Indianapolis Raceway Park, Inc. v. Curtiss

386 N.E.2d 724, 179 Ind. App. 557, 1979 Ind. App. LEXIS 1065
CourtIndiana Court of Appeals
DecidedMarch 15, 1979
Docket1-978A246
StatusPublished
Cited by34 cases

This text of 386 N.E.2d 724 (Indianapolis Raceway Park, Inc. v. Curtiss) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indianapolis Raceway Park, Inc. v. Curtiss, 386 N.E.2d 724, 179 Ind. App. 557, 1979 Ind. App. LEXIS 1065 (Ind. Ct. App. 1979).

Opinion

ROBERTSON, Judge.

Defendant-appellant Indianapolis Raceway Park, Inc. (IRP) appeals an adverse judgment in favor of plaintiff-appellee Roger Curtiss (Curtiss).

The record reveals that IRP entered into a lease arrangement with a Mr. Heiman whereby Heiman agreed, in lieu of rent, to construct lighting for night races on the track owned by IRP, and in return Heiman was given the right to promote races for one season. The deposition of the track manager (Dakin) disclosed that IRP was hesitant to “gamble” on the capital expenditure themselves for lighting, but were willing to enter into a lease whereby the construction was required to be completed pursuant to IRP’s specifications before the season began. In this manner, IRP felt secure because the “rent” would be paid before the races began, and hence no bond or other security would be necessary. Under the terms of the lease, Heiman agreed to bear all costs of construction and to save IRP harmless from any liability arising therefrom. Heiman was required to submit all invoices pertaining to his indebtedness for the construction to IRP, and within three days thereafter submit proof of payment. If Heiman were to default on his obligations, IRP could terminate the lease.

Curtiss had apparently worked with Hei-man on prior occasions, and Heiman asked Curtiss if he wanted to bid on the lighting project. Curtiss made several trips to Indianapolis to survey the site and confer with a local electric utility. Curtiss met Dakin at the track on one visit, and Dakin also attended a meeting with the utility and Curtiss. Thereafter, Curtiss submitted a proposal to Heiman which he accepted. IRP never received a copy of the proposal, although they were aware of a “ball park figure” for the total construction cost.

Construction began in March of 1968 and was completed in late April or early May. Dakin was responsible for making sure the work was accomplished pursuant to specifications; however, it does not appear that he actually directed or coordinated the construction. Dakin was at the site every day and since his office was located at the main gate, he signed for various materials as they arrived. Under the contract between Curtiss and Heiman, Heiman was not required to pay until completion. Hence, IRP never received invoices for progress payments. When the work was virtually complete, Curtiss presented a bill to Heiman and Heiman wrote a bad check therefor. Curtiss then notified IRP that Heiman failed to pay, and demanded payment from IRP. IRP exercised their rights to terminate the lease and assumed the use of the track. Although Curtiss knew Heiman had to construct lighting in order to operate night races, he was unaware of the specific provisions of the lease until demand was made upon IRP. IRP refused to pay, and Curtiss never gave notice or filed a mechanic’s lien. 1 Trial was had to the court upon depositions and other matters on file, the trial court made special findings of fact and conclusions of law, and rendered judgment thereon for Curtiss.

Special findings are intended to preserve grounds for error in this court by *726 disclosing the factual basis for the legal theory applied below. In re Marriage of Miles, (1977) Ind.App., 362 N.E.2d 171.

Thus, whether the findings are adequate depends upon whether they are sufficient to disclose a valid basis under the issues for the legal result reached in the judgment. In making this determination a reviewing court will accept the findings made by the trial court if they are supported by evidence of probative value. [Citations omitted]. Furthermore, on appeal the findings will be construed [in support] of the judgment.

Id., 362 N.E.2d at 174 (citations omitted.) Both Curtiss and IRP assert the legal theory involved is quasi contract for unjust enrichment. No agency or ratification theory is before us. Therefore, we must decide whether the findings of fact are based upon evidence of probative value and whether such facts support recovery in quasi contract.

In Dyer Construction Co., Inc. v. Ellas Construction Co., Inc. et al., (1972) 153 Ind.App. 304, 287 N.E.2d 262, we held that:

Contracts implied in law, more properly termed constructive or quasi contracts, are not contracts in the true sense. They rest on a legal fiction imposed by law without regard to assent of the parties. They arise from reason, law, and natural equity, and are clothed with the semblance of contract for the purpose of a remedy. No action can lie in quasi contract unless one party is wrongfully enriched at the expense of another.

153 Ind.App. at 308, 287 N.E.2d at 264. “In other words, where there is a wrong, the court will find a remedy.” Clark v. Peoples Savings & Loan Association of DeKalb County, (1943) 221 Ind. 168, 172, 46 N.E.2d 681, 682. Unjust enrichment comes within the purview of an action based on quasi contract, Key Hotel Corporation, Club Olympia, Inc. v. Crowe, Chizek & Company, (1977) Ind.App,, 359 N.E.2d 262, and becomes an indispensible element thereof. Glick v. Seufert Construction and Supply Co., Inc., (1976) Ind.App., 342 N.E.2d 874. 2 Generally, the plaintiff must show the benefit was rendered to the party sought to be charged at his implied request under circumstance in which a court of equity invokes the remedy of restitution in order to avoid unjust enrichment. See Kody Engineering Company, Inc. v. Fox and Fox Insurance Agency, Inc., (1973) 158 Ind.App. 498, 303 N.E.2d 307; Glick, supra. Therefore, quasi contract is designed to remedy a wrong, and relevant considerations include whether the defendant is unjustly enriched and whether the benefits were bestowed at his implied request. Absent a wrong, intervention by equity is inappropriate.

Returning to the facts at bar, Heiman was obligated by contract to construct lighting for IRP, and in order to fulfill this obligation, Heiman contracted with Curtiss. Although in common parlance Heiman was not a “general contractor,” the arrangement was virtually indistinguishable from the typical situation wherein an owner contracts with another to perform certain construction, and the other engages a sub-contractor. In such a case the parties have voluntarily allocated the risks by contract, and the failure of the general contractor to perform does not generally give rise to an action for unjust enrichment against the owner. See generally Robertson v. Laughlin Insulation Company, Inc., 134 Ga.App. 509, 215 S.E.2d 274 (1975); Rolla Lumber Company v. Evans,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
N.D. Indiana, 2026
Redco Construction v. Profile Properties, LLC
2012 WY 24 (Wyoming Supreme Court, 2012)
Hughes v. Chattem, Inc.
818 F. Supp. 2d 1112 (S.D. Indiana, 2011)
Ritzert Co. v. United Fidelity Bank, FSB
935 N.E.2d 756 (Indiana Court of Appeals, 2010)
T-3 Martinsville, LLC v. U.S. Holding, LLC
911 N.E.2d 100 (Indiana Court of Appeals, 2009)
Wenning v. Calhoun
827 N.E.2d 627 (Indiana Court of Appeals, 2005)
Roberts v. ALCOA, INC.
811 N.E.2d 466 (Indiana Court of Appeals, 2004)
Inlow v. Inlow
797 N.E.2d 810 (Indiana Court of Appeals, 2003)
Savoree v. Industrial Contracting & Erecting, Inc.
789 N.E.2d 1013 (Indiana Court of Appeals, 2003)
Knowles & Associates LLC v. Cook
784 N.E.2d 1063 (Indiana Court of Appeals, 2003)
Encore Hotels of Columbus, LLC v. Preferred Fire Protection
765 N.E.2d 658 (Indiana Court of Appeals, 2002)
Dominiack Mechanical, Inc. v. Dunbar
757 N.E.2d 186 (Indiana Court of Appeals, 2001)
SLR Plumbing & Sewer, Inc. v. Turk
757 N.E.2d 193 (Indiana Court of Appeals, 2001)
Community Care Centers, Inc. v. Sullivan
701 N.E.2d 1234 (Indiana Court of Appeals, 1998)
Bennett Heating & Air Conditioning, Inc. v. NationsBank of Maryland
674 A.2d 534 (Court of Appeals of Maryland, 1996)
Browning v. Walters
616 N.E.2d 1040 (Indiana Court of Appeals, 1993)
City of Indianapolis v. Twin Lakes Enterprises, Inc.
568 N.E.2d 1073 (Indiana Court of Appeals, 1991)
First Wisconsin Trust Company v. Schroud
916 F.2d 394 (First Circuit, 1990)
First Wisconsin Trust Co. v. Schroud
916 F.2d 394 (Seventh Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
386 N.E.2d 724, 179 Ind. App. 557, 1979 Ind. App. LEXIS 1065, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indianapolis-raceway-park-inc-v-curtiss-indctapp-1979.