United States Ex Rel. Tech Coatings v. Miller-Stauch Construction Co.

904 F. Supp. 1209, 1995 U.S. Dist. LEXIS 16454, 1995 WL 646675
CourtDistrict Court, D. Kansas
DecidedSeptember 29, 1995
Docket94-4166-SAC
StatusPublished
Cited by12 cases

This text of 904 F. Supp. 1209 (United States Ex Rel. Tech Coatings v. Miller-Stauch Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Tech Coatings v. Miller-Stauch Construction Co., 904 F. Supp. 1209, 1995 U.S. Dist. LEXIS 16454, 1995 WL 646675 (D. Kan. 1995).

Opinion

MEMORANDUM AND ORDER

CROW, District Judge.

The case comes before the court on the defendants’ motion to dismiss for lack of jurisdiction, to compel arbitration, or, in the alternative, to dismiss for improper venue (Dk. 14), and on the plaintiffs motion for sanctions and attorney’s fees against the defendants for not conducting themselves in good faith during the mediation process. (Dk. 16). This is a case brought under the Miller Act, 40 U.S.C. § 270a et seq., in which the plaintiff subcontractor, Tech Coatings, seeks to recover from the defendant prime contractor, Miller-Stauch Construction Company, Inc. (“Miller-Stauch”), and from the defendant surety, Fidelity and Deposit Company of Maryland, on the contractor’s payment bond.

As alleged in the complaint, the United States, acting through the Small Business Administration, contracted with MillerStauch for the construction of a child care facility in the offices of the Federal Aviation Administration in Olathe, Kansas. In compliance with the Miller Act, 40 U.S.C. § 270a(a)(2), Miller-Stauch obtained a payment bond with the surety, Fidelity and Deposit Company of Maryland, “for the protection of all persons supplying labor and material in the prosecution of the work provided for in” the contract. On April 1, 1993, Miller-Stauch entered into a subcontract in which Tech Coatings would provide and apply all special coatings on the child care facility at the agreed price of $14,995.00. Tech Coatings alleges that though it performed its contractual obligations and more, the defendant Miller-Stauch has failed to pay any part of the original contracted price. Tech Coatings further alleges that it lost profits and incurred additional costs because of Miller-Stauch’s delays, design changes, excessive requests for product and/or work submittals, and premature demand to complete the subcontracted work. Tech Coatings seeks to recover $41,847.95, as being the sum owed after totalling the amount due under the subcontract, plus charges for the additional work that Miller-Stauch had ordered, and plus its damages as a result of the Miller-Stauch’s delays and demands.

CONTRACT DISPUTES ACT

The defendants insist Tech Coatings’ suit is covered by the Contract Disputes Act (“CDA”), 41 U.S.C. § 601, et seq. The CDA requires all covered disputes to be submitted first to a contracting officer and authorizes then either an appeal to a board of contract appeals or a direct action suit in the United States Court of Federal Claims. 41 U.S.C. §§ 605, 606, 609(a)(1). By enacting the CDA, Congress intended to create a comprehensive and uniform adjudication scheme for government contract claims. United States v. Seaboard Sur. Co., 817 F.2d 956, 961-62 (2nd Cir.), cert. denied, 484 U.S. 855, 108 S.Ct. 161, 98 L.Ed.2d 115 (1987); Eastern, Inc. v. Shelly’s of Delaware, Inc., 721 F.Supp. 649, 650 (D.N.J.1989). The effect of the CDA is to divest district courts of jurisdiction of federal government contract disputes. Seaboard Sur. Co., 817 F.2d at 962; McDonnell Douglas Corp. v. United States, 754 F.2d 365, 370 (Fed.Cir.1985). If Tech Coatings’ claims are subject to the CDA, then this court would lack subject matter jurisdiction.

“[T]he scope of the CDA is, by design, narrow.” George W. Kane, Inc. v. United States, 26 Cl.Ct. 655, 661 (1992). The CDA “speaks only of claims between a contractor and the government.” Riley Elec. Co. v. American Dist. Telegraph Co., 715 F.Supp. 813, 817 (W.D.Ky.1989) (citing 41 *1212 U.S.C. § 605(a)). 1 By its own plain terms, the CDA encompasses only claims or disputes in which the government is a party and makes no provision for disputes or claims between contractors. Allied Sys. Co. v. Marinette Marine Corp., No. 95-268-FR, 1995 WL 434340, at *3, 1995 U.S.Dist. LEXIS 10363, at *8 (D.Or. July 19, 1995); Riley Elec., 715 F.Supp. at 817-18; see United States ex rel. Jervis B. Webb Co. v. Newberg Construction Co., No. 93-C-5219, 1995 WL 263415, at *2, 1995 U.S.Dist. LEXIS 5872, at *4 (N.D.Ill. May 2, 1995) (The CDA “does not provide for administrative resolution of disputes in which the government is not a party.”); see, e.g., S & M Constructors, Inc. v. Foley Co., No. 92-0142, 1992 WL 37515, 1992 U.S.Dist. LEXIS 2249 (W.D.Mo. Feb. 21, 1992) (“While it [the CDA] has been construed to affect disputes between subcontractors and the Government, the present arbitration does not, as described, directly affect the Government____”). Therefore, the CDA does not govern contract disputes between the prime contractor and the subcontractor. Allied Sys., 1995 WL 434340, at *3, 1995 U.S.Dist. LEXIS 10363, at *8; Newberg Construction, 1995 WL 263415, at *3, 1995 U.S.Dist. LEXIS 5872, at *8; Riley Elec., 715 F.Supp. at 818; see, e.g., Bohn v. United States, 724 F.Supp. 443 (N.D.Tex.1989) (Court exercised Miller Act jurisdiction over subcontractor’s claim against prime contractor but dismissed prime contractor’s cross-claim against the government as subject to the CDA); COSMCO, Inc. v. Head, Inc., 70 Ohio App.3d 544, 591 N.E.2d 803 (1990) (Appeals court upheld the judgment for the subcontractor as to the unpaid balance of the original subcontract but, relying on the CDA, reversed the judgment as to the additional awards for changes in work that were initiated by the government, were made pursuant to the prime contract, and were not the subject of any agreement between the prime contractor and the subcontractor.)

It is by the terms of the CDA, not any contract, that exclusive jurisdictional authority comes to reside with a contracting officer. Allied Sys. Co. v. Marinette Marine Corp., 1995 WL 434340, at *3, 1995 U.S.Dist. LEXIS 10363, at *8. A subcontract that requires the submission of disputes to a contracting officer does not expand the officer’s jurisdictional authority. Id. Nor is it sufficient “to deprive this court of jurisdiction.” Riley, 715 F.Supp. at 819; see also Allied Sys. Co. v. Marinette Marine Corp., 1995 WL 434340, at *3, 1995 U.S.Dist. LEXIS 10363, at *8. It matters not to this court’s jurisdiction that the subcontract requires Tech Coatings to follow the same dispute resolution procedures found in the CDA. 2

Tech Coatings’ complaint plainly alleges that Miller-Stauch is at fault for not paying any part of the original contract price or the additional charges and for the increased costs and lost profits caused by Miller-Stauch’s delays, design changes, excessive requests for product and/or work submittals, and premature demand to complete the subcontracted work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
904 F. Supp. 1209, 1995 U.S. Dist. LEXIS 16454, 1995 WL 646675, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-tech-coatings-v-miller-stauch-construction-co-ksd-1995.