Greenup Industries, LLC v. Five S Group, LLC

CourtDistrict Court, E.D. Louisiana
DecidedMarch 16, 2023
Docket2:22-cv-02203
StatusUnknown

This text of Greenup Industries, LLC v. Five S Group, LLC (Greenup Industries, LLC v. Five S Group, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenup Industries, LLC v. Five S Group, LLC, (E.D. La. 2023).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA GREENUP * CIVIL ACTION INDUSTRIES LLC * * NO. 22-2203 VERSUS * * SECTION: “L” (4) FIVE S GROUP, LLC ET AL * * ORDER AND REASONS Before the Court are Motions to Dismiss Defendants’ First Amended and Restated Counterclaim by Plaintiff Greenup Industries, at R. Doc. 24, and Markel Insurance Company, at R. Doc. 25. Defendants have filed memoranda in opposition, at R. Doc. 29 and R. Doc. 28. I. BACKGROUND This case arises from a contract between Greenup Industries, LLC (“Greenup”) the Contractor, and Five S Group, LLC (“Five S”), the Subcontractor, to excavate fill from the Bonnet Carre Spillway and transport it to another site, in fulfillment of a contract Greenup was awarded by the United States Army Corps of Engineers’ (“USACE”) to complete work related to its Hurricane Storm Damage Risk Reduction Project. Greenup alleges that it entered into a subcontract (“Subcontract”) with Five S on October 26, 2020, in which Five S agreed to provide labor and equipment to excavate 1,000,000 cubic yards (“CY”) of fill from the Bonnet Carre Spillway, and that Hartford then issued a performance bond on behalf of Five S in the amount of $9,472,000.00. Id. at 2. Both parties note that the Subcontract schedule called for the fill to be excavated over 15 months, requiring that Five S excavate and transport an average of 66,667 CY of fill each month. Id. at 3; R. Doc. 29 at 2.The Subcontract provided that the fill was to be excavated from a “borrow pit,” and moved to a stockpile. R. Doc. 18-1 at 19. Greenup alleges that USACE began raising issues about Five S’s lack of performance in “late 2021.” R. Doc. 1-1 at 3. Among the concerns, Greenup alleges, were broken equipment left onsite, excessive employee turnover, and a lack of processing equipment that resulted in failed

quality tests regarding the moisture content of the fill. Id. at 4. Five S, by contrast, alleges that, while it “mobilized sufficient equipment and labor” to finish the project on schedule, Greenup’s breach of performance caused its inability to meet the Project timeline. R. Doc. 18 at 4. On November 21, 2021, Five S’s area manager, Justin Mibbs, sent Greenup a letter alleging that, despite an initial agreement that Greenup would provide Five S 40-50 trucks a day to transport the fill from the borrow site to the stockpile, “Greenup so far has been providing only about 8 or 9 trucks a day.” R. Doc. 18-3 at 1. In the letter, Mibbs alleged that the small number of trucks provided would delay the project’s completion by four years, and informed Greenup that it was “submitting an application for payment of 85% of our daily cost of keeping equipment and labor at the borrow pit” until “Greenup increases its number of trucks at the site.” Id. at 2. Greenup’s

counsel, Etienne Balart, replied to the letter on November 15, 2021, stating that Greenup viewed the request for daily costs as “outside of the terms of the Subcontract” because “5S agreed to be paid pursuant to the line items set forth in Exhibit B” and that these line items “must be based upon USACE approved calculations of in-place quantities.” R. Doc. 18-4 at 1. Over the next five months, the problems regarding the pace of the work did not abate. Monthly schedule updates issued by Greenup from December 2021 to April 2022 all note delays due to inadequate number of trucks and difficulties “keeping trucks onsite and available.” R. Doc. 29-1 at 2-5. Greenup alleges that, on April 12, 2022, Five S sent a demand letter re- emphasizing its November 1, 2021 request and notifying Greenup that it had de-mobilized from the site and would not resume until Greenup agreed to pay for past and future standby time. R. Doc. 1-1 at 4. Greenup further alleges that Five S demobilized from the site “well before March 15, 2022” and that Five S “made clear its intent to abandon the job well before any ‘declaration’ of alleged default.” Id. at 5. Five S alleges that it was “excused from further performance under

the Subcontract” when Greenup breached its obligations to supply sufficient trucks and to pay Five S for the services it provided under contract. R. Doc. 29 at 5. On May 27, 2022, Greenup sued Five S and its insurer, Hartford Fire Insurance Company (“Hartford”), in Orleans Parish civil court, seeking a declaratory judgment that Five S “does not have a legal or contractual basis to put Greenup in default and to discontinue its obligations under the Subcontract” and that any payment to Five S was conditioned upon Greenup’s receipt of USACE funds. R. Doc. 1-1 at 7. Greenup also made claims for breach of contract and indemnity against Five S and repeated its claims for declaratory judgment against Hartford, id. at 7-8, and sought attorney’s fees from Hartford, id. at 9. On July 15, 2022, Five S and Hartford removed the case to federal court, R. Doc. 1 at 6, under 28 U.S.C. § 1442(a)(1), asserting that

removal was proper because Five S acted at the direction of the USACE, and because Greenup’s claims rested on the Miller Act, at 40 U.S.C. § 3133(b)(3), which is under exclusive federal jurisdiction. Id. On July 22, 2022, Five S and Hartford filed a counterclaim against Greenup and its insurer, which Defendants named as “ABC Insurance Company.” R. Doc. 18 at 9. On September 20, 2022, Five S and Hartford filed an amended counterclaim against Greenup and its actual insurer, Markel Insurance Company. R. Doc. 18. Against Greenup, Five S and Hartford allege breach of contract. Against both Greenup and Markel, Five S and Hartford allege claims under the Miller Act for Greenup’s failure to pay Five S out of the Payment Bond that Markel issued for the work. Five S and Hartford also bring claims against Greenup and Markel under the Louisiana Prompt Payment Act, alleging that Greenup failed to remit payment within 14 days of receiving those funds from the USACE. R. Doc. 18 at 11-12.

II. PRESENT MOTIONS Movants seek to dismiss the counterclaims that Five S and Hartford allege against Greenup and Markel in Defendants’ First Amended Counterclaim, at R. Doc. 18, for failure to state a claim upon which relief can be granted. R. Doc. 24; R. Doc. 25. Greenup and Markel argue that Five S and Hartford’s counterclaims should be dismissed because they have failed to state a claim under state contract law, the Miller Act, or the

Louisiana Prompt Payment Act. Greenup and Markel contend that the language of the Subcontract did not oblige Greenup to provide trucks to Five S for transporting fill dug out of the Spillway, or to pay for “standby time” that accrued when Five S alleges that it was unable to maintain necessary production levels because it did not have enough trucks on which it could load fill. Greenup and Markel argue that the Subcontract does not include any “agreed schedule other than what is required in the Prime Contract,” or a schedule or rate for trucks, and that Five S agreed to “wait for payment from Greenup based on USACES acceptance of ‘in-place quantities’” of fill. Five S and Hartford filed memoranda in opposition, arguing that Greenup and Markel are

not entitled to a dismissal because there is enough evidence supporting their claim for relief based on the plain language of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baker v. Putnal
75 F.3d 190 (Fifth Circuit, 1996)
Plotkin v. IP Axess Inc.
407 F.3d 690 (Fifth Circuit, 2005)
Arias-Benn v. State Farm Fire & Casualty Insurance
495 F.3d 228 (Fifth Circuit, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Bernard Lumber Co. v. Lanier-Gervais Corp.
560 So. 2d 465 (Louisiana Court of Appeal, 1990)
United States v. Hirani Eng'g & Land Surveying, P.C.
345 F. Supp. 3d 11 (D.C. Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Greenup Industries, LLC v. Five S Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenup-industries-llc-v-five-s-group-llc-laed-2023.