United States v. Sci, Inc.

828 F.2d 671, 34 Cont. Cas. Fed. 75,404, 9 Fed. R. Serv. 3d 534, 1987 U.S. App. LEXIS 12825
CourtCourt of Appeals for the Eleventh Circuit
DecidedSeptember 28, 1987
Docket86-3477
StatusPublished
Cited by8 cases

This text of 828 F.2d 671 (United States v. Sci, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Sci, Inc., 828 F.2d 671, 34 Cont. Cas. Fed. 75,404, 9 Fed. R. Serv. 3d 534, 1987 U.S. App. LEXIS 12825 (11th Cir. 1987).

Opinion

828 F.2d 671

9 Fed.R.Serv.3d 534, 34 Cont.Cas.Fed. (CCH) 75,404

UNITED STATES of America, for the Use and Benefit of
SEMINOLE SHEET METAL COMPANY, Plaintiff-Appellant,
v.
SCI, INC., f/k/a Sainer Constructors, Inc. and Fidelity and
Deposit Company of Maryland, Defendants-Appellees.

No. 86-3477.

United States Court of Appeals,
Eleventh Circuit.

Sept. 28, 1987.

R. Wade Wetherington, Gibbons, Tucker, McEwen, Smith, Miller & Whatley, Tampa, Fla., for plaintiff-appellant.

Philip N. Hammersley, Trawick & Griffis, Henry P. Trawick, Jr., Sarasota, Fla., for defendants-appellees.

Appeal from the United States District Court for the Middle District of Florida.

Before JOHNSON and CLARK, Circuit Judges, and MORGAN, Senior Circuit Judge.

JOHNSON, Circuit Judge:

In this appeal brought under the Miller Act, 40 U.S.C.A. Secs. 270a-270d, Seminole Sheet Metal Co., the successor in interest to Floridaire Mechanical Systems, Inc.,1 challenges the district court's (1) dismissal of counts related to delay damages, (2) denial of an amendment to conform the evidence to the pleadings, and (3) selection of the date upon which to base prejudgment interest. We affirm in part and reverse and remand in part with directions.I.

In 1978, SCI, Inc., and the Veterans Administration (VA) executed a contract for the construction of a hospital in Bay Pines, Florida. Fidelity and Deposit Company of Maryland furnished a payment bond as required by the Miller Act. SHS Associates, an architectural firm, designed the hospital. SCI and Floridaire subsequently executed a subcontract for the heating, ventilating, and air conditioning component of the project.

In late December of 1978, Floridaire submitted its choice of fan coil units to SHS for approval. SHS rejected Floridaire's choice, stating that the fan coil units failed to comply with SHS's specifications. Floridaire informed SCI that SHS's prescribed ratio among required gallons per minute, minimum sensible BTUH, and cubic feet per minute was mathematically impossible. Consequently, Floridaire claimed it could not make fan coils meeting those specifications. Floridaire maintained that its choice was the best approximation. After a series of meetings, the VA and SHS eventually agreed to modify the specifications for the fan coil units. In December of 1979, they approved fan coil units very similar to those Floridaire had initially submitted.

Floridaire subsequently sued SCI under the Miller Act.2 Count I of the amended complaint sought the recovery of the subcontract's unpaid balance. Counts II through VI sought damages occasioned by the delay in approving the fan coil units, primarily increased labor and material costs. After the close of Floridaire's case in chief in the nonjury trial, the district court granted SCI's motion to dismiss Counts II through V on the grounds that Floridaire had not proven that the delay in its work was caused by the VA, SCI, or SHS, and that its damages were speculative and unsupported by any evidence. The court also refused to allow Floridaire to amend its complaint pursuant to Fed.R.Civ.P. 15(b) in order to add a claim for the recovery of the increased cost of the fan coil units. Consequently, the court entered judgment in favor of Floridaire for $88,970 with prejudgment interest calculated at 12% from February 15, 1983.

II.

Floridaire contends that the district court improperly dismissed its claims against SCI for damages resulting from the improper specifications for the fan coil units.3 As to this issue we affirm the district court.

Floridaire sought to recover delay damages from SCI by proving that SCI failed to timely resolve inconsistencies and errors in the fan coil drawings and specifications (Count III); that SCI impliedly warranted the validity of the drawings and the specifications (Count IV); and that SCI modified the drawings and specifications as a result of the errors and inconsistencies, thereby creating a constructive change in the subcontract (Count V).

The cross-examination testimony of Michael Tappouni, Floridaire's vice president in charge of construction during the time period relevant to this case, indicated that SCI did nothing to impede or impair Floridaire in the submittal approval process (R4-85). Tappouni also admitted that SCI "did not prepare the plans or specifications for the project" and that SCI did not have the responsibility "to approve or disapprove of the submittals in the final analysis" (R4-86). Responsibility for preparation of the specifications and approval of Floridaire's submittal rested with SHS, the hospital's architect. Thus, Floridaire seeks to hold SCI liable for delay damages occasioned by SHS's actions.

The subcontract between SCI and Floridaire absolves SCI of liability in such a situation. Paragraph 4(c) of the subcontract specified that:[SCI] shall not be liable to [Floridaire] for delay to [Floridaire]'s work because of the act, neglect or default of [the VA] or [SHS], or fire or other casualty, riots, strikes or combined action of the workmen or others, acts of God, any other cause beyond [Floridaire]'s control, or any circumstance caused or contributed to by [Floridaire].

Although this action was brought under the Miller Act, state law governs whether SCI materially breached the subcontract. United States ex rel. Riley v. Diran Co., 597 F.2d 446, 447 n. 1 (5th Cir.1979); United States ex rel. Aucoin Elec. Supply Co. v. Safeco Ins. Co. of Am., 555 F.2d 535, 541 (5th Cir.1977). Florida, where the subcontract was executed and performed, provides the governing law here. Florida courts have upheld the validity of "no damages for delay" clauses. See, e.g., C.A. Davis, Inc. v. City of Miami, 400 So.2d 536, 539-40 (Fla.Dist.Ct.App.), petition for review dismissed, 411 So.2d 380 (Fla.1981); McIntire v. Green-Tree Communities, Inc., 318 So.2d 197, 199 (Fla.Dist.Ct.App.1975). Thus, SCI ordinarily could invoke the "no damages for delay clause" to avoid liability for SHS's actions.4

A "no damages for delay" clause, however, does not immunize a contracting party for delays caused by that party's fraud or concealment or by that party's active interference. C.A. Davis, 400 So.2d at 539-40; McIntire, 318 So.2d at 199. This restriction comports with a contracting party's implied promise not to hinder the other party's ability to perform its contractual obligation. Casale v. Carrigan & Boland, Inc., 288 So.2d 299, 301 (Fla.Dist.Ct.App.), appeal dismissed, cert. dismissed, 301 So.2d 100 (Fla.1974). Furthermore, the subcontract here allowed Floridaire to communicate with SHS only through SCI. Consequently, SCI assumed an additional duty of assisting Floridaire with its complaints to SHS. Id.

Nothing indicates that SCI engaged in fraudulent conduct or concealed the flawed specifications from Floridaire.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
828 F.2d 671, 34 Cont. Cas. Fed. 75,404, 9 Fed. R. Serv. 3d 534, 1987 U.S. App. LEXIS 12825, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-sci-inc-ca11-1987.