NAVCOM DEFENSE ELECTRONICS, INC., Plaintiff-Appellee, v. BALL CORPORATION, Defendant-Appellant

92 F.3d 877, 41 Cont. Cas. Fed. 76,975, 96 Daily Journal DAR 9681, 96 Cal. Daily Op. Serv. 5891, 1996 U.S. App. LEXIS 19897, 1996 WL 445329
CourtCourt of Appeals for the Ninth Circuit
DecidedAugust 8, 1996
Docket94-56396
StatusPublished
Cited by11 cases

This text of 92 F.3d 877 (NAVCOM DEFENSE ELECTRONICS, INC., Plaintiff-Appellee, v. BALL CORPORATION, Defendant-Appellant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NAVCOM DEFENSE ELECTRONICS, INC., Plaintiff-Appellee, v. BALL CORPORATION, Defendant-Appellant, 92 F.3d 877, 41 Cont. Cas. Fed. 76,975, 96 Daily Journal DAR 9681, 96 Cal. Daily Op. Serv. 5891, 1996 U.S. App. LEXIS 19897, 1996 WL 445329 (9th Cir. 1996).

Opinion

PER CURIAM:

This is an appeal from the district court’s order granting summary judgment for Nav-Com and enjoining Ball from submitting its contract dispute with NavCom to arbitration. For the reasons set out below, we affirm the district court’s denial of Ball’s motion to dismiss, reverse the court’s grant of summary judgment, vacate the order prohibiting arbitration, and remand for entry of an order consistent with this opinion.

I.

The Air Force awarded NavCom a contract to produce a radar altimeter system. NavCom subcontracted with Ball to design and manufacture antennas to be used as part of the system. The Air Force required that the antennas meet certain pass/fail criteria, including the “MIL-STD-810” salt fog test. NavCom developed the NavCom Salt Fog Test Procedure to ensure that its antennas met Air Force specifications, and the Air Force approved the test. The subcontract required Ball’s antennas to pass the NavCom Salt Fog Test.

Ball asserted that NavCom’s test procedures were more rigorous than those required by the Air Force, but eventually performed the test according to NavCom’s procedure. NavCom claimed that the antennas failed, while Ball insisted that the antennas passed the Air Force’s criteria. NavCom directed Ball to redesign the antennas.

Ball asked NavCom to pay an equitable adjustment for redesign costs in the amount of $1,467,949. Ball claimed its prototype antenna could meet Air Force pass/fail criteria and failed only because of the more stringent NavCom testing procedure. 1 Ball also claimed NavCom required a redesign option that was more costly than other options.

The central question is whether the dispute between NavCom and Ball should have been submitted to an Air Force contracting officer or to arbitration. The Ball/NavCom contract required that the decision of a contracting officer about the prime contract would be binding on the two parties in disputes about the subcontract. 2 In the same paragraph the contract provided that any dispute not settled by agreement of the parties would be submitted to arbitration. 3

NavCom informed Ball that it planned to submit a claim to the contracting officer as specified in the contract. The claim submitted by NavCom described the dispute between NavCom and Ball and then argued, ostensibly on behalf of Ball, that the Air Force should be liable for increased costs because the Air Force’s pass/fail criteria *879 were ambiguous. 4 Although Ball cooperated to at least some degree in drafting the claim (as required under the contract), Ball objected throughout the process to submission of the claim to the contracting officer. For instance, in a letter commenting on a draft version of the claim NavCom planned to submit, Ball wrote:

Ball wishes to be on record that it has no claim against the Air Force and therefore does not endorse NavCom’s statements in the draft letter that NavCom is “sponsoring” a claim “on behalf of Ball” pursuant to a “contractual obligation”.... [I]f Ball was being sponsored, the effort was noticeably lacking in fervor; two, NavCom seems more intent on sidestepping or evading its liability to Ball by attempting to divert Ball’s claims to the Air Force.

The Contracting Officer eventually denied the claim, finding that “BalTs argument that the MIL-STD-810 failure criteria are ambiguous is unfounded” and that the antennas had failed the test.

Just prior to the Contracting Officer’s decision, Ball filed a demand for arbitration under the contract’s arbitration provision. After initially participating, objecting to locale and choosing acceptable arbitrators, NavCom filed this suit in state court seeking to enjoin the arbitration. Ball removed the suit to federal court.

NavCom moved for a preliminary injunction prohibiting arbitration, and for partial summary judgment prohibiting arbitration and determining the subcontract required the disputed claim be resolved in the Court of Federal Claims where appeal of the contracting officer’s decision was pending. Ball moved to dismiss for failure to state a claim.

The district court summarily granted Nav-Com’s motion for a preliminary injunction and partial summary judgment and denied Ball’s motion to dismiss. As clarified, the court’s order enjoins Ball “from arbitrating any claim raised in its request for arbitration dated April 1,1992, including, but not limited to, all claims or legal theories which refer or relate to Defendant’s claim for an equitable adjustment in the amount of $1,467,949.00.” The district court did not issue findings of fact or conclusions of law.

Ball appeals the district court’s grant of summary judgment for NavCom, denial of Ball’s motion to dismiss, and injunction prohibiting arbitration of Ball’s claims, arguing that its claim against NavCom was not and could not be resolved by the contracting officer and that its dispute with NavCom was arbitrable under the contract.

II.

The Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (“CDA”), provides the statutory framework for resolving disputes between government contractors and the government. Section 605(a) provides that “[a]ll claims by a contractor against the government relating to a contract ... shall be submitted to the contracting officer for a decision,” and § 601(a)(4) defines a “contractor” as “a party to a Government contract other than the Government.” Under the CDA, contracting officers have jurisdiction only over claims by contractors against the government, not over claims brought directly by subcontractors. Erickson Air Crane Co. v. United States, 731 F.2d 810, 813 (Fed.Cir.1984)(“hornbook rule” that subcontractors have no standing to enforce claims under CDA); United States v. Johnson Controls, Inc., 713 F.2d 1541, 1548-49 (Fed.Cir.1983); Clean Giant, Inc. v. United States, 19 Cl.Ct. 390, 392 (1990); see also Senate Report No. 1118, 95th Cong., 2d Sess. 16-17, reprinted in 1978 U.S.Code Cong. & Ad. News 5235, 5250-51 (discussing exclusion of claims brought by subcontractors). A subcontractor may assert a claim against the *880 government only by having the prime contractor “sponsor” and certify the subcontractor’s claim. Erickson Air Crane, 731 F.2d at 813; See Federal Acquisition Regulation 44.203(c); Major John J. Thrasher, “Subcontractor Dispute Remedies: Asserting Subcontractor Disputes against the Federal Government,” 23 Pub. Cont. L.J. 39, 82-99 (1993). The contracting officer has no jurisdiction to resolve disputes between a subcontractor and the prime contractor. U.S. West Communications Servs. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
92 F.3d 877, 41 Cont. Cas. Fed. 76,975, 96 Daily Journal DAR 9681, 96 Cal. Daily Op. Serv. 5891, 1996 U.S. App. LEXIS 19897, 1996 WL 445329, Counsel Stack Legal Research, https://law.counselstack.com/opinion/navcom-defense-electronics-inc-plaintiff-appellee-v-ball-corporation-ca9-1996.