Powercom, Inc., V. Valley Electric Co. Of Mt. Vernon, Inc.
Opinion
IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
POWERCOM, INC., a Washington No. 85120-9-I corporation, DIVISION ONE
Appellant,
v.
VALLEY ELECTRIC CO. OF MT. VERNON, INC., a Washington corporation; ARGONAUT INSURANCE COMPANY, a foreign insurer (Bond No. SUR0043723-00); CLARK CONSTRUCTION GROUP, LLC, a foreign limited liability company; TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, a PUBLISHED OPINION foreign insurer; FIDELITY AND DEPOSIT COMPANY OF MARYLAND, a foreign insurer; FEDERAL INSURANCE COMPANY, a foreign insurer, and ZURICH AMERICAN INSURANCE CO., a foreign insurer (Bond Nos. 106308203/ 82298673/09190971 and Bond Nos. 106356881/82298695/09207256); and PORT OF SEATTLE, a Washington State municipal corporation,
Respondents.
BOWMAN, J. — PowerCom Inc., a subcontractor on a renovation project at the Seattle-Tacoma International Airport, appeals the trial court’s stay of its pass- through claims against the Port of Seattle (Port), its prime contractor Clark Construction Group LLC (Clark), and their sureties pending the final resolution of Clark’s lawsuit against the Port. PowerCom argues the trial court’s stay violated
its right to sue under chapter 39.08 RCW, Washington’s “Little Miller Act.” Because the plain language of PowerCom’s subcontract explicitly waives its right to sue under the Little Miller Act pending resolution of pass-through claims, we affirm.
FACTS
In 2015, the Port hired Clark to renovate the “International Arrivals Facility South Satellite Corridor” at Seattle-Tacoma International Airport. The Port and Clark executed a design-build contract under which Clark was the prime contractor (Main Contract). In 2017, Clark executed a subcontract with Valley Electric Co. of Mt. Vernon Inc. (Valley) to install electric security, surveillance, and monitoring systems. And in 2018, Valley subcontracted with PowerCom to provide, install, and test certain electrical cables within Valley’s scope of work.1 All three contracts contain dispute resolution provisions. The Main Contract has a multistep dispute resolution process. First, the Port and Clark must meet to try to resolve any claims. If they do not resolve their dispute, they must submit the claim to a dispute resolution board. If they still cannot resolve their claim, the Port and Clark must mediate the claim under the voluntary construction mediation rules of the American Arbitration Association. And finally, having exhausted those avenues, the Port or Clark may file a lawsuit to resolve the claim.
1
Clark and Valley each posted bonds with surety companies to ensure payment to laborers, subcontractors, and material suppliers as required for public works contracts under RCW 39.08.010.
The Main Contract applies to claims not only between the Port and Clark but also to claims Clark “assert[s] on behalf of [a] Subcontractor, Sub- subcontractor, or Supplier.” Claims asserted by Clark for subcontractors are called “pass-through claims.” The contract between Clark and Valley incorporates the dispute resolution procedures of the Main Contract for any pass- through claims but authorizes arbitration of non-pass-through claims “at Clark’s sole option.”
The subcontract between Valley and PowerCom provides different processes for dispute resolution depending on the type of claim. For all pass- through claims, the contract binds PowerCom to “the procedure and final determination as specified in the Main Contract.” And PowerCom agreed that
it will not take, or will suspend, any other action or actions with respect to any such claims and will pursue no independent litigation with respect thereto, pending final determination of any dispute resolution procedure between [the Port] and [Clark].
All other claims—that is, non-pass-through claims—“shall be decided by arbitration.”2 PowerCom began its electrical work in late 2018, but between March 2020 and October 2021, it experienced delays because of the COVID-193 protocols that the Port, Clark, and Valley implemented at the project site. In October 2021, PowerCom submitted a pass-through claim to Valley, seeking payment of
2 For non-pass-through claims, the contract also requires the parties to attend at least four hours of mediation before arbitration. And if PowerCom’s subcontract and the Main Contract conflict, PowerCom’s subcontract controls.
3 Coronavirus disease 2019.
$1,306,250 for its total increased costs from the COVID-19 restrictions.4 Valley passed PowerCom’s and their own COVID-19-related claims to Clark. Clark then submitted both claims along with its own COVID-19-related claims to the Port.
The Port disputed the claims, so the Port and Clark engaged in the dispute resolution process described in the Main Contract. That process failed to resolve the claims. So, in December 2022, Clark sued the Port for recovery of its, Valley’s, and PowerCom’s losses.
On October 19, 2022, PowerCom sued the Port, Clark and its sureties, and Valley and its sureties, seeking compensation for its COVID-19-related costs and costs associated with its non-pass-through claims. It asserted claims of breach of contract; breach of the covenant of good faith and fair dealing; violation of the Prompt Payment Act, chapter 39.76 RCW; unjust enrichment; and payment for its “account stated.” PowerCom also sought foreclosure on Clark’s and Valley’s sureties’ bonds under the Little Miller Act.
In January 2023, PowerCom moved to compel arbitration of its claims against all parties. PowerCom argued that the arbitration clause in its subcontract applies to both pass-through and non-pass-through claims and asked that the claims be arbitrated together. It also asked for a stay pending that arbitration. Clark agreed to stay and arbitrate PowerCom’s non-pass-through claims. But it argued that the trial court should stay PowerCom’s COVID-19- related claim pending resolution of its lawsuit against the Port.
4 PowerCom also submitted non-pass-through claims to Valley for extra work and unpaid change orders. In total, PowerCom sought a judgment of $2,643,330 plus sales tax and prejudgment interest.
The court granted PowerCom’s motion to compel arbitration for its non-
pass-through claims against Clark but denied it as to the pass-through claims. The court stayed PowerCom’s COVID-19-related claim “pending resolution of Clark’s lawsuit against [the] Port” because that “lawsuit includes [PowerCom]’s pass-through COVID-19 claim.”
PowerCom appeals.5 ANALYSIS
PowerCom argues the court erred by staying its pass-through COVID-19-
related claim “pending resolution of Clark’s lawsuit against [the] Port.” According to PowerCom, the court’s stay “indefinitely postponed” its ability to recover payment on its claim in violation of the Little Miller Act. Clark argues that PowerCom contractually waived by “ ‘clear and explicit’ language” its right to recover under the Little Miller Act pending resolution of Clark’s lawsuit against the Port.6 We agree with Clark.
A trial court has inherent power to stay its proceedings where the interest of justice so requires. King v. Olympic Pipeline Co., 104 Wn. App. 338, 350, 16 P.3d 45 (2000). We review a trial court’s stay of proceedings for an abuse of discretion. Id. at 348. A trial court abuses its discretion if its ruling is manifestly
5 The Port and Clark filed response briefs to PowerCom’s appeal. We issued a letter instructing Valley to also file a response brief. Valley responded, joining the Port and Clark’s arguments. PowerCom moved to strike Valley’s joinder, arguing that it “attempts to raise new issues and arguments for the first time on appeal” and that it is “not [a] respondent[ ] or necessary part[y] to PowerCom’s appeal under RAP 5.3(i).” We deny PowerCom’s motion to strike Valley’s response, which was submitted at the direction of this court and raised no new issues.
Free access — add to your briefcase to read the full text and ask questions with AI
Powercom, Inc., V. Valley Electric Co. Of Mt. Vernon, Inc. (Powercom, Inc., V. Valley Electric Co. Of Mt. Vernon, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.