Great American Insurance Company v. Cline Precast, LLC

CourtIndiana Court of Appeals
DecidedMay 24, 2024
Docket23A-PL-02162
StatusPublished

This text of Great American Insurance Company v. Cline Precast, LLC (Great American Insurance Company v. Cline Precast, LLC) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Great American Insurance Company v. Cline Precast, LLC, (Ind. Ct. App. 2024).

Opinion

IN THE

Court of Appeals of Indiana FILED Great American Insurance Company, May 24 2024, 9:11 am

CLERK Appellant-Defendant/Counterclaim Plaintiff/Third-Party Plaintiff Indiana Supreme Court Court of Appeals and Tax Court

v.

Cline Avenue Bridge, LLC, and United Bridge Operating, LLC, Appellees-Plaintiffs/Counterclaim Defendants

Figg Group, Inc., et al., Appellees-Third-Party Defendants

May 24, 2024 Court of Appeals Case No. 23A-PL-2162 Appeal from the Lake Superior Court The Honorable John M. Sedia, Judge Trial Court Cause No. 45D01-2008-PL-517

Court of Appeals of Indiana | Opinion 23A-PL-2162 | May 24, 2024 Page 1 of 17 Opinion by Judge Mathias Judges Tavitas and Weissmann concur.

Mathias, Judge.

[1] Great American Insurance Company (“Great American”) appeals the trial

court’s entry of summary judgment in favor of Cline Avenue Bridge, LLC

(“CAB”) and United Bridge Operating, LLC (“UBO”) (we refer to CAB and

UBO collectively as the “Project Owners”). Great American had acted as a

surety for hire in a construction project by issuing payment and performance

bonds. CAB breached the underlying construction contract with the contractor,

and the Project Owners and Great American entered into litigation over

liability between them under the bonds. Eventually, Great American sought to

recover only its attorneys’ fees from the Project Owners, which request the trial

court denied on summary judgment.

[2] Great American raises a single issue for our review, which we restate as

whether the trial court erred when it concluded that Great American had no

contractual or equitable basis upon which Great American could seek to

recover attorneys’ fees from the Project Owners.

[3] We affirm.

Court of Appeals of Indiana | Opinion 23A-PL-2162 | May 24, 2024 Page 2 of 17 Facts and Procedural History [4] In June 2017, CAB entered into a $134-million construction contract with Figg

Bridge Builders, LLC (“Figg”) for Figg to design and construct the Cline

Avenue Bridge in East Chicago. The construction contract provided that, in the

event CAB were to breach the contract, the “Contractor[, i.e., Figg] shall be

entitled to . . . attorney’s fees and costs” from any ensuing dispute. Appellant’s

App. Vol. 3, p. 76. The construction contract further provided as follows with

respect to “Third Party Beneficiaries”:

Except with respect to the provisions of this Agreement pertaining to assignment, this Agreement is not intended to and shall not create rights of any character whatsoever in favor of any person other than the Parties to this Agreement, and the obligation[s] assumed herein are solely for the use and benefit of the Parties.

Id. at 88.

[5] The construction contract prohibited Figg from assigning its rights or

obligations under the contract without CAB’s prior written consent. However,

the contract made an exception for “any assignment to [Figg’s] surety required

in consideration for the Payment and Performance Bonds required under this

Agreement . . . .” Id. at 90. And, in 2010, Figg had executed an indemnity

agreement with Great American that assigned future construction contracts to

Great American “to secure the obligations” and “any other indebtedness and

liabilities” of Figg. Appellant’s App. Vol. 4, p. 58.

Court of Appeals of Indiana | Opinion 23A-PL-2162 | May 24, 2024 Page 3 of 17 [6] Following execution of the construction contract, Figg obtained the required

payment and performance bonds from Great American. 1 As relevant here, the

performance bond required Great American to pay its obligation under the

bond if CAB was not in default of the construction contract and after CAB had

provided notice to Great American that CAB was “considering declaring” Figg

to be in default. Appellant’s App. Vol. 3, p. 196. The performance bond also

reserved to Great American the right to hire a qualified and acceptable

contractor to replace Figg and complete the project if CAB were to consider

declaring Figg to be in default.

[7] The performance bond did not state any provision that entitled a party in a

dispute over payment under that bond to claim attorneys’ fees from another

party. See id. at 195-98, 203. Conversely, the payment bond stated that, if Great

American failed to discharge its obligations to a claimant under that bond,

Great American “shall indemnify the Claimant for the reasonable attorney’s

fees the Claimant incurs thereafter to recover any sums found to be due and

owing to the Claimant.” Id. at 200. The payment bond had no other provision

for the payment of attorneys’ fees. See id. at 199-203. Great American named

CAB and UBO, one of CAB’s members, as dual obligees to both bonds. 2

1 While the construction contract provided that Figg was to obtain the payment and performance bonds, the cost of those bonds was within the contract’s “Cost of the Work,” which was ultimately paid by CAB. Appellant’s App. Vol. 3, pp. 48, 51, 144. 2 Aside from the dual-obligee rider, the bonds issued by Great American were standard A312 documents issued by the American Institute of Architects. See id. at 183-91.

Court of Appeals of Indiana | Opinion 23A-PL-2162 | May 24, 2024 Page 4 of 17 [8] CAB issued a notice to proceed with construction to Figg on July 10, 2017,

which triggered a thirty-month schedule for substantial completion. Due to

numerous delays, Figg failed to meet that schedule. The construction contract

permitted CAB to assess liquidated damages against Figg for Figg’s failure to

meet the schedule, and the contract provided that such damages were CAB’s

“only remedy” against Figg for that noncompliance.3 Appellant’s App. Vol. 4,

p. 126. But CAB did not assess liquidated damages against Figg, and Figg

continued to perform under the construction contract.

[9] In April 2020, about three months after the expiration of the original thirty-

month schedule and a few months away from Figg’s anticipated completion of

the bridge, CAB terminated the construction contract and instructed Figg to

leave the project. CAB then hired a third party to complete the construction.

The Project Owners also sought payment from Great American under the

performance bond. However, as a result of CAB’s termination of Figg without

notice to Great American and CAB’s hiring of the third party, Great American

concluded that it had no liability to the Project Owners under that bond.

[10] CAB and Figg each alleged that the other had breached the construction

contract, and their dispute proceeded to arbitration before a panel of arbitrators.

Neither UBO nor Great American participated in the arbitration proceeding. In

3 The construction contract further provided that Figg would be in default if substantial completion had not been achieved “by the Delay Default Date,” which was six months after the target substantial-completion date. Appellant’s App. Vol. 4, p. 126.

Court of Appeals of Indiana | Opinion 23A-PL-2162 | May 24, 2024 Page 5 of 17 July 2022, the panel of arbitrators found that CAB had breached the

construction contract and that Figg was entitled to a net judgment of $4.4

million in damages, costs, and attorneys’ fees.

[11] Meanwhile, in August 2020 the Project Owners filed the instant lawsuit against

Great American. 4 The Project Owners alleged that, as Figg had purportedly

breached the construction contract, Great American was liable under the

performance bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loparex, LLC v. MPI Release Technologies, LLC
964 N.E.2d 806 (Indiana Supreme Court, 2012)
Bank of New York v. Nally
820 N.E.2d 644 (Indiana Supreme Court, 2005)
White v. Household Finance Corporation
302 N.E.2d 828 (Indiana Court of Appeals, 1973)
Garco Indus. Equipment Co., Inc. v. Mallory
485 N.E.2d 652 (Indiana Court of Appeals, 1985)
Indiana University v. Indiana Bonding & Surety Co.
416 N.E.2d 1275 (Indiana Court of Appeals, 1981)
City of Gary v. Allstate Insurance Co.
612 N.E.2d 115 (Indiana Supreme Court, 1993)
Town of Plainfield v. Paden Engineering Co.
943 N.E.2d 904 (Indiana Court of Appeals, 2011)
Meyer v. Building and Realty Service Co., Inc.
196 N.E. 250 (Indiana Supreme Court, 1935)
Damler v. Baine
51 N.E.2d 885 (Indiana Court of Appeals, 1943)
R. Kinsey Brooks, Susan K. Brooks v. Bank of Geneva
97 N.E.3d 647 (Indiana Court of Appeals, 2018)
R. Kinsey Brooks, Susan K. Brooks v. Bank of Geneva
105 N.E.3d 197 (Indiana Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Great American Insurance Company v. Cline Precast, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/great-american-insurance-company-v-cline-precast-llc-indctapp-2024.