State of Indiana Military Dept., State Armory Board of the State of Indiana, and Governor Mitch E. Daniels, Jr. v. Continental Electric Co., Inc.

971 N.E.2d 133, 2012 WL 2904183, 2012 Ind. App. LEXIS 334
CourtIndiana Court of Appeals
DecidedJuly 17, 2012
Docket45A05-11009-PL-465
StatusPublished
Cited by1 cases

This text of 971 N.E.2d 133 (State of Indiana Military Dept., State Armory Board of the State of Indiana, and Governor Mitch E. Daniels, Jr. v. Continental Electric Co., Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Indiana Military Dept., State Armory Board of the State of Indiana, and Governor Mitch E. Daniels, Jr. v. Continental Electric Co., Inc., 971 N.E.2d 133, 2012 WL 2904183, 2012 Ind. App. LEXIS 334 (Ind. Ct. App. 2012).

Opinion

OPINION

BAKER, Judge.

The State had an agreement with a general contractor for an airport construction project in Gary. There was no contract between the State and one of the subcontractors. But the trial court erroneously determined that the State had breached a contract between the State and the subcontractor. In this case, the subcontractor’s remedy for any alleged breach in these circumstances was against the general contractor.

Additionally, the trial court erred in concluding that the subcontractor was entitled to recover from the State on the basis of quantum meruit. Contrary to the subcon *135 tractor’s contention, there was no confusion in the main contract about what was— or was not—to be included in the agreement. Moreover, there has been no showing that the State unjustly retained a benefit without having paid for it.

Appellants-defendants State of Indiana Military Department, 1 State Armory Board of the State of Indiana, 2 and Governor Mitch E. Daniels, Jr. (collectively, Indiana Military), appeal the trial court’s judgment in favor of appellee-plaintiff Continental Electric Company, Inc. (Continental Electric), on its claim against Indiana Military for breach of contract and quantum meruit. Specifically, Indiana Military argues that the judgment must be set aside because it had paid the general contractor on a particular project in full, and that Continental Electric failed to meet the elements of a four-part test that relates to the entitlement of subcontractors to recover under the contract as a general contractor would. Moreover, Indiana Military maintains that Continental Electric failed to establish that a measurable benefit was conferred on Indiana Military and that the retention of alleged benefits without payment would be unjust.

For the reasons stated above, we conclude that the trial court erred in awarding judgment in Continental Electric’s favor. Thus, we reverse.

FACTS 3

A Project Manual for the Indiana National Guard Limited Army Aviation Support Facility, including bid documents, dated June 12, 2006, was prepared by Joint Forces Headquarters Indiana and CSO, the architect on the project. The primary purpose of the document preparation to solicit bids was for the construction of an aviation facility at the Gary/Chicago International Airport in Gary. CSO was both the project architect and construction administrator for Indiana Military.

Continental Electric is a family-owned company that specializes in electrical work, has had a long history of completing projects for the State of Indiana, and was experienced in handling the unique facets of such work. Bud Curry, a representative from Continental Electric, attended a pre-bid meeting on June 22, 2006. Alternate Number two that related to the installation of a generator at the facility was a topic of discussion at the meeting.

The Larson-Danielson Construction Company (Larson) submitted its bid of $15,558,120 for the primary contract and included prices for various alternatives to the projects on or about July 12, 2006. Larson’s bid was premised on estimates and bids that it had received from potential subcontractors, including Continental Electric. Continental Electric’s bid stated that it is “pleased to offer our proposal to furnish and install the labor, material and equipment necessary for the electrical portion for the above project, $1,794,660.” Tr. p. 143. Under one of the alternatives known as “Alternate 2,” Continental Electric stated “Diesel Generator, ADD $335,000.” Tr. Ex. 4, p. 143. Larson subsequently provided a list of sub-contractors to CSO and Indiana Military that included Continental Electric, which set *136 forth an amount of $1,794,000, for that company.

When Larson submitted its bid on the project, it indicated that it understood Alternate No. 2 was the provision of a diesel generator as specified in the Project Manual that included the packaged engine generators that were shown in various drawings. Larson’s understanding was that the Alternate No. 2 plan specifically did not include a concrete generator pad. Various sections of the project manual referred to incidental wiring and components that were needed to connect the generator at the Alternate 2 site.

On the other hand, Indiana Military maintained that while the generator itself was to be bid as Alternate No. 2, the wiring and other components of the generator should have been part of the base bid. Prior to execution of the agreement between the Indiana Military and Larson and the subcontract between Larson and Continental Electric, CSO prepared a “Clarification” of the Agreement. Paragraph 4 of Clarification No. 1 stated that

It was discussed in the prebid meeting that installation of the generator and all connections are to be included in the base bid. The description of Alternate 2 in the project manual states the concrete pad is to be provided in the base bid. Please clarify the intent of Alternate 2, Diesel Generator.
As discussed in the prebid meeting, the base bid shall include installation, final connections, startup and testing of the owner purchased generator. Alternate 2 shall include the generator only. Modify specifications to read as follows:
Section 01230—Alternates
A. Revise Section 01230-3.01, B., 1. to read:
1. In Base Bid, the Owner will provide the specified generator set only.
2. In Base Bid, the Contractor shall provide complete installation of the owner provided generator set including the concrete generator pad, all conduit and cabling as shown, final connections, startup and testing and as described in the drawings and specifications.

Tr. Ex. 7, p. 155.

The Project Manual described Alternate No. 2, as follows:

Alternate No. 2—Diesel Generator: State amount to be added to or deducted from Base Bid to provide diesel generator as specified in Section 16231, Packaged Engine Generators, as shown on Drawings.
1. Concrete Generator pad shall be included in base bid.

Tr. Ex. 2, p. 95-96.

Indiana Military accepted Larson’s bid on July 31, 2006. Thereafter, in September 2006, Larson contracted with Indiana Military for the base contract in the amount of $16,525,620 and a proposal under “Alternate # 1” in the amount of $972,500.

Continental Electric maintained that it was not bound by any verbal discussion of Alternate No. 2 at the pre-bid meeting because that discussion was not included in the written meeting minutes. Sometime after August 2, 2006, Continental Electric did obtain a copy of Clarification No. 1, which had been prepared by Dowdle, a CSO representative, but Continental Electric maintained that Clarification No. 1 was different than what was contained in the bid documents. According to Walton, Continental Electric had not understood at the time of its bid that any items associated with the generator were to be included in the base bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Claire's Boutiques, Inc. v. Brownsburg Station Partners LLC
997 N.E.2d 1093 (Indiana Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
971 N.E.2d 133, 2012 WL 2904183, 2012 Ind. App. LEXIS 334, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-indiana-military-dept-state-armory-board-of-the-state-of-indctapp-2012.