Elte, Inc. v. S. S. Mullen, Inc.

469 F.2d 1127
CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 11, 1972
Docket71-2572
StatusPublished
Cited by19 cases

This text of 469 F.2d 1127 (Elte, Inc. v. S. S. Mullen, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elte, Inc. v. S. S. Mullen, Inc., 469 F.2d 1127 (9th Cir. 1972).

Opinion

FRED M. TAYLOR, District Judge:

The Appellee, Elte, Inc. (Elte), brought this diversity action against Appellant, S. S. Mullen, Inc. (Mullen), in the United States District Court for the District of Oregon, seeking compensation for work allegedly performed beyond the scope of its subcontract with Mullen and for damages as a result of alleged breaches of the contract by Mullen. Mullen counterclaimed seeking to recover from Elte the sum of $81,400.00 for work Mullen performed and which it claimed Elte was obligated to perform under the terms of the subcontract.

The case was tried before the court, without a jury, and judgment was thereafter entered awarding Elte the sum of $109,655.49, together with interest at the rate of six per cent per annum from September 1, 1968, and dismissing Mullen’s counterclaim, from which judgment Mullen has appealed.

On March 31, 1967, Mullen entered into a contract with the United States, through the Corps of Engineers, to relocate approximately 12 miles of the Ca-mas Prairie Railroad along the north bank of the Snake River in Whitman County, Washington, as a part of the *1129 Little Goose Dam and Lock Project. The work in relocating the railroad right-of-way included grading, excavation, use of borrow materials, construction of embankments from materials excavated and obtained from borrow sources and the placement of a riprap protective blanket on the embankments.

The government, before bidding and after field exploration, designated two quarry sites known as the Hastings Hill Quarry and Stark Quarry as approved sources from which riprap materials could be taken, and also permitted the contractor to select its own sources. Rip-rap was defined in the specification as stone produced from bedrock which requires drilling and blasting for removal. The specification required that the rip-rap be placed at a certain time and in a specified manner during the construction.

Mullen was directed to proceed with its work on April 12, 1967. It experienced delay in obtaining a riprap subcontractor even though its schedules for the job required the placement of riprap by September 1, 1967. Sometime prior to November, 1967, Mullen had located a potential riprap source known as Smith Quarry at an advantageous location for the job. Prior to quoting a price and entering into the subcontract with Mullen, Mr. Forman, president and owner of Elte, visited and inspected the Smith Quarry site and also the Stark Quarry.

Originally, Mullen and Elte attempted to negotiate a contract involving the production, hauling and placing of the riprap. However, the parties could not agree on a price for all of this work and a written contract was negotiated limiting Elte’s functions to drilling, shooting and processing the riprap, leaving quarry location, development, removal of overburden, hauling and placing of riprap with Mullen. The subcontract was executed on November 2,1967. 1

*1130 Elte commenced operations at the Smith Quarry on November 19, 1967. The Smith Quarry proved to be a disappointment due to the lack of available riprap. Despite the fact that the government had previously advised Mullen that success would be unlikely in this quarry, Mullen directed Elte to continue exploring and to open up other areas in the quarry site. Elte was instructed to record its costs for the exploration work and present them for payment. On January 28, 1968, Elte submitted a bill to Mullen for this work in the sum of $29,466.15. A supplemental billing was sent to Mullen on September 7, 1968 in the amount of $36,573.95.

On or about January 5, 1968, Elte was directed to move into the Stark Quarry where all of the riprap for the project was produced except for 3,700 cubic yards salvaged from Smith Quarry.

On this appeal, appellant does not challenge the trial court’s findings of fact nor the necessity of applying the “clearly erroneous” rule. It is appellant’s contention that the issues raised on this appeal involve only questions of law.

Mullen first contends that the allowance by the trial court of $29,000 as damages for the work done at the Smith Quarry was error. Elte claims that Mullen breached its subcontract because of Mullen’s failure to provide Elte with a suitable quarry from which Elte could obtain and manufacture riprap. Mullen’s defense to this claim is that the subcontract contains no warranty or representation concerning the quality or nature of material to be found in Smith Quarry. The trial court found:

“On the first quarry, [referring to the Smith Quarry] I find that the excessive expenses directly attributable to the abortive effort to exploit the nonproductive quarry were $29,000.00. I further find that this expense was caused by the defendant’s unwarranted insistence upon trying to obtain rock where the government had previously advised the defendant that success would be unlikely.”

Section 1 of the subcontract contains the following provisions:

“Contractor [Mullen] will provide quarry site and access roads.”
“Contractor will remove overburden to expose rock which cannot be ripped.”

It is clear that, pursuant to these two provisions of the subcontract, Mullen expressly undertook the obligation of locating suitable quarries and in removing all the overburden to expose rock which could not be ripped. Mullen was the one who chose the Smith Quarry and directed Elte to the site. Elte’s ob *1131 ligation under the subcontract did not begin until a suitable quarry site containing riprap was selected by Mullen. The crux of the agreement between these parties was the obtaining of suitable riprap in a reasonably economical manner from a quarry selected by Mullen. To interpret this contract as not requiring Mullen to provide a quarry where riprap could be produced would render the entire contract meaningless. In Purvis v. United States, 344 F.2d 867, 870 (9th Cir. 1965), this court stated, inter alia, that writings should be interpreted and applied so that they may have effect rather than be destroyed. This court subscribes to the principle that where one interpretation makes a contract unreasonable or such that a prudent person would not normally contract under such circumstances, but another interpretation equally consistent with the language would make it reasonable, fair and just, the latter interpretation would apply. See Stender v. Twin City Foods, Inc., 5 Wash.App. 809, 490 P.2d 1311, 1315 (1971).

Mullen also argues that the admission in evidence of the negotiations preceding the execution of the subcontract was error. We disagree. A trial court is entitled to ascertain what the intention of the parties was at the time of contracting, and evidence of the character of the subject matter, the nature of the business, antecedent offers and counteroffers, and the communications of the parties with each other in the process of negotiation is admissible for such purpose. Seaver v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kizer v. PTP, Inc.
129 F. Supp. 3d 1000 (D. Nevada, 2015)
United States v. Brimhall-Palmer Construction, Inc.
62 F. App'x 141 (Ninth Circuit, 2003)
Cargill, Inc. v. Mountain Cement Co.
891 P.2d 57 (Wyoming Supreme Court, 1995)
Woodson Const. Co., Inc. v. RL Abshire Const. Co.
459 So. 2d 566 (Louisiana Court of Appeal, 1984)
Domingo v. New England Fish Co.
727 F.2d 1429 (Ninth Circuit, 1984)
Shakey's Inc. v. Covalt
704 F.2d 426 (Ninth Circuit, 1983)
Cook v. Southern Pacific Transportation Co.
623 P.2d 1125 (Court of Appeals of Oregon, 1981)
Herbert S. Zim v. Western Publishing Company
573 F.2d 1318 (Fifth Circuit, 1978)
City of Seattle v. Dyad Construction, Inc.
565 P.2d 423 (Court of Appeals of Washington, 1977)
Rissler & McMurry Co. v. Atlantic Richfield Co.
559 P.2d 25 (Wyoming Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
469 F.2d 1127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elte-inc-v-s-s-mullen-inc-ca9-1972.