Great American Insurance Company v. Cline Precast, LLC

Indiana Court of Appeals·Decided May 24, 2024·No. 23A-PL-02162·Published

Opinion

IN THE

Court of Appeals of Indiana FILED

Great American Insurance Company, May 24 2024, 9:11 am

CLERK

Appellant-Defendant/Counterclaim Plaintiff/Third-Party Plaintiff Indiana Supreme Court Court of Appeals

and Tax Court

v.

Cline Avenue Bridge, LLC, and United Bridge Operating, LLC, Appellees-Plaintiffs/Counterclaim Defendants

v.

Figg Group, Inc., et al., Appellees-Third-Party Defendants

May 24, 2024

Court of Appeals Case No.

23A-PL-2162

Appeal from the Lake Superior Court The Honorable John M. Sedia, Judge Trial Court Cause No.

45D01-2008-PL-517

Court of Appeals of Indiana | Opinion 23A-PL-2162 | May 24, 2024 Page 1 of 17

Opinion by Judge Mathias

Judges Tavitas and Weissmann concur.

Mathias, Judge.

[1] Great American Insurance Company (“Great American”) appeals the trial court’s entry of summary judgment in favor of Cline Avenue Bridge, LLC (“CAB”) and United Bridge Operating, LLC (“UBO”) (we refer to CAB and UBO collectively as the “Project Owners”). Great American had acted as a surety for hire in a construction project by issuing payment and performance bonds. CAB breached the underlying construction contract with the contractor, and the Project Owners and Great American entered into litigation over liability between them under the bonds. Eventually, Great American sought to recover only its attorneys’ fees from the Project Owners, which request the trial court denied on summary judgment.

[2] Great American raises a single issue for our review, which we restate as whether the trial court erred when it concluded that Great American had no contractual or equitable basis upon which Great American could seek to recover attorneys’ fees from the Project Owners.

[3] We affirm.

Facts and Procedural History [4] In June 2017, CAB entered into a $134-million construction contract with Figg

Bridge Builders, LLC (“Figg”) for Figg to design and construct the Cline Avenue Bridge in East Chicago. The construction contract provided that, in the event CAB were to breach the contract, the “Contractor[, i.e., Figg] shall be entitled to . . . attorney’s fees and costs” from any ensuing dispute. Appellant’s App. Vol. 3, p. 76. The construction contract further provided as follows with respect to “Third Party Beneficiaries”:

Except with respect to the provisions of this Agreement pertaining to assignment, this Agreement is not intended to and shall not create rights of any character whatsoever in favor of any person other than the Parties to this Agreement, and the obligation[s] assumed herein are solely for the use and benefit of the Parties.

Id. at 88.

[5] The construction contract prohibited Figg from assigning its rights or obligations under the contract without CAB’s prior written consent. However, the contract made an exception for “any assignment to [Figg’s] surety required in consideration for the Payment and Performance Bonds required under this Agreement . . . .” Id. at 90. And, in 2010, Figg had executed an indemnity agreement with Great American that assigned future construction contracts to Great American “to secure the obligations” and “any other indebtedness and liabilities” of Figg. Appellant’s App. Vol. 4, p. 58.

[6] Following execution of the construction contract, Figg obtained the required payment and performance bonds from Great American. 1 As relevant here, the performance bond required Great American to pay its obligation under the bond if CAB was not in default of the construction contract and after CAB had provided notice to Great American that CAB was “considering declaring” Figg to be in default. Appellant’s App. Vol. 3, p. 196. The performance bond also reserved to Great American the right to hire a qualified and acceptable contractor to replace Figg and complete the project if CAB were to consider declaring Figg to be in default.

[7] The performance bond did not state any provision that entitled a party in a dispute over payment under that bond to claim attorneys’ fees from another party. See id. at 195-98, 203. Conversely, the payment bond stated that, if Great American failed to discharge its obligations to a claimant under that bond, Great American “shall indemnify the Claimant for the reasonable attorney’s fees the Claimant incurs thereafter to recover any sums found to be due and owing to the Claimant.” Id. at 200. The payment bond had no other provision for the payment of attorneys’ fees. See id. at 199-203. Great American named CAB and UBO, one of CAB’s members, as dual obligees to both bonds. 2

1 While the construction contract provided that Figg was to obtain the payment and performance bonds, the cost of those bonds was within the contract’s “Cost of the Work,” which was ultimately paid by CAB. Appellant’s App. Vol. 3, pp. 48, 51, 144. 2 Aside from the dual-obligee rider, the bonds issued by Great American were standard A312 documents issued by the American Institute of Architects. See id. at 183-91.

Court of Appeals of Indiana | Opinion 23A-PL-2162 | May 24, 2024 Page 4 of 17

[8] CAB issued a notice to proceed with construction to Figg on July 10, 2017, which triggered a thirty-month schedule for substantial completion. Due to numerous delays, Figg failed to meet that schedule. The construction contract permitted CAB to assess liquidated damages against Figg for Figg’s failure to meet the schedule, and the contract provided that such damages were CAB’s “only remedy” against Figg for that noncompliance.3 Appellant’s App. Vol. 4, p. 126. But CAB did not assess liquidated damages against Figg, and Figg continued to perform under the construction contract.

[9] In April 2020, about three months after the expiration of the original thirty- month schedule and a few months away from Figg’s anticipated completion of the bridge, CAB terminated the construction contract and instructed Figg to leave the project. CAB then hired a third party to complete the construction. The Project Owners also sought payment from Great American under the performance bond. However, as a result of CAB’s termination of Figg without notice to Great American and CAB’s hiring of the third party, Great American concluded that it had no liability to the Project Owners under that bond.

[10] CAB and Figg each alleged that the other had breached the construction contract, and their dispute proceeded to arbitration before a panel of arbitrators. Neither UBO nor Great American participated in the arbitration proceeding. In

3 The construction contract further provided that Figg would be in default if substantial completion had not been achieved “by the Delay Default Date,” which was six months after the target substantial-completion date. Appellant’s App. Vol. 4, p. 126.

Court of Appeals of Indiana | Opinion 23A-PL-2162 | May 24, 2024 Page 5 of 17

July 2022, the panel of arbitrators found that CAB had breached the construction contract and that Figg was entitled to a net judgment of $4.4 million in damages, costs, and attorneys’ fees.

[11] Meanwhile, in August 2020 the Project Owners filed the instant lawsuit against Great American. 4 The Project Owners alleged that, as Figg had purportedly breached the construction contract, Great American was liable under the performance bond. Great American denied liability and filed counterclaims against the Project Owners. In relevant part, in its counterclaim Count 4, Great American alleged that CAB’s wrongful termination of Figg and lack of notice to Great American of that termination had caused Great American to make payments to Figg and subcontractors in reliance on CAB’s contractual obligations. In particular, Great American alleged it had advanced to Figg more than $14 million to fund completion costs and that it had paid more than $4 million in post-termination claims under the payment bond due to CAB’s failure to disperse construction funds.

Free access — add to your briefcase to read the full text and ask questions with AI

Great American Insurance Company v. Cline Precast, LLC, (Ind. Ct. App. 2024).

Great American Insurance Company v. Cline Precast, LLC (Great American Insurance Company v. Cline Precast, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Loparex, LLC v. MPI Release Technologies, LLC
964 N.E.2d 806 (Indiana Supreme Court, 2012)
Bank of New York v. Nally
820 N.E.2d 644 (Indiana Supreme Court, 2005)
White v. Household Finance Corporation
302 N.E.2d 828 (Indiana Court of Appeals, 1973)
Garco Indus. Equipment Co., Inc. v. Mallory
485 N.E.2d 652 (Indiana Court of Appeals, 1985)
Indiana University v. Indiana Bonding & Surety Co.
416 N.E.2d 1275 (Indiana Court of Appeals, 1981)
City of Gary v. Allstate Insurance Co.
612 N.E.2d 115 (Indiana Supreme Court, 1993)
Town of Plainfield v. Paden Engineering Co.
943 N.E.2d 904 (Indiana Court of Appeals, 2011)
Meyer v. Building and Realty Service Co., Inc.
196 N.E. 250 (Indiana Supreme Court, 1935)
Damler v. Baine
51 N.E.2d 885 (Indiana Court of Appeals, 1943)
R. Kinsey Brooks, Susan K. Brooks v. Bank of Geneva
97 N.E.3d 647 (Indiana Court of Appeals, 2018)
R. Kinsey Brooks, Susan K. Brooks v. Bank of Geneva
105 N.E.3d 197 (Indiana Court of Appeals, 2018)