Indemnity Insurance Company of North America v. Browning-Ferris MacHinery Company, John A. Petty and Joe J. Wilson

227 F.2d 804, 1955 U.S. App. LEXIS 4670
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 9, 1955
Docket15493
StatusPublished
Cited by10 cases

This text of 227 F.2d 804 (Indemnity Insurance Company of North America v. Browning-Ferris MacHinery Company, John A. Petty and Joe J. Wilson) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indemnity Insurance Company of North America v. Browning-Ferris MacHinery Company, John A. Petty and Joe J. Wilson, 227 F.2d 804, 1955 U.S. App. LEXIS 4670 (5th Cir. 1955).

Opinion

BROWN, Circuit Judge.

A ease so simple that master strategists could not possibly have planned it into complexity has inadvertently become so snarled that we must painstakingly unthread the backlash to assure the result so evidently required.

Browning-Ferris sued Petty, the primé contractor, Wilson, the subcontractor, and Indemnity Insurance, surety, on a Miller Act, 40 U.S.C.A. § 270, bond for unpaid rental charges for machinery used on a Government contract. Execution of the bond and the giving of the. 90-day notice by the materialman to the prime contractor, 40 U.S.C.A. 270b (a), was admitted. 1 2 So the area of controversy was confined to the defense that (a) the machinery was in subcontractor’s hands under a lease-purchase, rather than a rental, contract, and (b) the machinery had been used on the job 5 days only rather than 38 as claimed. On the close of all of the evidence, the Court denied, the motions of all parties for a directed verdict and submitted the case to the jury by a charge to which no exceptions were taken.

It was here that the trouble started. Despite his denial of all defendants’ motions for directed verdict then just immediately announced, the Court in his charge instructed the jury to find for Petty, prime contractor. 2 But this the jury did not do. It returned a verdict for the plaintiff, but, literally, against none. 3 The final judgment under review here adjudged recovery against Wilson, the subcontractor, and the surety but in favor of Petty. 4

Except -for their respective motions for directed verdict, all declined, no one, up to this point, made any objection to the actions of the Trial Court. This era of contentment ended shortly when new, separate counsel appeared for the surety contending that the rendered judgment could not properly stand against the *807 surety since the principal .(Petty) had been discharged. 5 These motions denied, this appeal ensued, the surety now urging that the judgment should be reformed to discharge the surety if the principal, Petty, remains discharged; that the judgment be reformed to render judgment for plaintiff against Petty, and that the surety be given judgment over against Petty and Wilson.

It is clear, indeed conceded by all except Petty, that the instruction to the jury and the judgment dismissing Petty was wrong. The suit was on the bond in which Petty was a principal obligor. If, on the factual basis, the surety was liable, so was the principal. But if wrong, what are the consequences?

The surety urges, albeit somewhat faintly and most likely as a makeweight for reformation of the judgment to hold Petty equally liable, that on a familiar rule of suretyship where the principal has been discharged, it is an automatic release of the surety. 6

No contention is made here, or below, that on the facts and the jury verdict there was any real, meritorious basis for discharging the surety. The plea, thus made, is the harsh one that since the Trial Court committed patent error, we must compound it by one of our own. The law is no such strait jacket, either generally, or in a Miller Act situation specifically. That Act, and bonds furnished under it, present matters for application of federal law, Continental Casualty Company v. Schaefer, 9 Cir., 173 F.2d 5; Liebman v. United States, 9 Cir., 153 F.2d 350, the underlying approach of which is that, “technical rules otherwise protecting sureties from liability have never been applied in proceedings under this statute,” Illinois Surety Co. v. John Davis Co., 244 U.S. 376, 37 S.Ct. 614, 61 L.Ed. 1206. Fleisher Engineering & Construction Co. v. United States, 311 U. S. 15, 61 S.Ct. 81, 85 L.Ed. 12. Justice requires that plaintiff, already long delayed in the amounts so clearly due through circumstances wholly uninvited by it, obtain the benefits of the judgment against the surety and it will be affirmed.

It seems equally plain that the judgment dismissing Petty was wrong and that the surety, whose rights are likely to be adversely affected if it stands, has taken adequate, timely steps for review by us. The point was plainly reserved in the motions for new trial and to amend and reform the judgment. The fact that the surety’s counsel 7 did *808 not except to the Court's charge (footnote 2 supra) discharging Petty is not an acquiescence in the subsequent erroneous judgment, specifically excepted to, since the jury, though instructed to do so, failed to return a verdict for Petty 8 and the judgment recitation is incorrect on the fact of such a verdict, or that the evidence was undisputed in favor of Petty. Disregarding all that occurred prior to the retirement of the jury, the judgment as entered was wrong in fact. The surety promptly and sufficiently pointed this out.

Thus far it is simple — the judgment for Petty was wrong and must be reversed. The serious question is whether we can now order the Trial Court to do what ought to have been done or must we send it back for a new trial as to Petty?

We cannot direct the entry of such a judgment on the theory that the Trial Court, upon the plaintiff’s motion for directed verdict, should have done so below, for there are issues of fact requiring jury decision. That is not decisive, however, since we think that there has already been a jury verdict adverse to Petty on all of the issues he was entitled to have submitted. It must be remembered that the liability here asserted is that on the bond to respond for unpaid claims against subcontractors. Petty’s liability flowed therefore from that imposed on Wilson, the subcontractor. Where a subcontractor is involved, as here, the liability of the prime contractor, as principal, is derivative and the issues to be submitted, whether specially or by general verdict, relate only to the subcontractor. 9 As framed by the pleadings and as made by the evidence, the controversy was narrowed to the simple one of whether Wilson had purchased rather than rented, and if rented, the extent of the use on the federal job site.

Had the Trial Court, therefore, not given the erroneous direction freeing Petty, there Would have been nothing submitted not already in the charge. It would have been precisely as it was concerning the surety, since under the form of instructions used the jury was not charged, nor was it necessary to do so, to find for the plaintiff and against the surety.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
227 F.2d 804, 1955 U.S. App. LEXIS 4670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indemnity-insurance-company-of-north-america-v-browning-ferris-machinery-ca5-1955.