Rowland v. Lepire

662 P.2d 1332, 99 Nev. 308, 1983 Nev. LEXIS 449
CourtNevada Supreme Court
DecidedApril 29, 1983
Docket13495
StatusPublished
Cited by48 cases

This text of 662 P.2d 1332 (Rowland v. Lepire) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rowland v. Lepire, 662 P.2d 1332, 99 Nev. 308, 1983 Nev. LEXIS 449 (Neb. 1983).

Opinion

*310 OPINION

Per Curiam:

This is an appeal involving construction of a substantial residence by appellant, Rowland Corporation, for respondents, Eugene and Judy Lepire, husband and wife. Appellants contend that the trial court committed several errors in (1) finding that the express contract between appellants and respondents was modified rather than abandoned; (2) finding sufficient evidence supported respondents’ claim of slander of title; (3) awarding respondents punitive damages; (4) awarding respondents attorney’s fees; and (5) finding sufficient evidence upon which to base application of the alter ego doctrine.

Appellants Glen Rowland and Martin Rowland are officers, directors and shareholders of the Rowland Corporation. In July of 1977, the Rowland Corporation was issued a class B-2 general contractor’s license with an authorized limit of $60,000. In April of 1978, appellants entered into a contract with the Lepires to construct a home for them in Carson City. The contract was for a total price of $119,000, less certain offsets and plus any extras the Lepires might request during the course of construction. The contract provided for four progress payments through completion. It did not provide for a compjetion date.

Construction began in April of 1978. During the course of construction, numerous changes were requested by the Lepires. Among other things, these changes increased the floor space in the house from 4,500 square feet to 6,500 square feet and *311 raised the house several inches. The foundations and outside dimensions remained the same. The Lepires made payments on the contract ahead of schedule and paid for extra labor and materials as requested.

In early December, problems began developing between the parties. A lien claim by a subcontractor hired pursuant to a contract with the Rowland Corporation had been filed in October of 1978. In addition, the Meek Lumber Company gave notice of its intent to file a lien against the residence. During this same period, Glen Rowland prematurely requested an additional payment.

These events precipitated a meeting between Glen Rowland and the Lepires on December 13, 1978. The district court found that an oral modification of the contract resulted from that meeting. Shortly thereafter, a controversy arose at the job site, causing the Rowlands to refuse further performance despite requests for completion by the Lepires. Instead, the Rowlands, upon advice of their attorney, filed a lien against the project for $68,000 on December 22, 1978. Recordation of the lien resulted in the Lepires’ loss of an anticipated loan to be secured by the home. They were, nevertheless, able to obtain a personal loan at a higher interest rate.

As a consequence, the Lepires commenced this action in April of 1979, alleging breach of contract, slander of title and defamation. The defamation claim was later dismissed. In August 1979, the Rowland Corporation filed suit against the Lepires, alleging breach of contract, unjust enrichment and abuse of process. The two cases were eventually consolidated and the Rowland Corporation complaint was treated as a counterclaim in the Lepires’ suit. Subsequently, a bench trial was conducted. The lower court found that the express contract had been modified and that appellants had materially breached the contract. Predicated on the foregoing findings and conclusions, the court awarded damages for the cost of completion, for the cost of correcting defective construction and for paying bills which the Rowland Corporation had incurred and was obligated to pay. Additionally, the court found that the lien made of record by the corporation constituted slander of title and awarded special damages and punitive damages in the amount of $15,000. Further, the court awarded the Lepires $12,000 in attorney’s fees. Finally, the court found that the Rowland Corporation was the alter ego of Glen Rowland and Martin Rowland and entered a personal judgment against the Rowlands in the approximate sum of $65,000. Appellants appeal, challenging every portion of the judgment.

*312 1. The Express Contract.

Appellants initially contend that the lower court erred in failing to find that the express contract between the parties was abandoned. They contend that because the completed house varied extensively from the house they contracted to build, the original contract was abandoned. They assert that because the express contract was abandoned, they are entitled to a quantum meruit recovery. Appellants rely on the case of Paterson v. Condos, 55 Nev. 134, 28 P.2d 499 (1934), to establish this position.

In Paterson, the trial court had found that where the provisions of an express contract were extensively changed during the course of construction, the express contract had been abandoned with the consent, acquiescence and direction of the defendant. On appeal, we held there was sufficient evidence to support the trial court’s conclusion. In the present case, no such finding was made by the trial court; rather, it found that the contract had been modified and, impliedly, that no abandonment had occurred.

On appeal, the issue before this court is whether the lower court’s finding is supported by substantial evidence. Jacobson v. Best Brands, Inc., 97 Nev. 390, 632 P.2d 1150 (1981); Clark Co. Sports v. City of Las Vegas, 96 Nev. 167, 606 P.2d 171 (1980). It is the prerogative of the trier of fact to evaluate the credibility of witnesses and determine the weight of their testimony. Jacobson v. Best Brands, Inc., supra. Where there is substantial evidence to support the findings of the trial court, this court will affirm the judgment even though the evidence is conflicting. Id.; Clark Co. Sports v. City of Las Vegas, supra. Only in rare circumstances will changes in the course of construction be so extensive as to require the conclusion as a matter of law that a contract was abandoned. Modern Builders, Inc. of Tacoma v. Manke, 615 P.2d 1332 (Wash.Ct.App. 1980). Our review of the record demonstrates that the evidence in support of the findings of the trial court is substantial and does not require a conclusion as a matter of law that the express contract was abandoned.

In light of our resolution of the issue of the existence of an express contract, the issue of whether “unclean hands” bars appellants’ rights to a quantum meruit recovery need not be addressed.

2. Slander of Title.

Appellants next contend that the evidence does not support the trial court’s finding that their actions in perfecting the labor and materialmen’s lien constituted slander of title. We agree.

*313

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acor Vs. Bulloch C/W 80947/80948
Nevada Supreme Court, 2021
Meiri v. Hayashi
Nevada Supreme Court, 2018
Phillips v. Carlton Energy Group, LLC
475 S.W.3d 265 (Texas Supreme Court, 2015)
David Philip v. Bac Home Loans Servicing
573 F. App'x 637 (Ninth Circuit, 2014)
In re: Armin D. Van Damme
Ninth Circuit, 2013
Jsa, LLC v. Golden Gaming, Inc.
Nevada Supreme Court, 2013

Cite This Page — Counsel Stack

Bluebook (online)
662 P.2d 1332, 99 Nev. 308, 1983 Nev. LEXIS 449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rowland-v-lepire-nev-1983.