Howell Contractors, Inc. and Fidelity and Deposit Company of Maryland v. Calumet Civil Contractors, Inc.

CourtIndiana Court of Appeals
DecidedOctober 4, 2013
Docket49A05-1305-PL-232
StatusUnpublished

This text of Howell Contractors, Inc. and Fidelity and Deposit Company of Maryland v. Calumet Civil Contractors, Inc. (Howell Contractors, Inc. and Fidelity and Deposit Company of Maryland v. Calumet Civil Contractors, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howell Contractors, Inc. and Fidelity and Deposit Company of Maryland v. Calumet Civil Contractors, Inc., (Ind. Ct. App. 2013).

Opinion

Pursuant to Ind.Appellate Rule 65(D), Oct 04 2013, 5:44 am this Memorandum Decision shall not be regarded as precedent or cited before any court except for the purpose of establishing the defense of res judicata, collateral estoppel, or the law of the case.

ATTORNEYS FOR APPELLANTS: ATTORNEYS FOR APPELLEE:

ZACHARY J. EICHEL DAVID B. VORNEHM MICHAEL L. EINTERZ SEAN T. DEVENNEY MICHAEL L. EINTERZ, JR. WILLIAM E. KELLEY, JR. Einterz & Einterz Drewry Simmons Vornehm, LLP Zionsville, Indiana Carmel, Indiana

IN THE COURT OF APPEALS OF INDIANA

HOWELL CONTRACTORS, INC., and ) FIDELITY AND DEPOSIT COMPANY OF ) MARYLAND, ) ) Appellants-Defendants, ) ) vs. ) No. 49A05-1305-PL-232 ) CALUMET CIVIL CONTRACTORS, INC., ) ) Appellee-Plaintiff. )

APPEAL FROM THE MARION SUPERIOR COURT The Honorable Thomas J. Carroll, Judge Cause No. 49D06-1001-PL-891

October 4, 2013

MEMORANDUM DECISION - NOT FOR PUBLICATION

BAILEY, Judge Case Summary

Howell Contractors, Inc. (“Howell”) and Fidelity and Deposit Company of Maryland

(“Fidelity”), (collectively, “Howell”), appeal the grant of partial summary judgment to

Calumet Civil Contractors, Inc. (“Calumet”) on Calumet’s breach of contract, unjust

enrichment, and surety claims and also appeal a final summary judgment order entered in

response to Howell’s motion to reconsider and motion for clarification. We affirm the grant

of partial summary judgment as to liability, reverse the entry of summary judgment on

damages, and remand for further proceedings.

Issues

Howell presents two issues for review:

I. Whether partial summary judgment on liability was improvidently

granted; and

II. Whether summary judgment on damages was improvidently granted.

Facts and Procedural History

In late 2007, Howell had submitted a bid to act as the general contractor for the City

of Indianapolis (“the City”) on a project known as the 10th and Mitthoefer Septic Tank

Elimination Program (“the Project”), and in turn requested bids for subcontracted paving

work. Calumet’s proposal for the paving work, dated November 21, 2007 (“the Proposal”),

listed the “scope of work” as follows:

5 HMA for Driveway Repair 35.0 Ton $ 180.00 $ 6,300.00 6 HMA 9.5mm Surface 1,700.0 Ton $ 60.00 $102,000.00 7 HMA 19mm Intermediate 7,800.0 Ton $ 50.00 $390,000.00 8 HMA 25mm Base 130.0 Ton $ 78.00 $ 10,140.00

2 52 Mobilization/Demobilization 1.0 LSUM $15,700.00 $ 15,700.00 56 Temporary CMA 25mm 3,500.0 Ton $ 89.00 See Below

TOTAL $524,140.00

(App. 23.) The Proposal also included price escalation clauses in the “Clarifications” section, as follows:

Q. All work performed after November 30, 2008 will be subject to additional escalation.

R. This price shall be valid for ten (10) days from the bid date. After this time, all prices are subject to adjustment due to the volatile nature of liquid asphalt pricing related to the cost of oil.

(App. 24.)

On December 31, 2007, Howell entered into an agreement with the City to act as the

general contractor for the Project. Howell furnished, through Fidelity, a payment bond on the

Project equal to the amount of the contract.

On March 13, 2008, Howell and Calumet entered into a contract for the paving work,

whereby Calumet agreed “to perform the work identified in the Technical Specifications

Section 400 in accordance with the Project’s Contract Documents” (“the Subcontract.”)

(App. 25.) The Proposal was specifically incorporated into the Subcontract.1 Howell’s

contract with the City did not contain parallel escalation clauses.

Over the course of the performance of the Subcontract, certain events occurred

relative to the sums due from Howell to Calumet. On November 7, 2008, Matt Young of

Howell sent an e-mail to Calumet’s project manager:

1 Article 9 provided in part: “Pricing is as noted on the attached proposal which is made part of this contract.” (App. 27.)

3 I am writing in response to your voice mail about additional work. What I understand is that Clark Dietz will be paying for a portion of 10th Street that we disturbed. Apparently there is a small portion outside the work limits that they are not paying for and there [are] some inside the limits they are paying for. We will pay you the agreed quantity for work that is outside the limits paid by Clark Dietz. Currently this spot and a small spot on Malvina are the only spots I know of that are outside of the planned project scope. Please continue to have your field guys and our field guys agree to these quantities each day.

(App. 81.) A third party paid for a portion of the cost to repair the damaged area, and

Calumet claimed entitlement to $1,021.05 from Howell. Howell did not pay Calumet the

claimed amount. Also, during 2008, the price of asphalt increased significantly. Calumet

notified Howell and Howell submitted a request to the City for the price escalation. When

the City refused to pay Howell the escalated price, Howell refused to pay Calumet.

Finally, the scope of the work was changed with respect to Item 7. On June 16, 2008,

the City issued Work Directive Change 8 providing that the depth of the asphalt would be

changed from 6 inches to 3 inches. The same area was to be covered, but with less material.

Calumet claimed that its bid had been calculated with labor costs divided by tons as opposed

to area, and that, with the labor and mobilization requirements constant, but the quantity

decreased, a higher unit cost was appropriate. The City issued Change Order 4 to Howell,

providing Howell with a price adjustment so that Howell was paid $61.00 per ton. When

Calumet sought compensation from Howell, Howell “forwarded” a request to the City,

without noting the existence of Change Order 4. (App. 360.) A representative of the City

responded that the City could not accept a claim from a subcontractor and rejected the

request. Howell did not execute a Change Order for Calumet’s benefit and did not pay

4 Calumet above the $50.00 per ton for Item 7 originally contemplated.2

On January 8, 2010, Calumet filed a Complaint against Howell and Fidelity, claiming

that Howell had wrongly refused to pay $1,021.05 for work performed on April 2, 2009,

$44,965.12 for the increase in the price of liquid asphalt, and $79,458.00 due to a significant

change in the scope of work (Item 7). Calumet alleged that Howell’s failure to pay

constituted a default under the Fidelity payment bond.

On December 2, 2010, Calumet filed a motion for partial summary judgment. On

February 11, 2011, Howell filed its response and a cross-motion for summary judgment. On

June 29, 2011, the trial court conducted a hearing on the respective motions and denied both.

The matter was set for a bench trial.

On September 11, 2012, at a pre-trial conference in chambers, the parties advised the

trial court of an agreement as to the conduct of proceedings. An Agreed Entry was submitted

on September 25, 2012, whereby the parties agreed that the trial date should be vacated and

the trial court should re-examine motions for partial summary judgment as to liability only.

The parties were afforded the opportunity to submit supplemental briefs. On September 21,

2012, the trial court approved the Agreed Entry.

On March 22, 2013, the trial court issued its “Entry on Summary Judgment” providing

that Calumet’s “Motion for Partial Summary Judgment on contractual liability is hereby

granted.” (App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Payton v. Hadley
819 N.E.2d 432 (Indiana Court of Appeals, 2004)
AutoXchange. Com, Inc. v. Dreyer and Reinbold, Inc.
816 N.E.2d 40 (Indiana Court of Appeals, 2004)
Huntington v. Riggs
862 N.E.2d 1263 (Indiana Court of Appeals, 2007)
Landmark Health Care Associates L.P.-1989-A v. Bradbury
671 N.E.2d 113 (Indiana Supreme Court, 1996)
Best Homes, Inc. v. Rainwater
714 N.E.2d 702 (Indiana Court of Appeals, 1999)
In Re Guardianship of Phillips
926 N.E.2d 1103 (Indiana Court of Appeals, 2010)
Bayh v. Sonnenburg
573 N.E.2d 398 (Indiana Supreme Court, 1991)
Kiltz v. Kiltz
708 N.E.2d 600 (Indiana Court of Appeals, 1999)
Indiana Farmers Mutual Insurance Group v. Blaskie
727 N.E.2d 13 (Indiana Court of Appeals, 2000)
Cowe Ex Rel. Cowe v. Forum Group, Inc.
575 N.E.2d 630 (Indiana Supreme Court, 1991)
Stelko Electric, Inc. v. Taylor Community Schools Building Corp.
826 N.E.2d 152 (Indiana Court of Appeals, 2005)
Otto v. Park Garden Associates
612 N.E.2d 135 (Indiana Court of Appeals, 1993)
Yates v. Johnson County Board of Commissioners
888 N.E.2d 842 (Indiana Court of Appeals, 2008)
Crossno v. State
726 N.E.2d 375 (Indiana Court of Appeals, 2000)
Coleman v. Coleman
949 N.E.2d 860 (Indiana Court of Appeals, 2011)
Indiana Regional Recycling, Inc. v. Belmont Industrial, Inc.
957 N.E.2d 1279 (Indiana Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Howell Contractors, Inc. and Fidelity and Deposit Company of Maryland v. Calumet Civil Contractors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/howell-contractors-inc-and-fidelity-and-deposit-co-indctapp-2013.