M.J. Sheridan & Son Co. v. Seminole Pipeline Co.

731 S.W.2d 620, 1987 Tex. App. LEXIS 7078
CourtCourt of Appeals of Texas
DecidedApril 23, 1987
Docket01-86-0429-CV
StatusPublished
Cited by88 cases

This text of 731 S.W.2d 620 (M.J. Sheridan & Son Co. v. Seminole Pipeline Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.J. Sheridan & Son Co. v. Seminole Pipeline Co., 731 S.W.2d 620, 1987 Tex. App. LEXIS 7078 (Tex. Ct. App. 1987).

Opinion

OPINION

SAM BASS, Justice.

M.J. Sheridan and Son, Co., Inc., sued Seminole Pipeline Company alleging that Seminole had breached its contract with Sheridan by failing to provide Sheridan with a pipeline easement and that this damaged Sheridan because it was unable to proceed with its contract. Sheridan also sought recovery on theories of fraud and quantum meruit. After a jury trial, the court entered a directed verdict as to the fraud and quantum meruit causes of ac *622 tions, and the jury found that Seminole had provided Sheridan with a right-of-way within a reasonable time. Therefore, the court concluded that Seminole had not breached the contract, and entered a take-nothing judgment in its favor.

We affirm.

Sheridan agreed to construct a pipeline for Seminole on a right-of-way to be provided by Seminole. The contract consisted of general requirements, specifications sheet, equipment rate schedule, labor rates, and a job description. The job description provided for commencement on September 15, 1981, and completion by November 2, 1981. The contract was signed on November 3rd, and construction of the pipeline began November 9th and was completed on February 27, 1982.

The agreement contained specific provisions to record any extra work on a “memorandum of work” performed to be signed by representatives of both Sheridan and Seminole. The extra, work compensation was based on the actual cost of materials, the labor, and equipment rates contained in the bid.

A provision was provided for payment of shutdown rates on days when pipe could not be laid because of Seminole’s failure to provide the right-of-way. The first right-of-way problems began shortly after the start of construction, when Sheridan’s crews worked up to a property in which the easement had not been obtained. Sheridan recorded the shutdown days, submitted the charges, and was paid.

Other situations occurred where there was no right-of-way and the crews moved around the tract and worked on other tracts. When these “move arounds” occurred, the parties prepared a memorandum containing; (1) the location moved from; (2) the location moved to; (3) the men and equipment involved; and (4) the time consumed, and both parties signed the document. Also, the chief inspector for Seminole made a detailed explanation of the “move around” and approved a memorandum of work performed, which was signed and accepted by Sheridan’s superintendent. Sheridan would then include those charges, and Seminole paid such charges.

In point of error one, Sheridan contends that the trial court erred in denying it’s motion for new trial, arguing that the jury’s negative answer to special issue 1, which asked: “Do you find [from] a preponderance of the evidence that Seminole failed to provide Sheridan with right-of-way in a reasonable time?”, was against the great weight and preponderance of the evidence.

Where a contract does not fix a time for performance, a reasonable time is allowed. See Heritage Resources, Inc. v. Anschutz Corp., 689 S.W.2d 952, 955 (Tex.App.—El Paso 1985, no writ). What is a reasonable time depends on the circumstances in each case and requires a fact finding by the jury. Id. at 955. In this case it was Sheridan’s burden to obtain a favorable finding that the right-of-way was not acquired within a reasonable time.

Some courts have held that where a jury fails to find a vital issue in favor of a party having the burden of proof on the issue, that party, to complain on appeal, must show that the evidence “conclusively” established the issue “as a matter of law.” See Pouncy v. Garner, 626 S.W.2d 337, 342-43 (Tex.Civ.App.—Tyler 1981, writ ref'd n.r.e.); Jordon v. Ortho Pharmaceuticals Inc., 696 S.W.2d 228, 237 (Tex.App.—San Antonio 1985, no writ); Bell v. Buddies Supermarket, 516 S.W.2d 447, 451 (Tex.Civ.App.—Tyler 1974, writ ref’d n.r. e.); Ross v. Sher, 483 S.W.2d 297 (Tex.Civ.App.—Houston 1972, writ ref’d n.r.e.); Smith v. Safeway Stores, Inc., 433 S.W.2d 217 (Tex.Civ.App.—Tyler 1968, writ ref’d n.r.e.). As support for this test, those decisions indicate reliance on statements in Judge Calvert’s article, “No Evidence” and “Insufficient Evidence” Points of Error, 38 Tex.L.Rev. 361, 363 (1960), that we conclude relate only to “no evidence” situations. Judge Calvert wrote that before a party is entitled to have a judgment based on [a jury’s failure to find a vital fact] reversed and judgment rendered in his favor, it must appear that the evidence estab *623 lishes conclusively that the act was committed. However, the cases cited above have erroneously adopted this standard for reversal of factual sufficiency challenges as well. Id. at 364 (emphasis added).

Thus, we do not follow the rationale of those decisions in this case, which involves a “factual sufficiency” complaint that the jury’s negative finding is against the great weight and preponderance of the evidence. We believe the proper standard of review in such a case is that enunciated in In re King’s Estate, 150 Tex. 662, 244 S.W.2d 660 (1951), and reaffirmed in Pool v. Ford Motor Co., 715 S.W.2d 629, 633-34 (Tex.1986). There the Texas Supreme Court applied the “great weight” standard, as established in In re King’s Estate, to a defendant’s complaint about the jury’s failure to find an affirmative defensive issue in its favor.

Under the Supreme Court’s decision in Pool, and in view of the interpretation generally accorded to Judge Calvert’s article over the years, we conclude that we are required to follow the In re King’s Estate standard of review in all “factual sufficiency” cases, whether we review a negative or affirmative jury finding and regardless of whether the complaining party had the burden of proof on the issue. That is, where the complaining party asserts that either an affirmative or a negative finding is against the great weight and preponderance of the evidence, we must review all the evidence, both for and against the issue, and determine whether the finding is so against the great weight and preponderance of the evidence as to be manifestly unjust. Pool, 715 S.W.2d at 625; In re King’s Estate, 224 S.W.2d at 662, 244 S.W.2d 660. We also conclude that this standard of review requires no greater showing on appeal by the party who had the burden of proof on the issue at trial than in an appeal by the party who did not have the burden of proof at trial. But see U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diamond Services v. RLB Contracting
113 F.4th 430 (Fifth Circuit, 2024)
Stan Martin and Roma Martin v. Cottonwood Creek Construction, LLC
560 S.W.3d 759 (Court of Appeals of Texas, 2018)
in the Interest of B.F. and P.F., Children
Court of Appeals of Texas, 2017
Horseshoe Bay Resort, Ltd. v. CRVI CDP Portfolio, LLC
415 S.W.3d 370 (Court of Appeals of Texas, 2013)
Chambers v. Hunt Petroleum Corp.
320 S.W.3d 578 (Court of Appeals of Texas, 2010)
Kroger Co. v. Persley
261 S.W.3d 316 (Court of Appeals of Texas, 2008)
City of Houston v. Swinerton Builders, Inc.
233 S.W.3d 4 (Court of Appeals of Texas, 2007)
LTS Group, Inc. v. Woodcrest Capital, L.L.C.
222 S.W.3d 918 (Court of Appeals of Texas, 2007)
Gonzalez v. Denning
394 F.3d 388 (Fifth Circuit, 2004)
Continental Casing Corp. v. Siderca Corp.
38 S.W.3d 782 (Court of Appeals of Texas, 2001)
Lesikar v. Rappeport
33 S.W.3d 282 (Court of Appeals of Texas, 2000)
Smith v. Aqua-Flo, Inc.
23 S.W.3d 473 (Court of Appeals of Texas, 2000)
Oyster Creek Financial Corp. v. Richwood Investments II, Inc.
957 S.W.2d 640 (Court of Appeals of Texas, 1998)
Shannon v. Law-Yone
950 S.W.2d 429 (Court of Appeals of Texas, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
731 S.W.2d 620, 1987 Tex. App. LEXIS 7078, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mj-sheridan-son-co-v-seminole-pipeline-co-texapp-1987.