Williams Enterprises, Inc. v. Strait Manufacturing & Welding, Inc.

728 F. Supp. 12, 1990 U.S. Dist. LEXIS 169, 1990 WL 1227
CourtDistrict Court, District of Columbia
DecidedJanuary 4, 1990
DocketCiv. A. 86-1226
StatusPublished
Cited by2 cases

This text of 728 F. Supp. 12 (Williams Enterprises, Inc. v. Strait Manufacturing & Welding, Inc.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams Enterprises, Inc. v. Strait Manufacturing & Welding, Inc., 728 F. Supp. 12, 1990 U.S. Dist. LEXIS 169, 1990 WL 1227 (D.D.C. 1990).

Opinion

MEMORANDUM OPINION

. BARRINGTON D. PARKER, Senior District Judge:

INTRODUCTION

In this proceeding, the Court is faced with disputed claims of three corporate liti *14 gants covering payment of delay damages arising from the construction of an addition to a public school building in Washington, D.C. At a bench trial, full consideration was given to the testimony of the various witnesses for the parties, their credibility was carefully assessed, and the numerous documents supporting their testimony were reviewed.

The Court determines that cross-plaintiff The Sherman R. Smoot Co. (“Smoot”), has proved by a preponderance of credible evidence that it should prevail and be awarded damages against Williams Enterprises, Inc. (“Williams”) and Strait Manufacturing & Welding, Inc. (“Strait”).

Pursuant to Rule 52, Fed.R.Civ.P., the Court enters Findings of Fact and Conclusions of Law as follow.

FINDINGS OF FACT

A.

(1) This negligence and breach of contract action arises from the construction of a new gymnasium and certain modernizations at the Coolidge High School (“Project”) in Washington, D.C. (“District”). The prime contract for the Project was between the District and Smoot, an Ohio corporation.

Smoot entered into a subcontract with Strait on December 15, 1983. Strait undertook to fabricate and erect the steel frame for the Project. That subcontract provided that Strait would take reasonable safety precautions. Thereafter Strait engaged Williams to undertake the steel erection on the Project.

(2) On September 25, 1984, a steel tower assembled in the area of the Project, which was almost completed by Williams, collapsed causing 25 tons of steel to fall nearly 50 feet to the ground below. The work on the steel erection was totally interrupted. This accident was highly visible, dramatic; it was featured prominently in reports by the print and electronic media. The damaged steel was removed from the job and replaced. The new refabricated steel was delivered to the Project on December 17, 1984.

(3) This legal action was originally brought in 1986 by Williams a second-tier steel erection subcontractor and a local corporation, against a first-tier subcontractor, Strait, a Pennsylvania corporation. Williams sought certain retention payments alleged to be due and owed by Strait. Williams had been employed to accomplish steel erection by Strait. Strait had responsibility for both fabrication and erection of the structural steel for the Project. In turn, Strait filed a third party complaint against Smoot, the prime contractor. Smoot denied the claim for retention payments. In addition, Smoot filed a counterclaim against both Strait and Williams alleging delay damages.

In its counterclaim, Smoot sued the defendant Strait for breach of contract and negligence and the defendant Williams for negligence. Smoot claimed both delay damages, attorneys’ fees, costs, and other expenses from Williams and Strait.

(4) In July 1987, while the litigation was then pending, Williams and Strait entered into an indemnity agreement in which Williams agreed to hold Strait harmless for any responsibility for damages to Smoot arising from Smoot’s claims in this action. Williams also assumed full responsibility for defense of this matter both for itself and Strait.

B.

(5) The prime contract was the Project awarded to Smoot by the District government in late 1983. That contract included a base bid of $9.4 million for the school gymnasium and established a final completion date of 900 days from the date of notice to proceed. That period was established to permit completion of all work on the Project, including the base bid and certain add-ons.

Smoot was required to prepare a Project schedule for submission to and approval by the District. Data for this schedule were gathered by Smoot’s manager, Arthur Dur-rah. He testified that in the process of schedule preparation, he consulted with subcontractors to verify the timing and du *15 ration of sub-elements of the work. This first project schedule, called for a computerized critical path method (“CPM”) document, prepared on December 21, 1983, and approved in due course by the District.

(6) The subcontract between Smoot and Strait contained important provisions related to this present dispute. Section 1 of the subcontract incorporated by reference all terms of the prime contract between Smoot and the District, including the scheduling requirements. Section 2 required that-Strait furnish all labor, materials, and equipment to erect structural steel, steel joist, and steel deck in strict accordance with specifications. Section 6 provided that Strait prosecute the work in a prompt and diligent manner whenever such work, or any part of it, became available, or at such other time the contractor may direct, so as to promote the general prbgress of the entire construction, and shall not, by delay or otherwise, interfere with or hinder the work of the contractor or any other subcontractor. Strait agreed to pay to Smoot such damages as Smoot -might sustain by reason of any delays.

(7) In the original CPM, Smoot established a projected completion date of October 10, .1985, for the Project. Also indicated in the schedule was the final contract completion date required by the District, June 13, 1986. The CPM also specified a duration for each sub-activity. In the case of structural steel erection, the original CPM provided for a total duration of 40 work days. The CPM was updated periodically. A CPM revision dated September 7, 1984 (reflecting the status of the Project as of August 13, 1984, the date on which steel erection actually began) extended the permitted duration of structural steel erection from 40 work days to 45 work days on the critical path.

C.

(8) With respect to the September 25, 1984 steel collapse, Smoot presented expert testimony, including impressive investigative reports of the Occupational Safety and Health Administration (“OSHA”), and other reputable and creditable sources. Wholesale violations of industry and government safety standards were indicated. Williams’ attorney presented no contrary evidence, and he admitted that his client did not contest that its failure to follow appropriate safety standards caused the collapse.

(9) There is no dispute that the steel erection was on the CPM. The original schedule established for steel erection was 40 work days, expanded to 45 days as of August 13, 1984. According to daily job logs, August 13,1984 was the day on which Williams mobilized and began steel erection, pursuant to arrangements with Smoot and Strait. Scheduled completion of structural steel as of that date was October 16, 1984.

(10) It is generally accepted that a delay to an item on the critical path of a project will cause an equal delay to the completion of the project. To quantify delay, Smoot presented expert testimony of Barry Brow-er, of Brower & Associates, who measured the delay by using two alternate methods. First, he examined the Project which scheduled completion of steel erection on October 16, 1984. Actual completion of structural steel, including completion of the setting of roof decking on the building as required by the subcontract, was not achieved until January 30, 1985.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
728 F. Supp. 12, 1990 U.S. Dist. LEXIS 169, 1990 WL 1227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-enterprises-inc-v-strait-manufacturing-welding-inc-dcd-1990.