United States Ex Rel. Ragghianti Foundations III, LLC v. Peter R. Brown Construction, Inc.

674 F. App'x 901
CourtCourt of Appeals for the Eleventh Circuit
DecidedJanuary 4, 2017
Docket14-15336
StatusUnpublished
Cited by5 cases

This text of 674 F. App'x 901 (United States Ex Rel. Ragghianti Foundations III, LLC v. Peter R. Brown Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Ragghianti Foundations III, LLC v. Peter R. Brown Construction, Inc., 674 F. App'x 901 (11th Cir. 2017).

Opinions

PER CURIAM:

Defendant-Appellee Peter R. Brown Construction, Inc. (“PRBC”), hired Plaintiff-Appellant Ragghianti Foundations III, LLC (“Ragghianti”), as a subcontractor to pour concrete for the construction of a military training facility in San Angelo, Texas. Concluding that Ragghianti did a poor job, PRBC terminated its contract with Ragghianti for default. Ragghianti, however, blamed any deficiencies in the construction project on PRBC’s own shortcomings in orchestrating the project. Through this lawsuit, Ragghianti sought to recover damages in the form of costs it incurred as a result of PRBC’s alleged mismanagement and negligence.

Following a bench trial, the district court denied Ragghianti’s claims, except that it awarded the money Ragghianti was still owed for work performed. Because Ragghianti cannot show that its subcontract entitled it to the damages it sought, we affirm the district court’s judgment.

I. Background

Detailed findings of fact are set forth in the district court’s order. We include a summary of facts relevant to this appeal.

On August 16, 2010, the United States Army Corps of Engineers (“Corps”) contracted with PBS&J Constructors, Inc., to build a military training facility in San Angelo, Texas. In compliance with the Miller Act, 40 U.S.C. § 3131,1 PBS&J obtained payment and performance bonds from sureties Liberty Mutual Insurance Company and Safeco Insurance Company of America, naming PBS&J as principal, and PBS&J furnished them to the government.

PBS&J’s subsidiary, PRBC, entered into a subcontract with Ragghianti on January 24, 2011. The subcontract required Ragghianti to install the concrete for the training facility, including its slab on grade foundation. By the subcontract’s terms, the law of the state in which the project was [904]*904located—Texas—governed the relationship, except where otherwise provided.

From its start, the construction project was beset by obstacles causing delay and deviation from its ever-amended schedule. First, Ragghianti was not prepared to mobilize its labor until almost three weeks after the scheduled time due to its delay in procuring a bond, as required by the subcontract. Then PRBC was not ready for Ragghianti’s work until over two months after that. Next, unforeseen soil conditions delayed drilling. When drilling resumed, Ragghianti’s failure to provide sufficient labor further delayed the project. In late 2011, the Corps issued PRBC a draft “interim unsatisfactory” review.

Most significantly for purposes of this appeal, the initial concrete pour for the slab on grade went terribly. Only six of the expected thirteen workers from Ragghian-ti’s sub-subcontractor showed up on February 14, 2012, the day of the pour. Then eight of the fourteen pump trucks transporting concrete turned the concrete for longer than the 90-minute time limit before use. As a result, much of the concrete became too dry to finish properly. While Ragghianti blames PRBC in part for the quality of the concrete it provided and for delaying the pump trucks, neither party currently disputes that the finish on the slab was of “unacceptable quality.”

On February 16, 2012, PRBC issued a failure-to-perform letter related to the February 14 concrete pour. The failure-to-perform letter provided Ragghianti 48 hours to remove the unsatisfactory concrete, and it requested an action plan for future slab pours. Ragghianti submitted an action plan the next day, which stated that “demolition of the existing [slab on grade]” would commence no later than February 20 and could “arguably” be completed within a week’s time.

By the morning of February 22, however, Ragghianti’s workers still had not begun removing the slab, despite having been on premises for most of the intervening days. So on February 22, 2012, PRBC issued a notice-of-termination letter, citing Ragghianti’s failure to cure the defective slab on grade, among other faults. Although Ragghianti employed one worker and one piece of borrowed equipment to begin breaking up the concrete slab on February 22 and 23, PRBC did not consider this a sufficient attempt to complete the necessary remedial work in a timely manner. PRBC therefore hired other subcontractors to break up the slab and complete the concrete work for the training facility.

In April 2012, Ragghianti filed suit. The amended complaint set forth a breach-of-contract claim against PRBC and an alternative claim for damages in quantum me-ruit. Ragghianti also sought recovery from PRBC’s co-sureties, Safeco Insurance and Liberty Mutual, under the Miller Act. PRBC counterclaimed for contractual indemnification and breach of contract.

Following a five-and-a-half-day bench trial, the district court awarded Ragghianti damages under the subcontract for its unpaid furnished labor and materials but denied its other claims. The court entered judgment in favor of PRBC on both of its claims, an award totaling $435,457 after Ragghianti’s damages were subtracted from PRBC’s. In addition, the court awarded PRBC attorneys’ fees, which have yet to be determined.

II. Analysis

Following a bench trial, we review a district court’s factual findings for clear error and its legal conclusions de novo. Renteria-Marin v. Ag-Mart Produce, Inc., 537 F.3d 1321, 1324 (11th Cir. 2008).

Ragghianti raises four main issues on appeal. First, Ragghianti argues that the [905]*905district court erred in holding that fair-notice requirements under Texas law were not applicable to the indemnity provisions at issue in the subcontract. Second, Rag-ghianti disputes the district court’s determination that Ragghianti was properly terminated for default rather than at PRBC’s convenience. Third, Ragghianti takes issue with the scope of damages that the district court awarded it. And fourth, Ragghianti challenges the decisions of the district court denying Ragghianti’s attorneys’ fees and granting PRBC’s attorneys’ fees. We address each argument in turn.

A.

We begin with the district court’s determination that Texas’s fair-notice requirements were not applicable to the indemnity provisions under review. In Texas, “extra-ordinary risk shifting clauses” that indemnify a party from the consequences of its own negligence or release a party in advance for liability for its own negligence must meet two so-called fair-notice requirements. Green Int’l, Inc. v. Solis, 951 S.W.2d 384, 386 (Tex. 1997). First, the express-negligence doctrine requires “a party seeking indemnity from the consequences of that party’s own negligence [to] express that intent in specific terms within the four corners of the contract.” Dresser Indus., Inc. v. Page Petroleum, Inc., 853 S.W.2d 505, 508 (Tex. 1993) (citation omitted). Second, the terms must appear conspicuously “on the face of the contract to attract the attention of a reasonable person when [s]he looks at it.” Id. (alteration and internal quotation marks omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
674 F. App'x 901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-ragghianti-foundations-iii-llc-v-peter-r-brown-ca11-2017.