Fett Roofing & Sheet Metal Co. v. Seaboard Surety Co.

294 F. Supp. 112, 13 Fed. R. Serv. 2d 102, 1968 U.S. Dist. LEXIS 9820
CourtDistrict Court, E.D. Virginia
DecidedOctober 10, 1968
DocketCiv. A. No. 6237
StatusPublished
Cited by5 cases

This text of 294 F. Supp. 112 (Fett Roofing & Sheet Metal Co. v. Seaboard Surety Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fett Roofing & Sheet Metal Co. v. Seaboard Surety Co., 294 F. Supp. 112, 13 Fed. R. Serv. 2d 102, 1968 U.S. Dist. LEXIS 9820 (E.D. Va. 1968).

Opinion

MEMORANDUM ORDER

KELLAM, District Judge.

The Court has for determination (a) two motions of plaintiff for summary judgment, (1) for $3,671.45 representing balance of payments due under amount of contract bid and (2) determining defendant Seaboard Surety Company is liable to it for extra work and material, with amount to be later established; (b) motion of United States to dismiss the action as to it; (c) motion of John B. McGaughy and others to dismiss as to them; (d) motion of Seaboard Surety Company for summary judgment against Fett Roofing & Sheet Metal Co., Inc.

Briefly stated, Fine and Salzberg, Inc. (Fine) entered into a contract with United States to construct a post office [114]*114facility in Hampton, Virginia. Fine subcontracted with Fett Roofing & Sheet Metal Co., Inc. (Fett) for certain roofing and other work at a price of $35,525.00. Seaboard Surety Company (Seaboard) became surety on the payment and performance bond given by Fine pursuant to its contract. John B. McGaughy and others (Architects) prepared the plans and specifications for the United States and were charged with supervision of the construction of the building.

During construction, a dispute arose over the proposed use of certain materials to meet the required performance of the roofing contract. Fett contended certain material met the requirements of the contract, but Architects ruled different (and more costly) materials were required. The contract required the materials used to produce a certain “U” factor — which is the measurement in BTUs of heat flow per hour — square foot (°F) through material.1

Pursuant to rulings by the Architects, different materials from those contended for by Fett were used, which Fett says was at an additional cost of $10,300.00. Fett contends this sum is an extra, and due to it. Fine says, on the one hand, it is not an extra, but required by the contract and specifications, as ruled by the Architects. Fine also says it is beyond the terms of the contract and specifications, and an extra to be charged to the United States.

Fett instituted this Miller Act action against Seaboard. Seaboard impleaded Fine, alleging it was entitled to indemnity from Fine. Seaboard filed a third-party complaint and amended third-party complaint against Architects and United States, alleging they were indebted to Seaboard for any sum found to be due by Seaboard to Fett. Fine filed a cross-claim against Architects and United States.

1. It is agreed Fett has performed all the work it contracted to perform. The only issue is whether it is entitled to all or any part of its claim of $10,300.00 alleged as extras. It is also agreed that of the contract bid of $35,525.00, all but $3,671.45 has been paid. There are no offsets or claims against this remaining sum of $3,671.45.

2. There exists, a dispute as to whether the Architects correctly interpreted the language of the contract as to what should be taken into consideration in determining when the “U” factor of the roof had been met. Too, the record at this point is not clear as to whether Fett met the requirement of the Architects as an obligation of its contract, or whether it did so as an extra at the direction of Fine, or otherwise. Some of the correspondence filed in the cause refers to an alleged request by Fett for arbitration on the issue of the “U” factor, but no conclusion can be reached at this point on this issue.

Fine also contends that Fett was required as a condition precedent to the institution of this suit, to submit its contention and claim to arbitration, as provided in paragraph 11 of the General Conditions of the Specifications and Contract between Fine and the United States. The conditions of said paragraph 11 are:

DISPUTES
(a) Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Lessor. The decision of the Contracting Officer shall be final and conclusive unless, within 30 days from the date of receipt of such copy, the Lessor mails or otherwise furnishes to the Contracting Officer a written appeal addressed to the Postmaster ■ General. The decision of the Postmaster General or his duly authorized [115]*115representative for the determination of such appeals shall be final and conclusive. This provision shall not be pleaded in any suit involving a question of fact arising under this contract as limiting judicial review of any such decision to cases where fraud by such official or his representative or board is alleged: PROVIDED, HOWEVER, that any such decision shall be final and conclusive unless the same is fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith or is not supported by substantial evidence. In connection with any appeal proceeding under this clause, the Lessor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the Lessor shall proceed diligently with the performance of the contract and in accordance with the Contracting Officer’s decision.
(b) This Disputes clause does not preclude consideration of questions of law in connection with decisions provided for in paragraph (a) above. Nothing in this contract, however, shall be construed as making final the decision of any administrative official, representative, or board on a question of law.

Fine says that by the terms of the contract between Fett and Fine, Fett agreed to be bound by all of the terms of Fine’s contract with the United States; that since the last mentioned contract provided for arbitration, Fett was bound by the same terms.

The purpose of the Miller Act (jurisdiction for this suit) is to provide security for those furnishing labor and/ or materials in the performance of a government contract. It should be given a liberal construction. United States for Benefit and on Behalf of Sherman v. Carter, 353 U.S. 210, 77 S.Ct. 793, 1 L. Ed.2d 776; St. Paul-Mercury Indemnity Co. v. United States, 238 F.2d 917 (10th Cir.). The prime contractor is the one required by the Act to furnish the bond, and the Act is not for his benefit. The provisions of the contract for settlement of disputes is for disputes “arising under this contract.” A right of appeal is furnished. The liability of the United States is to the prime contractor, and the contract dispute clause is for consideration of claims of the prime contractor. Nowhere does it provide for consideration of the claim of a subcontractor, and since there is no contract between the United States and the subcontractor, there is no basis for it arbitrating dispute between the sub-contractor and the general contractor. The sub-contractor has no standing before the contracting officer or the Postmaster General.

The remedy for a sub-contractor with a claim for labor or materials furnished on a contract with the United States is under the Miller Act. The fact that a prime contractor has a claim for the same amount pending under the dispute clause of the prime contract does not affect the Miller Act cases. John A. Johnson & Sons v. United States,

Related

Cite This Page — Counsel Stack

Bluebook (online)
294 F. Supp. 112, 13 Fed. R. Serv. 2d 102, 1968 U.S. Dist. LEXIS 9820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fett-roofing-sheet-metal-co-v-seaboard-surety-co-vaed-1968.