Kevin Walsh v. Chris Sweeney Construction, Inc.

CourtIndiana Court of Appeals
DecidedJanuary 25, 2012
Docket17A05-1107-PL-370
StatusUnpublished

This text of Kevin Walsh v. Chris Sweeney Construction, Inc. (Kevin Walsh v. Chris Sweeney Construction, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kevin Walsh v. Chris Sweeney Construction, Inc., (Ind. Ct. App. 2012).

Opinion

Pursuant to Ind.Appellate Rule 65(D), this Memorandum Decision shall not be regarded as precedent or cited before FILED any court except for the purpose of Jan 25 2012, 8:53 am establishing the defense of res judicata, collateral estoppel, or the law of the case. CLERK of the supreme court, court of appeals and tax court

ATTORNEY FOR APPELLANT: ATTORNEY FOR APPELLEE:

JAMES A. McENTARFER ADAM C. SQUILLER Stout & McEntarfer, P.C. Squiller Law Office, P.C. Angola, Indiana Auburn, Indiana

IN THE COURT OF APPEALS OF INDIANA

KEVIN WALSH, ) ) Appellant-Defendant, ) ) vs. ) No. 17A05-1107-PL-370 ) CHRIS SWEENEY CONSTRUCTION, INC., ) ) Appellee-Plaintiff. )

APPEAL FROM THE DEKALB SUPERIOR COURT The Honorable Monte L. Brown, Judge Cause No. 17D02-0910-PL-64

January 25, 2012

MEMORANDUM DECISION - NOT FOR PUBLICATION

BAILEY, Judge Case Summary

Appellant-defendant Kevin Walsh (“Walsh”) appeals the trial court’s order

foreclosing Appellee-plaintiff Chris Sweeney Construction, Inc.’s (“Sweeney Construction”)

mechanic’s lien on his home, awarding Sweeney Construction unjust enrichment damages for

unpaid labor services and attorney’s fees, and denying his counterclaims against Sweeney

Construction. We affirm and remand for correction of scrivener’s error.

Issues

Walsh presents three issues for our review, which we restate as:

I. Whether the trial court erred in interpreting the Indiana Home Improvement Contract Act (“HICA”) because it:

(a) Allowed Sweeney Construction to pursue foreclosure of its mechanic’s lien and unjust enrichment damages, even though it did not provide a written contract to Walsh that complied with the HICA; and

(b) Denied his counterclaim based upon Sweeney Construction’s non- compliance with HICA;

II. Whether the trial court erred by foreclosing on Sweeney Construction’s mechanic’s lien; and

III. Whether the trial court’s computation of unjust enrichment damages is supported by evidence in the record.

Facts and Procedural History

Chris Sweeney (“Sweeney”) is the President of Sweeney Construction, a company that

performs miscellaneous construction projects primarily in Steuben County, Indiana. Walsh

owns a house on the other side of a lake from Sweeney’s residence. In August 2008,

Sweeney heard from Walsh’s mother that Walsh was planning a renovation project on his

2 home, so Sweeney met with Walsh, Walsh’s parents, and Walsh’s friend, Frank Affatigato

(“Affatigato”) to discuss the project. Sweeney submitted a bid for certain portions of the

work, but Walsh rejected it because it was too high.

Sometime later, Walsh called Sweeney, the two met, and Walsh asked Sweeney to

submit bids for other parts of the renovation project. Sweeney submitted two written bids,

one to frame the garage and breezeway for $7,100 and the other to frame the proposed

screened patio area on the back of the house for $8,300. Walsh accepted the bids, but

Sweeney did not draw up a written contract and Walsh never asked for one.

Sweeney began work, but the job was “a disaster” because the renovation project was

disorganized, and “things would change all the time.” Tr. 24-25. One of Sweeney’s

employees testified that “[he] didn’t quite know what was going on…from one day to the

next” and “there was…no one running the show.” Tr. 86. Although Affatigato claimed at

trial to be the project’s general contractor, Sweeney testified that he didn’t know what

Affatigato’s role was on the project, and that Affatigato did not act like the general contractor

and he did not consider him as such. Instead, Affatigato performed his own job on the site,

the stone and masonry work, and did not provide Sweeney with instructions on a daily basis.

During the construction, Walsh did not live in the house,1 and instead visited on weekends to

inspect the project. After these weekend inspections, Walsh made several changes to the

original plans that both he and Affatigato conveyed to Sweeney. Sweeney informed Walsh

that changes in the work would require a price increase, but Walsh replied that he wanted the

1 Walsh’s primary residence is in Valparaiso, Indiana. He also owns a business and real estate in Illinois.

3 changes and that Sweeney should go ahead and make them, without asking for specifics on

the price increases.

Sweeney continued to work on Walsh’s home and billed him for labor. Walsh paid

Sweeney a total of $20,000, but when Sweeney sent Walsh another invoice in late November

2008, Walsh requested a meeting with Sweeney. At the meeting, Walsh told Sweeney that it

would be best if they cut ties, and Sweeney told Walsh that Walsh still owed him $9,500.

Sweeney offered to take $4,150 for his services and to walk away. Walsh never paid

Sweeney any money on the final invoice, and dismissed him from the jobsite.

Sweeney Construction stopped working on Walsh’s home on November 25, 2008, and

filed a “Notice of Intention to Hold Mechanics [sic] Lien” in the amount of $4,150 in the

Steuben County Recorder’s Office on January 21, 2009. On August 5, 2009, Sweeney

Construction filed a complaint in Steuben County Superior Court seeking foreclosure of the

mechanics lien, alleging breach of contract, and seeking damages for unjust enrichment.

Walsh answered the complaint and filed counterclaims on September 17, 2009. His specific

counterclaims were that Sweeney Construction’s complaint was frivolous thereby entitling

him to attorney’s fees, Sweeney Construction’s lien was improper and slandered Walsh’s title

to the property, Sweeney Construction’s decision to stop work resulted in a cost to Walsh of

$4,000 to comply with county codes, Sweeney Construction’s work was negligent, Sweeney

Construction committed fraud by deceiving Walsh as to its competency, Sweeney

Construction converted Walsh’s money, and Sweeney Construction violated the HICA and

therefore committed a deceptive act against Walsh.

4 On October 27, 2009, the case was transferred to DeKalb Superior Court. A bench

trial commenced on April 19, 2011, and at the beginning of the trial, Sweeney Construction

orally dismissed Count II of its complaint, the breach of contract claim. The parties

submitted written final arguments following the trial, and on June 24, 2011, the trial court

issued its final order. In that order, the trial court foreclosed on Sweeney Construction’s

mechanic’s lien, ordered that Walsh pay Sweeney Construction $4,150 “for services

rendered” and $10,585.09 for attorney’s fees, and denied Walsh’s counterclaims. App. 23.

Walsh now appeals.

Discussion and Decision

Standard of Review

When a trial court enters findings of fact and conclusions of law sua sponte, as it did

here, we employ a two-tiered standard of review. Cyr v. J. Yoder, Inc., 762 N.E.2d 148, 150

(Ind. Ct. App. 2002). We first determine whether the evidence supports the findings, and

then whether the findings support the judgment. Id. The specific findings control only the

issues they cover, while a general judgment standard applies to any issue upon which the trial

court has not entered findings. Id. A general judgment may be affirmed upon any legal

theory supported by the evidence. Humphries v. Ables, 789 N.E.2d 1025, 1030 (Ind. Ct.

App. 2003).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cavens v. Zaberdac
849 N.E.2d 526 (Indiana Supreme Court, 2006)
Troutwine Estates Development Co. v. ComSub Design & Engineering, Inc.
854 N.E.2d 890 (Indiana Court of Appeals, 2006)
Benge v. Miller
855 N.E.2d 716 (Indiana Court of Appeals, 2006)
King v. Terry
805 N.E.2d 397 (Indiana Court of Appeals, 2004)
Hayes v. Chapman
894 N.E.2d 1047 (Indiana Court of Appeals, 2008)
Homer v. Burman
743 N.E.2d 1144 (Indiana Court of Appeals, 2001)
Deutsche Bank National Trust Co v. Mark Dill Plumbing Co.
903 N.E.2d 166 (Indiana Court of Appeals, 2009)
R.T.B.H., Inc. v. Simon Property Group
849 N.E.2d 764 (Indiana Court of Appeals, 2006)
Romine v. Gagle
782 N.E.2d 369 (Indiana Court of Appeals, 2003)
Fairway Developers, Inc. v. Marcum
832 N.E.2d 581 (Indiana Court of Appeals, 2005)
Matter of Estate of Carroll
436 N.E.2d 864 (Indiana Court of Appeals, 1982)
Wiggin v. Gee Co.
386 N.E.2d 1218 (Indiana Court of Appeals, 1979)
Bayh v. Sonnenburg
573 N.E.2d 398 (Indiana Supreme Court, 1991)
Deutsche Bank National Trust Co. v. Mark Dill Plumbing Co.
908 N.E.2d 1273 (Indiana Court of Appeals, 2009)
Lee & Mayfield, Inc. v. Lykowski House Moving Engineers, Inc.
489 N.E.2d 603 (Indiana Court of Appeals, 1986)
Estate of Mueller v. Karns
873 N.E.2d 652 (Indiana Court of Appeals, 2007)
Crider & Crider, Inc. v. Downen
873 N.E.2d 1115 (Indiana Court of Appeals, 2007)
Barker v. Brownsburg Lumber Co., Inc.
399 N.E.2d 426 (Indiana Court of Appeals, 1980)
Cyr v. J. Yoder, Inc.
762 N.E.2d 148 (Indiana Court of Appeals, 2002)
Humphries v. Ables
789 N.E.2d 1025 (Indiana Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Kevin Walsh v. Chris Sweeney Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/kevin-walsh-v-chris-sweeney-construction-inc-indctapp-2012.