Stan Martin and Roma Martin v. Cottonwood Creek Construction, LLC

560 S.W.3d 759
Court of Appeals of Texas·Decided October 3, 2018·No. 10-17-00005-CV·Published·Cited by 11 cases

Opinion

IN THE

TENTH COURT OF APPEALS

No. 10-17-00005-CV

STAN MARTIN AND ROMA MARTIN, Appellants

v.

COTTONWOOD CREEK CONSTRUCTION, LLC, Appellee

From the 249th District Court Johnson County, Texas

Trial Court No. C201300177

OPINION

Stan and Roma Martin contracted with Cottonwood Creek Construction, LLC to build the Martins a house. The estimated cost was over $880,000, and Cottonwood’s estimated fees were over $120,000. When the Martins failed to pay two draws, Cottonwood suspended further work on the project. The Martins then retained another contractor to finish the house.

Cottonwood sued the Martins for breach of contract. The Martins filed a counterclaim against Cottonwood and a claim against a third party.1 After a jury trial, the trial court rendered judgment against the Martins on all the claims alleged by the parties.

On appeal, the Martins raise five issues. Because we overrule each issue, the trial court’s judgment is affirmed. ANTICIPATORY REPUDIATION/LOST PROFITS In their first issue, the Martins assert the trial court erred in submitting Question 3 and in refusing to submit their Requested Question 4 on what they believed to be Cottonwood’s claim of anticipatory repudiation. Specifically, the Martins assert that the inclusion of the ability to recover damages for lost profits in Question 3 without another question submitted about repudiation, was error. Alternatively, the Martins argue in their second issue that if there was no error in the wording of Question 3, nevertheless there was error in submitting it because there was no evidence to support the value damages found by the jury.

Initially, we note that a request for submission is the method of preserving the right to complain of the omission of, or failure to submit, an issue or question which is relied on by the complaining party. Lyles v. Tex. Employers' Ins. Asso., 405 S.W.2d 725, 727 (Tex. Civ. App.—Waco 1966, writ ref’d n.r.e.). An objection, on the other hand, is the proper method to preserve a complaint as to (1) an issue or question actually submitted, but claimed to be defective; or (2) the failure to submit, where the ground of recovery or

1 The Martins have no issue on appeal regarding the third-party claim.

Martin v. Cottonwood Creek Construction, LLC Page 2 defense is relied on by the opposing party. Id. See Religious of Sacred Heart v. Houston, 836 S.W.2d 606, 614 (Tex. 1992).

At the charge conference, the Martins made the following objection to Question 3:

Objection is made to Pattern Jury Charge Question No. 3 for the reason that it says, Cottonwood Creek may not recover – may recover not only for the value of the work actually done. There's been no evidence of the value of the work performed before this jury, and that assumes there was a value for work performed. Objection is further made that … for any profit Cottonwood Creek would have made had it been permitted to complete the contract. That assumes that the Martins repudiated the contract and stopped Cottonwood Creek from completing the contract. And that assumes a fact that has not been established, although pled by the Plaintiff.

The Plaintiff has not submitted an issue for that. Therefore, I submit Issue No. 4, Question No. 4 for the jury on anticipatory repudiation.

***

Objection is made to the lost profits, 12 percent fee for remaining contract balance. It assumes as an anticipatory repudiation by the Martins which requires an unconditional repudiation of which there's no evidence of and nevertheless assumes that before asking the jury to receive a lost profit.

The Martins objected to the submission of Question 3 because, according to the Martins, the question was defective in that it included the ability to recover damages for lost profits which assumed repudiation by the Martins.

The Martins’ request for submission of Requested Question 4 regarding anticipatory repudiation, however, did not preserve their complaint for appellate review because anticipatory repudiation was not an issue relied upon by the Martins, i.e. the complaining party. The Martins were required to object to the trial court’s failure to submit a question on anticipatory repudiation because it was, arguably, a ground of recovery relied on by Cottonwood. The Martins did not object. Thus, any complaint about the trial court’s failure to submit the Martins’ Requested Question 4 on anticipatory Martin v. Cottonwood Creek Construction, LLC Page 3 repudiation is not preserved; and we need not decide that part of the Martin’s first issue.2 As to the lost profits portion of the Martins’ first issue, they complain that the trial court improperly included lost profits in Question 3. In substance, the Martins argue on appeal that the damages question improperly mixed breach of contract damages with damages only recoverable under quantum meruit. Question 3 provided, in relevant part:

What amount of money, if paid in cash today, would fairly and reasonably compensate Cottonwood Creek for the Martins’ failure to comply with the Agreement?

You are instructed that Cottonwood Creek may recover not only for the value of the work actually done, but also for any profit Cottonwood Creek would have made had it been permitted to complete the contract.

Therefore, in answering Question No. 3, consider the following elements of damages, if any, and none other.

***

Lost Profit (12% Fee) for Remaining Contract Balance: $65,514.35

The Martins argue that an attempt to recover lost profits is an attempt to recover on the contract; but because the trial court instructed the jury that Cottonwood could recover for the “value” of the work done, this was a recovery in quantum meruit for which Cottonwood could not recover in addition to lost profits. The Martins contend the Court should have used the phrase “work done” rather than the phrase “value of the work done.”

2 Additionally, we note that the jury was asked whether the Martins failed to comply with the Agreement, which was Question 1, and answered, “Yes.” In Question 2, the jury was asked whether the failure to comply with the Agreement was excused by a prior material breach by Cottonwood, which the jury answered, “No.” Under the conditional submission of Question 3, the jury was then asked about damages. Thus, while the Martins complain about the failure to submit a question on anticipatory repudiation of a contract, which is one method of establishing a breach of contract, it is not the only type of breach. The Martins fail to address why Question 1 and Question 2 do not properly set up Question 3 for damages for their breach of contract as found by the jury.

Martin v. Cottonwood Creek Construction, LLC Page 4

But that was not the objection the Martins made to the trial court. There, the Martins only objected that there was “no evidence of the value of the work performed before this jury, and that assumes there was a value for work performed.” The Martins did not object that “value” corresponded to a recovery in quantum meruit which is inconsistent with a recovery for breach of contract. In order to preserve error for appellate review, a party's argument on appeal must comport with its argument in the trial court. See In re D.E.H., 301 S.W.3d 825, 829 (Tex. App.—Fort Worth 2009, pet. denied); Kershner v. State Bar of Tex., 879 S.W.2d 343, 347 (Tex. App.—Houston [14th Dist.] 1994, writ denied). Because the objection asserted at trial does not comport with the complaint argued on appeal, the second portion of the Martins’ first issue that an improper measure of damages was submitted is not preserved. See TEX. R. APP. P. 33.1(a).

Accordingly, the Martins’ first issue is overruled.

VALUE Next, the Martins assert there is no evidence in the record to support the amounts awarded by the jury of the “value of the work actually done” in response to the first eight elements of damages in Question 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Stan Martin and Roma Martin v. Cottonwood Creek Construction, LLC, 560 S.W.3d 759 (Tex. Ct. App. 2018).

560 S.W.3d 759 (Stan Martin and Roma Martin v. Cottonwood Creek Construction, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related