Cosmco, Inc. v. Head, Inc.

38 Cont. Cas. Fed. 76,421, 591 N.E.2d 803, 70 Ohio App. 3d 544, 1990 Ohio App. LEXIS 5424
CourtOhio Court of Appeals
DecidedDecember 6, 1990
DocketNo. 90AP-735.
StatusPublished
Cited by3 cases

This text of 38 Cont. Cas. Fed. 76,421 (Cosmco, Inc. v. Head, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cosmco, Inc. v. Head, Inc., 38 Cont. Cas. Fed. 76,421, 591 N.E.2d 803, 70 Ohio App. 3d 544, 1990 Ohio App. LEXIS 5424 (Ohio Ct. App. 1990).

Opinion

McCormac, Judge.

Defendant-appellant, Head, Inc., appeals from the judgment of the Franklin County Court of Common Pleas in favor of plaintiff-appellee, COSMCO, Inc., and raises the following assignment of error:

“The Trial Court erred as a matter of law in concluding that the subcontract and applicable provisions of the prime contract are not enforceable.”

Appellant was awarded a contract by the federal government to serve as the general contractor on an $8,000,000 construction project at the federally owned. Defense Construction Supply Center (“DCSC”) in Columbus, Ohio. COSMCO submitted a proposal to do certain sheet metal work comprising part of the total contract. It appears that COSMCO originally submitted its proposal to an unsuccessful general contract bidder and the record is unclear as to how Head actually engaged COSMCO. Nevertheless, Head did orally request that COSMCO commence work in the early part of 1987. About a month after COSMCO began working on the project, the two parties con *546 firmed their oral agreement by the execution of a written subcontract calling for COSMCO to perform specified work at a contracted price of $61,050.

The part of the prime contract that is applicable to this suit involves the construction of new roofs over existing roofs on seven buildings at DCSC. Appellee was responsible for fabricating vents which extended from various points on the old roofs through the new roofs and the capping of unwanted vents in the existing roofs. At issue are two changes in the original plans and specifications. Change number one involved the addition of six new vents to one building, which COSMCO contends added $7,140 to the cost of the project. Change number two included the total elimination of vents in four buildings and necessitated capping the openings in the existing roofs. COSMCO submitted a price of $3,960 to Head for these changes.

Head refused to pay the additional sums demanded by COSMCO, contending that its only obligation in the contract was to submit the additional bills to the government official in charge of the contract. Since the official determined that the sums were not due and owing, Head claimed that it had no liability to COSMCO. COSMCO argues that the terms of the prime contract mandating this procedure are not binding on it and, hence, Head is liable to COSMCO for the additional amounts. As a result of the dispute, COSMCO filed suit in the common pleas court.

The trial court, in adopting the report of its referee, concluded that there was no meeting of the minds as to the alternative dispute mechanism and, therefore, COSMCO’s actions were properly commenced against Head. Continuing, the trial court held that Head was liable to COSMCO in the amount of $24,350. That amount consisted of $13,250 outstanding on the original $61,050 contract price, which is undisputed except for a $333 deduction allegedly resulting from the changes, and $11,100 for the aforesaid changes.

Head argues that the trial court erred when it concluded that the subcontract executed by the parties was unenforceable. Head argues that both parties were experienced businessmen who knew or should have known of the contents of the prime contract and that to hold otherwise would violate the right to freely contract.

The subcontract was a standard three-page document which, by its terms, incorporated by reference much of the voluminous prime contract. Section 1 of the subcontract provides, in part:

“ * * * The SUBCONTRACTOR shall furnish all material and perform all work * * *

(( * * *

*547 “in accordance with the Contract between the OWNER and the CONTRACTOR, and in accordance with the General Conditions, Plans, Special Conditions, Drawings, Specifications and Addenda thereto * * *

« * * *

“all of which Contract, General Conditions, Special Conditions, Plans, Drawings, Specifications and Addenda thereto form a part of the Contract between the CONTRACTOR and the OWNER dated January 23, 1987 and further designated and hereby become a part of this SUBCONTRACT. Contract No. DACA27-87-C-0009.”

Subsection 5 of the contract states that:

“ * * * The SUBCONTRACTOR shall make all claims for extras, for extensions of time and for damage for delays or otherwise, to the CONTRACTOR in the manner provided in the General Conditions for like claims by the CONTRACTOR upon the OWNER. The CONTRACTOR shall have no liability to the SUBCONTRACTOR on claims of the SUBCONTRACTOR except to present such claims of the SUBCONTRACTOR to the OWNER and to pay over to the SUBCONTRACTOR any payment received from the OWNER on such claims.”

Subsection 58 of the prime contract vests the government contracting officer with the right to make changes in the work, so long as the changes are within the general scope of the contract. Section 43 of the prime contract addresses disputes and expressly provides that the project is subject to the terms of the Contract Disputes Act of 1978, Sections 601-613, Title 41, U.S.Code.

Section 602(a), Title 41, U.S. Code states:

“(a) Executive agency contracts

“Unless otherwise specifically provided herein, this chapter applies to any express or implied contract (including those of the nonappropriated fund activities described in sections 1346 and 1491 of Title 28) entered into by an executive agency for—

“(1) the procurement of property, other than real property in being;

“(2) the procurement of services;

“(3) the procurement of construction, alteration, repair or maintenance of real property; or,

“(4) the disposal of personal property.”

The Act goes on to provide that all disputes must first be submitted to the contracting officer. The contracting officer’s decision can then be appealed to the Board of Contract Appeals or to the Claims Court. Therefore, if the *548 contract provisions dealing with disputes are applicable to COSMCO, this court cannot entertain jurisdiction over the matter since the Contract Disputes Act has expressly reserved jurisdiction in another forum.

The prime contract at issue involves the “ * * * procurement of construction, alteration, repair or maintenance of real property * * *” and expressly includes the provisions of the Act. Therefore, there is no doubt that the prime contract is governed by the Act. The question is whether the subcontract is governed by the Act.

The trial court determined that, since the work was commenced under an oral agreement and because of the voluminous nature of the contract, there was no agreement on COSMCO’s part to be bound by an alternative dispute mechanism. Both parties testified that commencing work prior to signing a written contract was standard procedure in the construction trade. The written contract was merely meant to confirm and elaborate on the oral understanding. Furthermore, a party to any contract has the duty to read the document before signing it. As this court has stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,421, 591 N.E.2d 803, 70 Ohio App. 3d 544, 1990 Ohio App. LEXIS 5424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cosmco-inc-v-head-inc-ohioctapp-1990.