Powercom, Inc., V. Valley Electric Co. Of Mt. Vernon, Inc.

CourtCourt of Appeals of Washington
DecidedJanuary 8, 2024
Docket85120-9
StatusPublished

This text of Powercom, Inc., V. Valley Electric Co. Of Mt. Vernon, Inc. (Powercom, Inc., V. Valley Electric Co. Of Mt. Vernon, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Powercom, Inc., V. Valley Electric Co. Of Mt. Vernon, Inc., (Wash. Ct. App. 2024).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

POWERCOM, INC., a Washington No. 85120-9-I corporation, DIVISION ONE Appellant,

v.

VALLEY ELECTRIC CO. OF MT. VERNON, INC., a Washington corporation; ARGONAUT INSURANCE COMPANY, a foreign insurer (Bond No. SUR0043723-00); CLARK CONSTRUCTION GROUP, LLC, a foreign limited liability company; TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, a PUBLISHED OPINION foreign insurer; FIDELITY AND DEPOSIT COMPANY OF MARYLAND, a foreign insurer; FEDERAL INSURANCE COMPANY, a foreign insurer, and ZURICH AMERICAN INSURANCE CO., a foreign insurer (Bond Nos. 106308203/ 82298673/09190971 and Bond Nos. 106356881/82298695/09207256); and PORT OF SEATTLE, a Washington State municipal corporation,

Respondents.

BOWMAN, J. — PowerCom Inc., a subcontractor on a renovation project at

the Seattle-Tacoma International Airport, appeals the trial court’s stay of its pass-

through claims against the Port of Seattle (Port), its prime contractor Clark

Construction Group LLC (Clark), and their sureties pending the final resolution of

Clark’s lawsuit against the Port. PowerCom argues the trial court’s stay violated No. 85120-9-I/2

its right to sue under chapter 39.08 RCW, Washington’s “Little Miller Act.”

Because the plain language of PowerCom’s subcontract explicitly waives its right

to sue under the Little Miller Act pending resolution of pass-through claims, we

affirm.

FACTS

In 2015, the Port hired Clark to renovate the “International Arrivals Facility

South Satellite Corridor” at Seattle-Tacoma International Airport. The Port and

Clark executed a design-build contract under which Clark was the prime

contractor (Main Contract). In 2017, Clark executed a subcontract with Valley

Electric Co. of Mt. Vernon Inc. (Valley) to install electric security, surveillance,

and monitoring systems. And in 2018, Valley subcontracted with PowerCom to

provide, install, and test certain electrical cables within Valley’s scope of work.1

All three contracts contain dispute resolution provisions. The Main

Contract has a multistep dispute resolution process. First, the Port and Clark

must meet to try to resolve any claims. If they do not resolve their dispute, they

must submit the claim to a dispute resolution board. If they still cannot resolve

their claim, the Port and Clark must mediate the claim under the voluntary

construction mediation rules of the American Arbitration Association. And finally,

having exhausted those avenues, the Port or Clark may file a lawsuit to resolve

the claim.

1 Clark and Valley each posted bonds with surety companies to ensure payment to laborers, subcontractors, and material suppliers as required for public works contracts under RCW 39.08.010.

2 No. 85120-9-I/3

The Main Contract applies to claims not only between the Port and Clark

but also to claims Clark “assert[s] on behalf of [a] Subcontractor, Sub-

subcontractor, or Supplier.” Claims asserted by Clark for subcontractors are

called “pass-through claims.” The contract between Clark and Valley

incorporates the dispute resolution procedures of the Main Contract for any pass-

through claims but authorizes arbitration of non-pass-through claims “at Clark’s

sole option.”

The subcontract between Valley and PowerCom provides different

processes for dispute resolution depending on the type of claim. For all pass-

through claims, the contract binds PowerCom to “the procedure and final

determination as specified in the Main Contract.” And PowerCom agreed that

it will not take, or will suspend, any other action or actions with respect to any such claims and will pursue no independent litigation with respect thereto, pending final determination of any dispute resolution procedure between [the Port] and [Clark].

All other claims—that is, non-pass-through claims—“shall be decided by

arbitration.”2

PowerCom began its electrical work in late 2018, but between March 2020

and October 2021, it experienced delays because of the COVID-193 protocols

that the Port, Clark, and Valley implemented at the project site. In October 2021,

PowerCom submitted a pass-through claim to Valley, seeking payment of

2 For non-pass-through claims, the contract also requires the parties to attend at least four hours of mediation before arbitration. And if PowerCom’s subcontract and the Main Contract conflict, PowerCom’s subcontract controls. 3 Coronavirus disease 2019.

3 No. 85120-9-I/4

$1,306,250 for its total increased costs from the COVID-19 restrictions.4 Valley

passed PowerCom’s and their own COVID-19-related claims to Clark. Clark then

submitted both claims along with its own COVID-19-related claims to the Port.

The Port disputed the claims, so the Port and Clark engaged in the

dispute resolution process described in the Main Contract. That process failed to

resolve the claims. So, in December 2022, Clark sued the Port for recovery of

its, Valley’s, and PowerCom’s losses.

On October 19, 2022, PowerCom sued the Port, Clark and its sureties,

and Valley and its sureties, seeking compensation for its COVID-19-related costs

and costs associated with its non-pass-through claims. It asserted claims of

breach of contract; breach of the covenant of good faith and fair dealing; violation

of the Prompt Payment Act, chapter 39.76 RCW; unjust enrichment; and

payment for its “account stated.” PowerCom also sought foreclosure on Clark’s

and Valley’s sureties’ bonds under the Little Miller Act.

In January 2023, PowerCom moved to compel arbitration of its claims

against all parties. PowerCom argued that the arbitration clause in its

subcontract applies to both pass-through and non-pass-through claims and

asked that the claims be arbitrated together. It also asked for a stay pending that

arbitration. Clark agreed to stay and arbitrate PowerCom’s non-pass-through

claims. But it argued that the trial court should stay PowerCom’s COVID-19-

related claim pending resolution of its lawsuit against the Port.

4 PowerCom also submitted non-pass-through claims to Valley for extra work and unpaid change orders. In total, PowerCom sought a judgment of $2,643,330 plus sales tax and prejudgment interest.

4 No. 85120-9-I/5

The court granted PowerCom’s motion to compel arbitration for its non-

pass-through claims against Clark but denied it as to the pass-through claims.

The court stayed PowerCom’s COVID-19-related claim “pending resolution of

Clark’s lawsuit against [the] Port” because that “lawsuit includes [PowerCom]’s

pass-through COVID-19 claim.”

PowerCom appeals.5

ANALYSIS

PowerCom argues the court erred by staying its pass-through COVID-19-

related claim “pending resolution of Clark’s lawsuit against [the] Port.” According

to PowerCom, the court’s stay “indefinitely postponed” its ability to recover

payment on its claim in violation of the Little Miller Act. Clark argues that

PowerCom contractually waived by “ ‘clear and explicit’ language” its right to

recover under the Little Miller Act pending resolution of Clark’s lawsuit against

the Port.6 We agree with Clark.

A trial court has inherent power to stay its proceedings where the interest

of justice so requires. King v. Olympic Pipeline Co., 104 Wn. App. 338, 350, 16

P.3d 45 (2000).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
3A Industries, Inc. v. Turner Construction Co.
869 P.2d 65 (Court of Appeals of Washington, 1993)
Allen v. Cartan & Jeffrey Co.
7 F.2d 21 (Eighth Circuit, 1925)
Mayer v. Sto Industries, Inc.
132 P.3d 115 (Washington Supreme Court, 2006)
Mayer v. Sto Industries, Inc.
156 Wash. 2d 677 (Washington Supreme Court, 2006)
King v. Olympic Pipe Line Co.
16 P.3d 45 (Court of Appeals of Washington, 2000)
Fanderlik-Locke Co. v. United States
285 F.2d 939 (Tenth Circuit, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
Powercom, Inc., V. Valley Electric Co. Of Mt. Vernon, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/powercom-inc-v-valley-electric-co-of-mt-vernon-inc-washctapp-2024.