Stelko Electric, Inc. v. Taylor Community Schools Building Corp.

826 N.E.2d 152, 2005 Ind. App. LEXIS 721, 2005 WL 995321
CourtIndiana Court of Appeals
DecidedApril 29, 2005
Docket34A02-0312-CV-1071
StatusPublished
Cited by15 cases

This text of 826 N.E.2d 152 (Stelko Electric, Inc. v. Taylor Community Schools Building Corp.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stelko Electric, Inc. v. Taylor Community Schools Building Corp., 826 N.E.2d 152, 2005 Ind. App. LEXIS 721, 2005 WL 995321 (Ind. Ct. App. 2005).

Opinion

OPINION

KIRSCH, Chief Judge.

Stelko Electric, Inc. (“Stelko”) appeals the trial court’s grant of summary judgment in favor of Taylor Community Schools Building Corporation (“Taylor”) and Hagerman Construction Corporation (“Hagerman”). 1 On appeal, Stelko raises the following restated issues:

I. Whether the trial court erred in granting summary judgment to Taylor on the basis that the terms of the contract between Stelko and Taylor barred Stelko’s breach of contract claims.
II. Whether it was. error for the trial court to grant Hagerman summary judgment on the basis that the “economic loss doctrine” barred Stelko’s negligence claim.
We affirm.

FACTS AND PROCEDURAL HISTORY

This controversy arose in connection with Taylor’s project to convert an existing high school into a combined high school and middle school (“Project”). The Project required renovation of existing buildings as well as construction of new additions. In 1996, Taylor contracted with Schmidt Associates, Inc. (“Schmidt”) to provide architectural services for the design and construction of the Project. Approximately one year later, Taylor entered into a contract with Hagerman to provide construction management services for the Project (“Hagerman/Taylor Contract”).

On March 25, 1998, Taylor entered into a contract with Stelko (“Stelko/Taylor Contract”), pursuant to which Stelko agreed to supply all of the Project’s electrical work between a commencement date in March 1998 and a substantial completion date in December 1999. Appellant’s Appendix at 28-29. The General Conditions of the Contract for Construction (“General Conditions”)—a form document generated by the American Institute for Architects that sets forth construction conditions—governed conditions on the Project. Appellant’s Appendix at 348, 386. A second form document, titled Supplementary Conditions, in turn, modified the General Conditions. Id. at 365.

Stelko’s December 1999 completion date was estimated on the basis that the work would be completed while the school buildings were occupied with staff, faculty, and multiple contractors during most of the Project. Prior to contracting for the work, Stelko knew of the timing of the Project and the conditions under which work would be completed.

*154 Stelko began its work in the spring of 1998, but immediately encountered unforeseen obstacles, including: defects in the design drawings; lack of compliance by Taylor and Hagerman with the construction schedule; interference due to student tours through the Project site; interference with Stelko’s access to both materials and the Project site; and damage from a June 1998 tornado. 2 Stelko also noted that the Project was further hampered by Taylor’s unilateral decision to shorten the completion deadline by four months. As a result of the tornado and the need for storm repair, the Stelko/Taylor Contract was modified. Taylor and Stelko entered into ten separate change orders between April 1998 and June 1999, which resulted in increasing the contract price by more than $250,000.00. Id. at 208. '

According to the General and Supplementary Conditions of the contract, Stelko was required to advise Taylor if it intended to make a claim for an increase in the contract sum or an extension of time within twenty-one days after the event giving rise to such claim. Id. Stelko substantially completed the Project on August 20, 1999, four months early, by hiring additional laborers and incurring unanticipated costs. Nevertheless, it never made either a claim for an extension of time or a claim for an increase in contract sum within the required twenty-one days of incurring the costs. Instead, Stelko waited until four months after the construction had been completed to claim Taylor owed it cost overruns of more than one million dollars. Taylor refused to pay the additional costs on the grounds that Stelko should have sought an extension of time, and could not now be reimbursed for a unilateral increase in manpower.

On February 1, 2000, Stelko filed suit against Taylor seeking damages for breach of contract, breach of implied warranty of suitability of plans and specifications, breach of implied covenant of good faith and fair dealing, and quantum meruit. The complaint also alleged negligence on the part of Hagerman. 3

In May 2003, Taylor and Hagerman filed a joint motion for summary judgment and argued that they were entitled to judgment as a matter of law because: (1) Stelko’s claim for money damages was barred by Section 8.3.4, the “no damages for delay” clause, which provided that the only remedy available to a contractor is an extension of time; and (2) the negligence claim against Hagerman was barred both by the “economic loss doctrine” and because Stelko lacked contractual privity with Hagerman and was not an intended third-party beneficiary of the Hager-man/Taylor Contract. Stelko filed its response to the joint motion for summary judgment, along with its designation of evidence, arguing that Section 8.3.4 did not bar its claims because its monetary damages arose from acceleration of the contract and not from delay. Stelko, likewise, argued that the negligence claim was not barred. In their reply, Taylor and Hager-man reiterated their original arguments and elaborated on the argument that the tornado, instead of interfering with the *155 Project, allowed it to be completed four months ahead of schedule.

The trial court held a hearing and granted Taylor and Hagerman’s joint motion for summary judgment noting:

[W]ith regard to Counts V and VI [the negligence claims against Hagerman and Schmidt], the Motion for Summary Judgment is granted. Judgment is entered on behalf of the Defendants Hag-erman and Schmidt. The only question of fact that has been put forth by the Plaintiff on this issue is what the duties were under the contract and what the intent was. I think these only become material in the event that a suit for negligence is allowed. All of the law that I’ve seen indicates that the facts in this case bar such a suit. I conclude that there was no privity. There was no third party beneficiary, and there was no actual knowledge of the exception that—pointed [sic] out by Plaintiff. And I have to agree with the Defendants that the questions I’ve asked are very material. There is nothing in Plaintiffs Brief or argument that propounds any facts that would be material in construing the—the defectiveness or—that’s not a good word, the character of the exculpatory clause which is the key issue, and when queried, nobody can come up with those facts here today' even. So in addition, the Defendant’s Motion for Summary Judgment with regard to Counts I through IV is granted. Court finds there is no factual—-no dispute as to any material fact with regard to those claims. That’s all.

Transcript at 37. Stelko now appeals the summary judgment with respect to Taylor and Hagerman.

DISCUSSION AND DECISION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tonia Land v. IU Credit Union
Indiana Supreme Court, 2023
Lathan Co. v. State
237 So. 3d 1 (Louisiana Court of Appeal, 2017)
The Peoples State Bank v. Benton Township of Monroe County, Indiana
28 N.E.3d 317 (Indiana Court of Appeals, 2015)
Toby D. Pope v. City of Lawrenceburg
Indiana Court of Appeals, 2014
Ponziano Construction Services, Inc. v. Quadri Enterprises, LLC
980 N.E.2d 867 (Indiana Court of Appeals, 2012)
Kb Home Indiana Inc. v. Rockville Tbd Corp.
928 N.E.2d 297 (Indiana Court of Appeals, 2010)
City of East Chicago v. East Chicago Second Century, Inc.
878 N.E.2d 358 (Indiana Court of Appeals, 2007)
Reginald Martin Agency, Inc. v. Conseco Medical Insurance
388 F. Supp. 2d 919 (S.D. Indiana, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
826 N.E.2d 152, 2005 Ind. App. LEXIS 721, 2005 WL 995321, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stelko-electric-inc-v-taylor-community-schools-building-corp-indctapp-2005.