Diamond Services v. RLB Contracting

113 F.4th 430
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 16, 2024
Docket23-40137
StatusPublished
Cited by7 cases

This text of 113 F.4th 430 (Diamond Services v. RLB Contracting) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diamond Services v. RLB Contracting, 113 F.4th 430 (5th Cir. 2024).

Opinion

Case: 23-40137 Document: 81-1 Page: 1 Date Filed: 08/16/2024

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit ____________ FILED August 16, 2024 No. 23-40137 Lyle W. Cayce ____________ Clerk

Diamond Services Corporation,

Plaintiff—Appellant,

versus

RLB Contracting, Incorporated; Harbor Dredging, Incorporated; Travelers Casualty and Surety Company of America,

Defendants—Appellees. ______________________________

Appeal from the United States District Court for the Southern District of Texas USDC No. 3:21-CV-253 ______________________________

Before Graves, Higginson, and Ho, Circuit Judges. Stephen A. Higginson, Circuit Judge: This interlocutory appeal concerns a dispute between, on one side, a sub-subcontractor, and on the other, a contractor, subcontractor, and insurance company, over a contract for pipeline dredging in the Houston Ship Channel. We AFFIRM in part and DISMISS in part. I. We set forth below the factual and procedural background of this appeal. Case: 23-40137 Document: 81-1 Page: 2 Date Filed: 08/16/2024

No. 23-40137

A. On September 4, 2019, the U.S. Army Corps of Engineers, Galveston Division (“the Corps”) awarded RLB Contracting (“RLB”) a contract (“prime contract”) for pipeline dredging in the Houston Ship Channel. As required by the contract and the Miller Act, 40 U.S.C. §§ 3131 et seq., RLB furnished a surety bond which it obtained from Travelers Casualty and Surety Company of America (“Travelers”). To assist it in dredging the volume called for by the Corps, RLB entered into a subcontract with Harbor Dredging (“Harbor”). Harbor, in turn, entered into a sub-subcontract with Diamond Services Corporation (“Diamond”) for the dredge work. As part of its obligations under the sub-subcontract, Diamond was “responsible for traversing the hopper barges from excavation site to the unloading site” and Diamond was required to perform, among other things, “all work necessary or incidental to complete” its work on the project. During the performance of the project, the parties encountered “differing site conditions” in the area where Diamond’s dredge was excavating material. The unanticipated presence of tires in the channel, as well as other issues, slowed down the job considerably. Diamond determined that it would not be able to continue the project profitably. Agents of RLB, Harbor, and Diamond met to discuss the situation, and Diamond threatened to leave the project absent changes. In October 2020, RLB submitted a request for equitable adjustment (“REA”) of the prime contract to the Corps. In Diamond’s view, RLB and Harbor had agreed to compensate Diamond out of the REA using a measured-mile calculation, though in what proportion or for how much was left unsaid because it was, at the time, “unknowable.” As explained by the parties, a measured-mile calculation in this context involves comparing dredging costs incurred during a set period where differing site conditions

2 Case: 23-40137 Document: 81-1 Page: 3 Date Filed: 08/16/2024

interrupted operations to dredging costs completed during the same period where differing site conditions did not interrupt operations. Diamond, allegedly relying on these representations, continued working and increased operations, dredging twenty-four hours a day to build a favorable benchmark for its anticipated measured-mile calculations. RLB later withdrew its October 2020 REA because the Corps instructed RLB that the Corps would not entertain any future REAs for unanticipated costs not included in the initial REA, and it would require RLB to release its claims for all differing site conditions at the project. After project completion, RLB prepared to submit a second amended REA and asked Harbor to certify and submit its total project costs, including direct costs, overhead, and profit, as well as corresponding numbers from Diamond. On March 5, 2021, Diamond executive James Furlette sent Harbor executive Roland Maturin an email stating “[t]his is where we are at.” Attached to the email was a chart, with the sums “$1,530,323.09 Outstanding + 500,000.00 Extra work” scribbled by hand at the bottom. The sums totaled $2,030,323.09. On March 30, 2021, Harbor submitted to RLB its certified total costs in the amount of $3,179,169, which included Diamond’s certified total costs of $2,362,344. Using Harbor and Diamond’s total certified costs submissions as subcontractor and sub-subcontractor and RLB’s total certified costs, including RLB’s direct costs, overhead, and profit, RLB amended and resubmitted its REA on April 6, 2021, seeking $8,867,212 for the excess costs associated with the differing site conditions. The Corps offered to negotiate a settlement. RLB asked Harbor to determine the amounts that Harbor and Diamond “would accept in satisfaction of their claims for a share of the excess costs recovered by RLB from the [Corps] in a settlement of the amended REA.”

3 Case: 23-40137 Document: 81-1 Page: 4 Date Filed: 08/16/2024

Here, the parties’ accounts diverge. Harbor maintains that Diamond agreed, in subsequent conversations between Furlette and Maturin, to accept $950,000 “to resolve its claim for a share of excess costs recovered by RLB in an REA associated with the differing site condition[s].” Diamond insists that “when Harbor asked Diamond if Diamond would accept $950,000[,] Diamond responded not with ‘yes’ but with ‘maybe’: Diamond said that it could, but only if that’s what the [Corps] was willing to pay. . . . Diamond was clear that its accession to this request by Harbor was conditional,” and depended on how the REA was derived and what it included. For its part, Harbor determined that it would accept $500,000 in resolution of its claims and communicated a total settlement sum of $1,450,000—including the $950,000 allegedly agreed to by Diamond—to RLB. RLB did not communicate with Diamond during the REA negotiation process. After negotiations, the Corps and RLB reached a settlement of the amended REA in the amount of $6,000,000. RLB issued a joint check to Harbor and Diamond in the amount of $950,000, dated September 9, 2021. One week later, Diamond filed suit against RLB, Harbor, and Travelers. Diamond invoked the district court’s exclusive jurisdiction over Miller Act claims under 40 U.S.C. § 3133(b)(3) and supplemental jurisdiction under 28 U.S.C. § 1367 over the rest of its claims. In the alternative, Diamond asserted that the court had admiralty jurisdiction under 28 U.S.C. § 1333(1). Against Harbor and RLB, Diamond brought claims for breach of contract, implied contract, and quasi-contract; against RLB and Travelers, Diamond also brought Miller Act claims. Harbor endorsed and tendered RLB’s check for the full amount of $950,000 to Diamond on October 29, 2021. Diamond initially refused to

4 Case: 23-40137 Document: 81-1 Page: 5 Date Filed: 08/16/2024

accept the check marked “FULL AND FINAL PAYMENT,” but did so after RLB agreed to permit Diamond to disregard that notation. At some point after RLB and the Corps reached a settlement, Maturin, the Harbor executive, placed a recorded phone call to Furlette, the Diamond executive, and remarked that he “got a call from [RLB executive] Randy [Boyd] saying that you’re not going to sign the agreement that we had for the $950,000.” Furlette replied that he would ask Diamond executive Stephen Swiber about it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
113 F.4th 430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diamond-services-v-rlb-contracting-ca5-2024.