Woodson Const. Co., Inc. v. RL Abshire Const. Co.

459 So. 2d 566, 1984 La. App. LEXIS 9849
CourtLouisiana Court of Appeal
DecidedNovember 7, 1984
Docket83-1151
StatusPublished
Cited by28 cases

This text of 459 So. 2d 566 (Woodson Const. Co., Inc. v. RL Abshire Const. Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodson Const. Co., Inc. v. RL Abshire Const. Co., 459 So. 2d 566, 1984 La. App. LEXIS 9849 (La. Ct. App. 1984).

Opinion

459 So.2d 566 (1984)

WOODSON CONSTRUCTION COMPANY, INC., Plaintiff-Appellee,
v.
R.L. ABSHIRE CONSTRUCTION COMPANY, INC., Defendant-Appellant.

No. 83-1151.

Court of Appeal of Louisiana, Third Circuit.

November 7, 1984.
Rehearing Denied December 13, 1984.

*567 Plauche, Smith & Nieset, A. Lane Plauche, Lake Charles, for plaintiff-appellee.

Jones, Jones & Alexander, J.B. Jones, Jr., Cameron, for defendant-appellant.

Dennis Vidrine, Lafayette, for defendant-appellee.

Before DOMENGEAUX, CUTRER and LABORDE, JJ.

CUTRER, Judge.

The issue presented in this appeal is whether the trial court properly granted a motion for summary judgment nullifying a default judgment for the lack of subject matter jurisdiction. The default judgment was rendered in a separate suit entitled R.L. Abshire Construction Company, Inc. v. Woodson Construction Company, Inc., 459 So.2d 571 (La.App. 3rd Cir.1984). We shall render a separate opinion in this latter case.

After the default judgment was rendered in favor of Abshire and against Woodson in the amount of $2,356,354.34, Woodson filed this action of nullity seeking to set aside the default judgment. The trial court granted Woodson's motion for summary judgment nullifying the default judgment rendered in the separate suit. Appeals were taken in both suits.

We shall first consider the appeal in this nullity action for the reason that, if Woodson is successful in this nullity action, the issues presented in the appeal of the default judgment, 459 So.2d 571, will be rendered moot and that suit will be subject to dismissal.

FACTS

The United States Department of Energy hired Parsons-Gilbane, a Joint Venture (Parsons) as the prime contractor for the construction of a Petroleum Reserve Project near Sulphur, Louisiana. The project involved the preparation of the site, drilling of wells, and installation of equipment for the storage of oil in a salt dome. Woodson Construction Company, Inc. (Woodson) entered into a subcontract with Parsons to prepare the project site. Woodson's contract contained an arbitration clause covering all disputes arising under the contract. Woodson subcontracted much of the work to various other subcontractors, including defendant, R.L. Abshire Construction Company, Inc. (Abshire). For the sake of brevity, the contract between Parsons and Woodson will be referred to in this opinion as the "Parsons-Woodson contract." The contract between Woodson and Abshire will be referred to as the "Woodson-Abshire contract."

As the work progressed, a dispute arose, involving Parsons, Woodson and the subcontractors as to the sums owed to the subcontractors (including Abshire) for extra work performed by them. Upon completion of the job, Woodson and its subcontractors, including Abshire, entered into an agreement to retain Frederick Crowley, an expert arbitration attorney, to present their disputed claim to arbitration. Mr. Crowley presented Woodson's claims against Parsons in a six-week long arbitration proceeding entitled "In the Matter of Arbitration between Woodson Construction Company and Parsons-Gilbane, A Joint Venture." Mr. Crowley also represented and presented the claims of Abshire and the other subcontractors in the same proceeding under the sponsorship of Woodson. The panel awarded Woodson and its subcontractors the aggregate amount of $2,309,394.00. The total sum granted in the award was *568 paid to Woodson, which then paid all of the subcontractors their share as specified in the arbitration award. Abshire refused to accept payment because the company president, Robert Abshire, believed the arbitration award was not enough to cover its claim. Abshire then filed suit Number 83-983 against Woodson for $2,707,011.42. Upon Woodson's failure to timely file an answer, a default judgment against Woodson was entered in the amount of $2,356,354.83.[1] A motion for a new trial by Woodson was denied as being untimely filed. Woodson then appealed that judgment.

Woodson then filed this suit to nullify the default judgment, rendered in suit Number 83-983, for lack of subject matter jurisdiction. The trial judge issued a temporary restraining order pending hearing on Woodson's rule for a preliminary injunction. The trial judge held a hearing and granted the preliminary injunction enjoining the enforcement of the default judgment. Woodson then filed a motion for summary judgment. Woodson argued that the arbitration clause divested the trial court of subject matter jurisdiction in the rendition of the default judgment. The trial judge granted the summary judgment and also permanently enjoined Abshire from enforcing the default judgment. Abshire appeals from that judgment and we affirm.

SUMMARY JUDGMENT

A party is entitled to summary judgment "if the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to material fact, and the mover is entitled to judgment as a matter of law." LSA-C.C.P. art. 966. All doubts as to whether to grant a summary judgment must be resolved against the party seeking it. Kay v. Carter, 243 La. 1095, 150 So.2d 27 (La.1963). However, a summary judgment is proper when reasonable minds must inevitably conclude that the mover is entitled to judgment on the facts submitted to the court. Cates v. Beauregard Electric Cooperative, Inc., 328 So.2d 367 (La.1976); Clement v. Taylor, 382 So.2d 231 (La.App. 3rd Cir.1980). The plaintiff's motion for summary judgment was granted on the grounds that the default judgment is a nullity for lack of subject matter jurisdiction under LSA-C.C.P. art. 2002.

The propriety of the summary judgment in this case depends on the resolution of two questions. First, whether Abshire agreed to submit his disputed claims to arbitration.[2] Second, if so, does the submission of the dispute to arbitration divest the trial court of subject matter jurisdiction?

The Parsons-Woodson contract contains an arbitration clause which reads in pertinent part as follows:

"ARTICLE XII—DISPUTES
1.0 Any dispute arising under this subcontract that is not settled by agreement of the parties, or pursuant to the administrative relief provided for in the following paragraphs of this clause, shall be settled by arbitration as provided in Section 5 of this clause.....
* * * * * *
5.0 In the event of any dispute, not settled by agreement of the parties or pursuant to the administrative relief provided for in the proceeding [sic] Paragraphs 1.0, 2.0, or 3.0 of this Article, between Contractor and Subcontractor with respect to the interpretation or performance of this Subcontract, the same shall be settled by arbitration by the American Arbitration Association ("Association") before a single arbitrator in accordance *569 with the Association's Construction Industry Arbitration Rule, at Dallas, Texas....."

The Woodson-Abshire contract contains the following clause:

"The Subcontractor is required to complete the above described work according to the terms and conditions of that certain contract by and between Woodson Construction Company, Inc. and Parsons-Gilbane, A Joint Venture with the Department of Energy under Subcontract No. 287-1072-000 according to the plans and specifications as amended, submitted thereunder and let for bids by invitation for bids dated October 17, 1978...." (Emphasis ours.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Broussard v. First Tower Loan, LLC
150 F. Supp. 3d 709 (E.D. Louisiana, 2015)
Star Transport, Inc. v. Pilot Corp.
171 So. 3d 1195 (Louisiana Court of Appeal, 2015)
Aeneas Williams Imports, L.L.C. v. Carter
131 So. 3d 894 (Louisiana Court of Appeal, 2012)
Williams v. International Offshore Services, LLC
106 So. 3d 212 (Louisiana Court of Appeal, 2012)
FIA Card Services, N.A. v. Weaver
62 So. 3d 709 (Supreme Court of Louisiana, 2011)
Lamarque v. BARBARA ENTERPRISES, INC.
958 So. 2d 708 (Louisiana Court of Appeal, 2007)
Abshire v. Belmont Homes, Inc.
896 So. 2d 277 (Louisiana Court of Appeal, 2005)
Roland J. Abshire v. Belmont Homes, Inc.
Louisiana Court of Appeal, 2005
Dufrene v. HBOS MFG., LP
872 So. 2d 1206 (Louisiana Court of Appeal, 2004)
Peter Vicari General Contractor, Inc. v. St. Pierre
831 So. 2d 296 (Louisiana Court of Appeal, 2002)
Thomas v. Desire Community Housing Corp.
773 So. 2d 755 (Louisiana Court of Appeal, 2000)
Frisard v. Autin
747 So. 2d 813 (Louisiana Court of Appeal, 1999)
Martin v. Combine Quality Oilfield Services, Inc.
741 So. 2d 685 (Louisiana Court of Appeal, 1999)
J. Caldarera & Co. v. LA. STADIUM
725 So. 2d 549 (Louisiana Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
459 So. 2d 566, 1984 La. App. LEXIS 9849, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodson-const-co-inc-v-rl-abshire-const-co-lactapp-1984.