The United States of America for the Use and Benefit of TSI Tri-State Painting, LLC v. Federal Insurance Company

CourtDistrict Court, S.D. Georgia
DecidedJanuary 13, 2022
Docket2:16-cv-00113
StatusUnknown

This text of The United States of America for the Use and Benefit of TSI Tri-State Painting, LLC v. Federal Insurance Company (The United States of America for the Use and Benefit of TSI Tri-State Painting, LLC v. Federal Insurance Company) is published on Counsel Stack Legal Research, covering District Court, S.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The United States of America for the Use and Benefit of TSI Tri-State Painting, LLC v. Federal Insurance Company, (S.D. Ga. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF GEORGIA BRUNSWICK DIVISION

THE UNITED STATES OF AMERICA FOR THE USE AND BENEFIT OF TSI TRI- STATE PAINTING, LLC,

Plaintiff/Counter-Defendant, CIVIL ACTION NO.: 2:16-cv-113

v.

FEDERAL INSURANCE COMPANY,

Defendant/Counter-Claimant.

O RDE R This matter is before the Court on Plaintiff Tri-State Painting, LLC’s Motion to Exclude Certain Opinion Testimony of Michael Harris. Doc. 129. Defendant Federal Insurance Company (“Federal”) filed a Response, and Plaintiff filed a Reply. Docs. 138, 147. On November 15, 2021, the Court held a hearing on Plaintiff’s Motion to Exclude, at which counsel for both Plaintiff and Federal appeared. Dkt. entry dated Oct. 12, 2021; Doc. 158. Following the hearing, the parties submitted supplemental briefing on the matter. Docs. 161, 162. For the following reasons, the Court GRANTS Plaintiff’s Motion to Exclude. Harris is not permitted to offer expert testimony about the apportionment of responsibility for containment-related delays using figures provided by Federal’s counsel (e.g., the Government is responsible for 75% of the containment-related delays and the subcontractors, including Plaintiff TSI, are responsible for the remaining 25%). This Order does not otherwise limit Harris’ testimony, and he is generally permitted to testify in accordance with the Federal Rules of Evidence. BACKGROUND Plaintiff TSI sues Federal over a project at the Naval Submarine Base in Kings Bay, Georgia. Doc. 1. Plaintiff worked as a subcontractor for the general contractor, Sauer, Inc.1 Doc. 129-1 at 1–2. The project had a series of delays, and the parties dispute who is responsible

for the delays. Responsibility for the delays impacts the amount that may be owed under the contract for work Plaintiff performed. The reasons included delays due to weather and performance issues. Doc. 129-2 at 9–13. Additionally, significant delays arose from detection of lead paint at the site, which had to be removed before the project could continue. The removal of the lead paint also required use of a containment system. There were significant delays related to the implementation and execution of the containment system. Id. These “containment-related delays,” and Federal’s expert’s anticipated testimony on who bears responsibility for them, are the focus of Plaintiff’s challenge in the instant Motion. Federal hired Michael Harris, a civil engineer with Secretariat International, to perform a delay analysis of the project. Id.; Doc. 129-2. Harris has an undergraduate degree in civil and

environmental engineering, as well as a juris doctorate, and has worked as a licensed engineer for more than 30 years.2 Doc. 138 at 1. Harris has previously testified as an expert in arbitrations, boards of contract appeals, and state court proceedings. Id. Harris offers a comprehensive report and set of opinions on the allocation of responsibility for delays during the course of the project. Doc. 129-2. Harris’ opinions focus on determining allocation of responsibility for the days of delay and, specifically, delays associated with TSI’s work. Id. at 9–

1 Federal represents Sauer Inc.’s interests in this litigation. For convenience, the Court treats Federal and Sauer as interchangeable in this Order.

2 Plaintiff does not challenge Harris’ qualifications at this time. A summary of Harris’ qualifications is provided only as background. The Court makes no finding as to whether Harris is qualified to offer any particular opinion. 12. Harris provided two reports assigning responsibility for project delays—his Independent Report and Rebuttal Report. See generally id. Harris’ Independent Report involves an analysis on the causes of various delays occurring during the project and who bears responsibility for those delays—including responsibility for containment-related delays. Id. at 88–159. Harris’

Rebuttal Report offers similar opinions and also an analysis of Plaintiff’s expert’s opinions on delays. Id. at 7, 26–58. In his Rebuttal Report, Harris reached conclusions about which delays were TSI’s responsibility and for which delays TSI should be compensated. Id. at 14–17. In sum, in both his Independent and Rebuttal Reports, Harris generally provides his expert opinions on which party was responsible for which delays based on his own analysis of the project. The parties disagree over one aspect of Harris’ opinions contained in his Reports. In the Independent and Rebuttal Reports, Harris states Federal “has determined that delays related to the containment should be apportioned so that NAVFAC bears 75% of the responsibility and Sauer’s subcontractors bear the remaining 25%.”3 Id. at 18; see also id. at 93, 95. Harris explains he did not validate the 75/25 allocation figure for containment delays. Id. at 18. The

parties agree the 75/25 allocation figure was provided to Harris by Federal’s counsel and Harris has not had any opportunity to determine the accuracy of the figure. Indeed, Federal acknowledges it has not disclosed the basis for the 75/25 allocation figure to Plaintiff, instead explaining only it intends to “prove [the figure] at trial.” Doc. 138 at 5. Nonetheless, Harris

3 NAVFAC is the United States Naval Facilities Engineering Command, which Sauer and TSI performed work for at the Kings Bay Naval Submarine Base and which was ultimately responsible for overseeing the project. provides a new assessment of overall responsibility for all delays utilizing the 75/25 allocation figure for containment-related delays. Doc. 129-2 at 18, 93, 95. To be clear, the 75/25 allocation figure provided by Federal’s counsel is distinct from Harris’ own, independent opinions about the parties’ responsibility for containment-related

delays. Harris initially determined Plaintiff TSI is responsible a number of days of delay. Id. at 94, 155. This determination was based on his experience and expertise and review of several relevant aspects of the project. Id. at 101–154. Additionally, in his Rebuttal Report, Harris addressed expert opinions by JS Held, Plaintiff’s expert, and revised his own opinions about TSI’s responsibility for certain delays, including containment-related delays. Id. at 82. Harris provides a robust analysis of the JS Held opinion. Id. at 13–15, 24–50. Harris explains how JS Held’s conclusions and methodology influence his own analysis—even leading him to make revisions to his initial opinion. Id. at 55–59. That is, Harris provided opinion based on his expertise about the responsibility for containment-related delays at issue in this suit, both initially and in consideration of JS Held’s opinions.

Despite forming his own opinions about containment-related delays, Harris also utilized the 75/25 figure provided to him by Federal’s counsel. Id. at 83. Harris notes use of Federal’s counsel’s figure resulted in removing 77 compensable delays from Plaintiff and results in Plaintiff only having 64 compensable days. Id. Harris provides no reasoning for his adjustment, other than reliance on the 75/25 figure.4 Harris, in his Reports and testimony, was candid the 75/25 allocation was not the result of him applying his expertise to determine who was responsible for the delays, but was simply given to him by Federal’s counsel, who informed him

4 Harris also utilized a figure assuming 50% NAVFAC containment responsibility and 25% NAVFAC containment responsibility, which are also unsupported and are equally unreliable. Doc. 129-2 at 84–85. Unlike the 75/25 figure, there is no indication Federal relies on these other allocation figures. they would prove this is the correct allocation at trial. Doc. 129-2 at 18; Doc. 129-3 at 4–5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Richard Junior Frazier
387 F.3d 1244 (Eleventh Circuit, 2004)
Rink v. Cheminova, Inc.
400 F.3d 1286 (Eleventh Circuit, 2005)
Louise Cook v. Sheriff of Monroe County
402 F.3d 1092 (Eleventh Circuit, 2005)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Kumho Tire Co. v. Carmichael
526 U.S. 137 (Supreme Court, 1999)
Go Medical Industries Pty, Ltd. v. Inmed Corp.
300 F. Supp. 2d 1297 (N.D. Georgia, 2003)
Seamon Ex Rel. Estate of Seamon v. Remington Arms Co.
813 F.3d 983 (Eleventh Circuit, 2016)
Andre Ow Buland v. NCL (Bahamas) Ltd.
992 F.3d 1143 (Eleventh Circuit, 2021)
McLean v. 988011 Ontario, Ltd.
224 F.3d 797 (Sixth Circuit, 2000)
Tillman v. C.R. Bard, Inc.
96 F. Supp. 3d 1307 (M.D. Florida, 2015)
In re Delta/Airtran Baggage Fee Antitrust Litigation
245 F. Supp. 3d 1343 (N.D. Georgia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
The United States of America for the Use and Benefit of TSI Tri-State Painting, LLC v. Federal Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-united-states-of-america-for-the-use-and-benefit-of-tsi-tri-state-gasd-2022.