had reserved the right to subcontract certain portions of the work.

Subsequent to the execution of the terms of the settlement agreement, a subcontractor used by the Contractor successfully sued it on a claim arising from the construction of the building. The contractor impleaded the Owner as a third-party defendant, alleging the Owner was liable to indemnify the Contractor under the “settlement agreement.” After a trial to the court, a judgment was entered against the Owner on the third-party complaint. The Owner appeals from the denial of its motion to correct errors.

The controversy at trial and on appeal results from the divergent constructions placed upon the “settlement agreement” by the parties. A review of the Indiana law pertaining *29 to the construction of such agreements will quickly resolve this controversy.

The “settlement agreement” reached in the case at bar is, in the eyes of the law, a contractual modification of the parties’ original construction contract. The law is clear that parties competent to contract may mutually so modify or change their contracts. Commercial Acceptance Co. v. Walton (1931), 93 Ind. App. 136, 176 N.E. 244.

Since modifications such as that in question in the case at bar are themselves contractual undertakings, the law of construction of contracts must determine the outcome of any controversy as to their meaning. The foremost rule and guiding purpose of this body of law is to ascertain the intention of the parties from their expression of it, and to give effect to that intention, if it can be done consistently with legal principles. Walb Construction Co. v. Chipman (1931), 202 Ind. 434, 175 N.E. 132; McClain’s Estate v. McClain (1962), 133 Ind. App. 645, 183 N.E.2d 842.

Although evidence of the intent of the parties which is extrinsic to a contract may be properly considered by a court where fraud, mistake, illegality, duress or undue influence are shown, such evidence is not admissible where these are not shown and where the terms of the instrument are susceptible of a clear and unambiguous construction. Hauck v. Second National Bank of Richmond (1972), 153 Ind. App. 245, 286 N.E.2d 852 (transfer denied).

The following portions of the “settlement agreement” in the case at bar speak to the liability of the Owner to indemnify the Contractor against subcontractor’s claims:

“Owner-Architect assumes full and complete responsibility to pay all amounts due to persons, firms and corporations who were subcontractors or suppliers to Bank Building [the Contractor] on the Fort Wayne National Bank Building project (‘the building project’) and Owner-Architect further agrees to furnish to Bank Building full and *30 complete releases from any such subcontractors and suppliers thereby releasing Bank Building and Hartford [the surety] from any and all claims arising from work and/or materials furnished to the building project. * * * *.
“Owner-Architect hereby agrees to indemnify and hold harmless Bank Building and Hartford and [sic] from any claims by any third persons arising out of the design and construction of the building, * * * (Emphasis supplied.)

This language cannot be said to be ambiguous or uncertain. In McClain’s Estate v. McClain, supra, the court discussed the rules of construction to be employed in gleaning the intent of the parties from an unambiguous contract and, at 655-656 of 133 Ind. App., at 847-848 of 183 N.E.2d, stated:

“The intention of the parties must be gathered from the whole contract rather than isolated parts or fragments. The case of Ahlborn et al. v. City of Hammond (1953), 232 Ind. 12, 111 N.E.2d 70, states the rule in this manner:
Tt is well settled that words, phrases, sentences, paragraphs ... of a contract cannot be read alone. ... The intention of the parties must be gathered from the entire contract. . . .’
“To determine the meaning to be given the words of the agreement in question, the rule stated in Haworth v. Hubbard et al. (1942), 220 Ind. 611, 44 N.E.2d 967 might well serve as the accepted guide. The rule is stated as follows:
Tt is everywhere agreed that words used in a contract are to be given their usual and common meaning unless, from the entire contract and the subject matter thereof, it is clear that some other meaning was intended. . . .’
“Another rule of construction applicable to the agreement herein is set forth in Sindlinger et al. v. Dept. of Financial Institutions (1936), 210 Ind. 83, 199 N.E. 715, wherein the Court said:
‘A liberal or technical construction of an isolated or special clause should not be indulged to defeat the true meaning of a contract. The true meaning of a contract is to be ascertained from a consideration of all of its provisions in order to carry out the true intention of the parties gathered from the whole instrument. . . .’
*31

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gold v. CEDARVIEW MANAGEMENT CORP.
950 N.E.2d 739 (Indiana Court of Appeals, 2011)
In re Windmill Environmental Services, LLC
381 B.R. 717 (N.D. Indiana, 2008)
Jamrosz v. Resource Benefits, Inc.
839 N.E.2d 746 (Indiana Court of Appeals, 2005)
Thomas Hinc v. Lime-O-Sol Company
382 F.3d 716 (Seventh Circuit, 2004)
Leslie v. Hart (In Re Hart)
130 B.R. 817 (N.D. Indiana, 1991)
In Re Doty
129 B.R. 571 (N.D. Indiana, 1991)
City of Evansville v. Old State Utility Corp.
550 N.E.2d 1339 (Indiana Court of Appeals, 1990)
Shaver Motors, Inc. v. Mills (In Re Mills)
111 B.R. 186 (N.D. Indiana, 1988)
In Re Greives
81 B.R. 912 (N.D. Indiana, 1987)
Radio Picture Show Partnership v. Exclusive International Pictures, Inc.
482 N.E.2d 1159 (Indiana Court of Appeals, 1985)
Harvest Insurance Agency, Inc. v. Inter-Ocean Insurance Co.
478 N.E.2d 98 (Indiana Court of Appeals, 1985)
Burras v. Canal Construction & Design Co.
470 N.E.2d 1362 (Indiana Court of Appeals, 1984)
Fort Wayne Cablevision v. Indiana & Michigan Electric Co.
443 N.E.2d 863 (Indiana Court of Appeals, 1983)
Crestwood Park, Inc. v. Apostal
431 N.E.2d 789 (Indiana Supreme Court, 1982)
Ancich v. Mobil Oil Corp.
422 N.E.2d 1320 (Indiana Court of Appeals, 1981)
Sheller-Globe Corp. v. Sheller
413 N.E.2d 318 (Indiana Court of Appeals, 1980)
Piskorowski v. Shell Oil Co.
403 N.E.2d 838 (Indiana Court of Appeals, 1980)
Boswell v. Lyon
401 N.E.2d 735 (Indiana Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
309 N.E.2d 464, 160 Ind. App. 26, 1974 Ind. App. LEXIS 1005, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fort-wayne-bank-building-inc-v-bank-building-equipment-corp-of-indctapp-1974.