Hensel Phelps Construction Co. v. United States

413 F.2d 701, 1969 U.S. App. LEXIS 11327
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 28, 1969
Docket10137_1
StatusPublished
Cited by3 cases

This text of 413 F.2d 701 (Hensel Phelps Construction Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hensel Phelps Construction Co. v. United States, 413 F.2d 701, 1969 U.S. App. LEXIS 11327 (10th Cir. 1969).

Opinion

413 F.2d 701

HENSEL PHELPS CONSTRUCTION Co., a Colorado corporation and
Aetna Casualty and Surety Company, a Connecticut
corporation, Appellants,
v.
UNITED STATES of America for the Use and Benefit of Reynolds
Electrical and Engineering Company, Inc., Appellee.

No. 10137.

United States Court of Appeals Tenth Circuit.

July 28, 1969.

John J. Mullins, Jr., Denver, Colo. (Gorsuch, Kirgis, Campbell, Walker & Grover, Denver, Colo., were with him on the brief), for appellants.

Stuart S. Gunckel, Denver, Colo. (Akolt, Shepherd, Disk & Rovira, Denver, Colo., were with him on the brief), for appellee.

Before LEWIS, BREITENSTEIN and HOLLOWAY, Circuit Judges.

BREITENSTEIN, Circuit Judge.

In this Miller Act case, Reynolds Electrical and Engineering Company, a subcontractor, had judgment for $22,660 against Hensel Phelps Construction Company, the prime contractor, and its surety because of extra work performed by Reynolds in the construction of certain motor repair shops for the United States at Fort Carson, Colorado.

Hensel Phelps disputes the findings of the trial court that the work was not covered by the written subcontract and that Reynolds performed the work at the request of Hensel Phelps. The prime contract included the installation of 120 electrically operated overhead doors. Reynolds was the electrical subcontractor. The doors were supplied by McKee Door Company. The disputed items relate to the wiring of certain switches controlling the doors and to the additional wiring necessitated by the relocation of the motors which operate the doors.

The operation of each door requires an electric motor, two limit switches, and a safety switch. At the time of execution of the Reynolds contract, the drawings showed the motor location on the wall at the top of the door and did not show the control wiring for the switches. The door contract with McKee was made some 8-10 months after the Reynolds contract. The drawings accompanying the McKee contract showed the motor location some 20 feet inside from the top of the door opening and set out the control wiring for the switches.

In its description of the work to be performed the Reynolds contract specifically includes all work under Section 36 of the specifications and says: 'Included in this subcontract are all required equipment connections, overhead door hookup, and fence grounding.' Section 36-21 of the specifications reads:

'All wiring for the connection of motors and control equipment as indicated on the electrical drawings shall be furnished and installed under this section of the specifications. Except as otherwise specifically noted, automatic-control wiring, signaling, and protective devices are not included in this section of the specifications, but shall be furnished and installed under other sections of the specifications. Control wiring not shown on the electrical drawings shall be furnished under other sections of the specifications.'

We are concerned with automatic control wiring which was not shown on the drawings and with additional wiring caused by the change in motor location.

The arguments of Hensel Phelps are not persuasive. The general reference in the contract to 'over head door hookup' does not control over the specific provision of 36-21 that 'automaticcontrol wiring, signaling, and protective devices' are not included. Reliance on 2 of the specifications is misplaced. It provides that anything mentioned or shown in either the specifications or drawings shall be considered as if mentioned in both. The wiring of the switches was not shown on the drawings originally submitted to Reynolds when it bid on and contracted to do the work, and 36-21 of the specifications excludes such wiring. The reference to 18-10c(5) of the specifications is not appropriate because that section is not included within the provision of the Reynolds contract covering the work to be performed. We construe 36-16 to cover design changes in the equipment. The Hensel Phelps construction would make 36-16 conflict with 36-21. The intent of the parties to a contract shall be ascertained from the contract as a whole rather than from a specific provision. Fanderlik-Locke Co. v. United States, 10 Cir.,285 F.2d 939, 947, cert. denied 365 U.S. 860, 81 S.Ct. 826, 5 L.Ed.2d 823. When we view the Reynolds contract as a whole, we are convinced that neither the wiring for the switches nor the additional wiring required by the change in motor location was covered, or intended to be covered.

Before the execution of the Reynolds contract, an official of Reynolds discussed with an official of Hensel Phelps the situation regarding the overhead doors and said in effect that Reynolds was responsible for anything on the drawings. Hensel Phelps did not disagree. This testimony is said to be inadmissible. It was received subject to the court's determination of whether an ambiguity existed. If there was an ambiguity, the evidence was proper. If there was not, the evidence was not prejudicial. We agree with the trial court that the work in question was not covered.

Reynolds told Hensel Phelps before the electrical work on the doors was undertaken that it considered the wiring for switches and for the changed motor location extra work. Later, Reynolds wrote Hensel Phelps a letter saying that the work was extra and that its estimate therefor was $19,519. It also said that in the interest of maintaining the job schedules it would proceed with the questioned work. About two months thereafter, Hensel Phelps wrote McKee that it considered the questioned wiring part of the McKee contract. This evidence was pertinent because if the contract is not clear the conduct of the parties is given great weight in construing it. Sam Macri & Sons, Inc., v. United States, 9 Cir., 313 F.2d 119, 124; and see Fanderlik-Locke Co. v. United States, 10 Cir., 285 F.2d 939, 947, cert. denied 365 U.S. 860, 81 S.Ct. 826. Although we disagree with the Hensel Phelps contentions that the work was covered by the Reynolds contract, the effect of those contentions, if any, is to make the contract unclear. Hensel Phelps was not prejudiced by the admission of the evidence.

The wiring for the switches was not within the Reynolds contract. The change of motor location required additional wiring. A contractor who bids for work has the right to rely on the plans and specifications submitted to him for bidding purposes. Wunderlich Contracting Company v. United States, 10 Cir., 240 F.2d 201, 205, cert. denied 353 U.S. 950, 77 S.Ct. 861, 1 L.Ed.2d 859. Burdens other than those contemplated by the contract may not be placed upon the contractor without additional compensation. Id. The wiring in question was extra work for which Reynolds is entitled to be paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
413 F.2d 701, 1969 U.S. App. LEXIS 11327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hensel-phelps-construction-co-v-united-states-ca10-1969.