Harper v. Goodin

409 N.E.2d 1129, 78 Ind. Dec. 182, 1980 Ind. App. LEXIS 1651
CourtIndiana Court of Appeals
DecidedSeptember 9, 1980
Docket1-1279A371
StatusPublished
Cited by29 cases

This text of 409 N.E.2d 1129 (Harper v. Goodin) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harper v. Goodin, 409 N.E.2d 1129, 78 Ind. Dec. 182, 1980 Ind. App. LEXIS 1651 (Ind. Ct. App. 1980).

Opinion

*1132 NEAL, Judge.

STATEMENT OF THE CASE

This is an appeal from the Vanderburgh Superior Court by defendants James B. Harper and Jean L. Harper as two appellants (Harpers) from an adverse judgment for breach of contract and punitive damages, and by defendant Bert Claspell Heating, Cooling and Electric, Inc., as the other appellant (Claspell) from an adverse judgment for slander of title and punitive damages. Both judgments were in favor of the plaintiffs-appellees Estel Goodin and Martha L. Goodin (Goodins) after verdicts rendered by a jury.

We affirm in part and reverse in part.

STATEMENT OF THE FACTS

The Goodins, on September 13, 1974, purchased for $34,350 a parcel of real estate from the Harpers containing a residence, newly constructed by the Harpers who built it for the purpose of' sale. The sum of $2,500 was held in escrow by a bank to be paid to the Harpers when the Goodins were satisfied that the work was completed. The Goodins occupied the residence on September 24, 1974, and within five or six weeks a controversy arose relative to defects.

Evidence most favorable to the judgment disclosed the following major defects: (1) furnace not working properly, (2) defective tile fitting, (3) unlevel floors, and doors that would not close, (4) water problems in the basement and rusty furnace which had fallen, pulling ductwork loose, (5) kitchen sink pulled loose from the wall, (6) defective concrete walk, (7) defective plumbing, (8) defective septic system, and (9) absence of cold air ducts: In addition, there were numerous other lesser defects. The Goodins introduced evidence from professional tradesmen to show that the cost of repairing the defects would be $500-$750 to $4,316. Estel Goodin testified that the house was worth $14,000 less than it would be worth absent the defects.

The Harpers, who had no workmen themselves, had subcontracted the construction to various workmen. The Harpers sent workmen on occasions to repair the defects. Ultimately, when the parties were unable to resolve the dispute, the Harpers offered the Goodins their money back and later offered them $36,000 to rescind the transaction. The Goodins refused for various reasons.

Claspell was a subcontractor employed by the Harpers to do certain mechanical trades within its expértise. Its last work was performed and last materials were furnished sometime prior to the sale on September 13, 1974. In the late fall, Bert Claspell, the president and principal of the corporation, who had, according to the record, at least 15 years experience in the trade, became alarmed that he might not get his money from the Harpers. He told the Goodins that the Harpers had promised him that he would be paid from the $2,500 escrow account. He further demanded payment from the Goodins and said that if he were not paid, he would file a mechanic’s lien on the Goodins’ property. The Goodins refused, and on January 25, 1975, Claspell filed its mechanic’s lien. The Harpers paid Clas-pell about a week later, but Bert Claspell refused to release the lien even after demand by the Goodins and their attorney. He claimed that he filed the lien and refused to release it upon advice of counsel.

While this case was filed and tried as one action, there are in reality two separate actions. One action was against the Har-pers for breach of contract and punitive damages, and the other was against Clas-pell for slander of title and punitive damages. The jury returned verdicts against the Harpers for $10,000 compensatory damages and $7,500 punitive damages, and against Claspell for $385 compensatory damages and $2,500 punitive damages.

ISSUES

The defendants have preserved and argued on appeal the following alleged errors:

*1133 I. The awarding of punitive damages for alleged defective construction.
II. The awarding of excessive compensatory damages for alleged defective construction.
III. The awarding of compensatory damages for alleged slander of title.
IV. The awarding of punitive damages for alleged slander of title.
VI. The giving and reading to the jury of plaintiffs’ instruction No. 1 that allegedly misstated the law regarding punitive damages.

DISCUSSION AND DECISION

Issue I. Punitive damages for defective construction

Under this heading the Harpers allege the trial court committed error in denying their motion for judgment on the evidence regarding punitive damages for breach of contract for the defective construction.

In First Federal Savings and Loan Association of Indianapolis v. Mudgett, (1979) Ind.App., 397 N.E.2d 1002, this court engaged in an extensive review of the Indiana law of punitive damages arising out of breach of contract. We find it unnecessary to repeat that discussion in toto but refer the parties to it and the cases cited therein. Briefly, First Federal Savings and Loan Association of Indianapolis, recited that, as a general rule, punitive damages are not "recoverable in contract actions, but two exceptions do exist. The first exception is where the breach is accompanied by conduct which also, independently, establishes the elements of a common law tort such as fraud. The other exception is where a serious wrong, tortious in nature, has been committed in an instance in which the public interest would be served by the deterrent effect punitive damages would have on the conduct of the wrongdoer and parties similarly situated.

The promisor’s motive for breaching a contract is generally regarded as irrelevant because the promisee will be compensated for all damages proximately resulting from the promisor’s breach. Where the facts surrounding the promisor’s breach indicate substandard business conduct, the promisee may also enjoy a limited sense of requital in taking his business elsewhere in the future but he is not entitled to mulct the promisor in punitive damages.

Something more than a state of mind described as heedless disregard of the consequences is required for the imposition of punitive damages in breach of contract cases. Actual malice, or wantonness from which the law can imply malice, must be shown. The word “reprehensible” is used, as where there is conscious and deliberate conduct. Deceit is involved. Negligent conduct or incompetence is insufficient.

The Goodins’ position on punitive damages presents an anamoly. While they characterize the house in their brief as “a frightful example of one built below standards,” they refused the refund of their money. The evidence disclosed in the Statement Of The Facts fails to meet the sufficiency required for punitive damages in breach of contract cases. In support of punitive damages, the quality of construction was characterized, at best, as “extremely poor workmanship.” We find no evidence that the Harpers’ conduct could be described as an intentional tort, fraudulent, reprehensible, deceitful, false representation, or oppression commingled in the controversy, as required by our analysis in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Izynski v. Chicago Title Insurance Co.
963 N.E.2d 592 (Indiana Court of Appeals, 2012)
Crider & Crider, Inc. v. Downen
873 N.E.2d 1115 (Indiana Court of Appeals, 2007)
Gomez v. LIVING STONES FELLOWSHIP CHURCH, INC.
858 N.E.2d 1072 (Indiana Court of Appeals, 2006)
Tipmont Rural Electric Membership Corp. v. Fischer
697 N.E.2d 83 (Indiana Court of Appeals, 1998)
Henson v. CSC Credit Services
830 F. Supp. 1204 (S.D. Indiana, 1993)
Davis v. Sponhauer
574 N.E.2d 292 (Indiana Court of Appeals, 1991)
Johnson v. Naugle
557 N.E.2d 1339 (Indiana Court of Appeals, 1990)
Jordan v. Talaga
532 N.E.2d 1174 (Indiana Court of Appeals, 1989)
Bud Wolf Chevrolet, Inc. v. Robertson
508 N.E.2d 567 (Indiana Court of Appeals, 1987)
Rose Acre Farms, Inc. v. Cone
492 N.E.2d 61 (Indiana Court of Appeals, 1986)
Lee & Mayfield, Inc. v. Lykowski House Moving Engineers, Inc.
489 N.E.2d 603 (Indiana Court of Appeals, 1986)
Dunkelbarger Construction Co. v. Watts
488 N.E.2d 355 (Indiana Court of Appeals, 1986)
Terpstra v. Farmers and Merchants Bank
483 N.E.2d 749 (Indiana Court of Appeals, 1985)
Hamilton County Bank v. Hinkle Creek Friends Church
478 N.E.2d 689 (Indiana Court of Appeals, 1985)
Miller Pipeline Corp. v. Broeker
460 N.E.2d 177 (Indiana Court of Appeals, 1984)
Gintert v. Howard Publications, Inc.
565 F. Supp. 829 (N.D. Indiana, 1983)
Rowland v. Lepire
662 P.2d 1332 (Nevada Supreme Court, 1983)
D & T Sanitation, Inc. v. State Farm Mutual Automobile Insurance
443 N.E.2d 1207 (Indiana Court of Appeals, 1983)
Freiburger v. Fry
439 N.E.2d 169 (Indiana Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
409 N.E.2d 1129, 78 Ind. Dec. 182, 1980 Ind. App. LEXIS 1651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harper-v-goodin-indctapp-1980.