Encore Hotels of Columbus, LLC v. Preferred Fire Protection

765 N.E.2d 658, 2002 Ind. App. LEXIS 467, 2002 WL 467814
CourtIndiana Court of Appeals
DecidedMarch 28, 2002
Docket03A04-0108-CV-380
StatusPublished
Cited by5 cases

This text of 765 N.E.2d 658 (Encore Hotels of Columbus, LLC v. Preferred Fire Protection) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Encore Hotels of Columbus, LLC v. Preferred Fire Protection, 765 N.E.2d 658, 2002 Ind. App. LEXIS 467, 2002 WL 467814 (Ind. Ct. App. 2002).

Opinion

OPINION

NAJAM, Judge.

STATEMENT OF THE CASE

Preferred Fire Protection ("Preferred Fire") filed a cross-claim against Encore Hotels of Columbus, LL.C. ("Encore") seeking to recover payment for materials and labor it provided in the construction of *660 a hotel in Columbus. 1 Following a bench trial, the trial court entered judgment in favor of Preferred Fire in the amount of $16,745 plus interest and costs. Encore appeals from that judgment and presents several issues for our review, which we consolidate and restate as: whether the trial court erred when it concluded that Encore was unjustly enriched. 2

We affirm.

FACTS AND PROCEDURAL HISTORY

On April 11, 1997, Encore and S.C. Bod-ner Construction, Inc. ("Bodner") entered into a no-lien contract 3 for the construction of a hotel. As general contractor, Bodner was responsible for hiring and paying subcontractors to perform work on the project. Bodner hired Preferred Fire to construct a fire protection system for $54,000. By December 20, 1997, Preferred Fire had billed $37,950 for the work it had «done, and Bodner had paid Preferred Fire $34,155, with the rest held as retainage. On February 11, 1998, Preferred Fire billed Bodner $11,655 for its work done from December 21, 1997 through January 31, 1998, but Encore never paid Bodner for that work, and Bodner never paid Preferred Fire.

On February 4, 1998, Encore had terminated its contract with Bodner and took over as general contractor for the project. At that time, Preferred Fire had approximately two days' worth of work left, but it had to wait for another subcontractor to finish the ceilings in the hotel before it could finish the fire protection system. On February 18, 1998, Jim Huff, a representative of Encore, telephoned Tracy Hodges at Preferred Fire to request the following information: "all paperwork, proposals, ATA's (billings), what's owed[;] how much money to finish the project." Huff also inquired regarding whether Preferred Fire would be able to resume work on the project on February 20, 1998. Huff telephoned Delbert Donaldson, a representative of Preferred Fire, and told him that the work needed to be done in time for an inspection the following Monday. Donaldson told Huff that Preferred Fire needed some assurance from Encore that Encore would cover the overtime expenses required for work done over the weekend. Huff told Donaldson that he could not authorize such an agreement.

On February 19, 1998, Robert Peters, President of Preferred Fire, sent Huff a letter by facsimile, which read:

Dear Mr. Huff,

We have been informed that your firm will be taking over the completion and contractual obligation for subject job from Bodner Construction Inc. Our contract amount to date is $54,000, exelud-ing change order or additional work beyond the bid document.
We have been requested to return to the job on 2/20/98 to complete the remainder of our contract. Any overtime or additional work required in order to complete this project on time will be added to our above contract as part of our final contract payment.
*661 In order for us to continue forward, we must have an affidavit signed by a legal and authorized representative of [Encore] Construction that they will be responsible for a current remaining balance due to Preferred Fire Protection in the amount of $19,845, plus any and all additional cost incurred to complete this project per your new schedule.
Once this document is received in our office, (fax copy with hard copy to follow is acceptable), we will schedule our men for the next working day.
Please feel free to contact me if there are any questions.

Encore never responded to Peters' letter, so Preferred Fire did no further work on the project and retrieved its equipment from the construction site.

Thereafter, Encore hired a new company, United Fire Protection ("United Fire"), to complete the fire protection system at a cost of $18,732.87. When Encore did not pay either Bodner or Preferred Fire the $11,655 that Preferred Fire had billed for the work completed between December 21, 1997 and January 81, 1998, Preferred Fire filed its cross-claim against Encore to recover payment. Following a bench trial, the trial court entered judgment in favor of Preferred Fire in the amount of $11,655 plus $5,090 for retain-age, plus prejudgment interest and costs. This appeal ensued.

DISCUSSION AND DECISION

Where, as here, a party has requested specific findings and conclusions, we apply a two-tiered standard of review. Samar, Inc. v. Hofferth, 726 N.E.2d 1286, 1289 (Ind.Ct.App.2000), trams. denied. We must first determine whether the evidence supports the findings. Id. Then, we determine whether the findings support the judgment. Id. The findings are clearly erroneous when a review of the record leaves us firmly convinced that a mistake has been made. Id. We will disturb the judgment only where there is no evidence supporting the findings or the findings fail to support the judgment. Id.

Emeore contends that the trial court erred when it found in favor of Preferred Fire under the theory of unjust enrichment. To prevail on a claim of unjust enrichment, a plaintiff must establish that a measurable benefit has been conferred on the defendant under cireum-stances in which the defendant's retention of the benefit without payment would be unjust. Wright v. Pennamped, 657 N.E.2d 1223, 1229 (Ind.Ct.App.1995), trams. denied. For example, principles of equity prohibit unjust enrichment in cases where a party accepts the unrequested benefits another provides despite having the opportunity to decline those benefits. Id. at 12830.

Where, as here, an owner contracts with a general contractor to manage a project, and the general contractor hires subcontractors, the parties have voluntarily allocated the risks by contract, and the failure of the general contractor to perform does not generally give rise to an action for unjust enrichment against the owner. See Indianapolis Raceway Park, Inc. v. Curtiss, 179 Ind.App. 557, 386 N.E.2d 724, 726 (1979). However, Indiana courts have used the following four criteria to determine whether an owner has been unjustly enriched under those circumstances: 1) whether the owner impliedly requested the subcontractor to do the work; 2) whether the owner reasonably expected to pay the subcontractor, or the subcontractor reasonably expected to be paid by the owner; 3) whether there was an actual wrong perpetrated by the owner; and 4) whether the owner's conduct was so active and instrumental that the owner *662 "stepped into the shoes" of the contractor. Stafford v. Barnard Lumber Co., Inc., 581 N.E.2d 202, 204 (Ind.1988); Indianapolis Raceway Park, Inc., 386 N.E.2d at 727.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
765 N.E.2d 658, 2002 Ind. App. LEXIS 467, 2002 WL 467814, Counsel Stack Legal Research, https://law.counselstack.com/opinion/encore-hotels-of-columbus-llc-v-preferred-fire-protection-indctapp-2002.