Kinetic Systems, Inc. v. IPS-Integrated Project Services, LLC and Lonza Biologics, Inc.

2024 DNH 008
CourtDistrict Court, D. New Hampshire
DecidedFebruary 6, 2024
Docket20-cv-1125-SM
StatusPublished

This text of 2024 DNH 008 (Kinetic Systems, Inc. v. IPS-Integrated Project Services, LLC and Lonza Biologics, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinetic Systems, Inc. v. IPS-Integrated Project Services, LLC and Lonza Biologics, Inc., 2024 DNH 008 (D.N.H. 2024).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Kinetic Systems, Inc.

v. Civil No. 20-cv-1125-SM Opinion No. 2024 DNH 008 IPS-Integrated Project Services, LLC and Lonza Biologics, Inc.

O R D E R

This dispute arises out of a commercial construction

project in Portsmouth, New Hampshire. Kinetic Systems, Inc. was

a subcontractor on that project and brought an action against

Integrated Project Services, LLC (“IPS”), the project’s general

contractor, and Lonza Biologics, Inc., the owner, seeking nearly

$14 million for extra work it alleges that it did on that

project.1 IPS moves for partial summary judgment, challenging

Kinetics’s breach of contract claim for payment of amounts

related to certain changes in the project. Kinetics objects to

summary judgment, arguing that material factual disputes as to

whether IPS waived contract provisions preclude summary judgment

1 In the complaint, the plaintiff refers to itself as “Kinetics” although the name of the company is Kinetic Systems, Inc. In the current motions and memoranda, the plaintiff refers to itself as “KSI”, while IPS uses “Kinetics”. On its website, the plaintiff refers to itself as “Kinetics”. www.kinetics.net (last visited January 18, 2024). To avoid confusion, the court will consistently refer to the plaintiff as “Kinetics”.

1 and that the partial waivers and releases it signed are not

enforceable.

Standard of Review

Summary judgment is appropriate when the moving party shows

that there is no genuine dispute of material fact and that it is

entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a);

M.L. by and through D.L. v. Concord Sch. Dist., 86 F.4th 501,

510 (1st Cir. 2023) (internal quotation marks omitted). A

genuine dispute “is one that must be decided at trial because

the evidence, viewed in the light most flattering to the

nonmovant, would permit a rational factfinder to resolve the

issue in favor of either party.” Id. (internal quotation marks

omitted). “Material facts are those that might affect the

outcome of the suit under the governing law.” Id. Therefore,

no genuine dispute of material fact is shown “if, based on the

record, there is no factual determination which a rational

factfinder could make as to the existence or nonexistence of a

fact that has the potential to change the outcome of the suit.”

Gibson Found., Inc. v. Norris, 88 F.4th 1, 5 (1st Cir. 2023).

Background

IPS was the general contractor on a project to construct a

manufacturing facility for Lonza. It, in turn, hired Kinetics

2 to construct and implement mechanical and process systems at the

Lonza facility. That subcontracting relationship was governed

by two contracts: the Early Mechanical Subcontract and the

Process Piping Subcontract. Each Subcontract requires IPS to

pay Kinetics a lump sum for the work specified. The

Subcontracts also include provisions for changing the scope of

work, increasing the amount to be paid, and resolving disputes

about changes and payments.

A. Subcontract Provisions for Changing Work and Payment

The Subcontracts require certain procedures to make changes

to the scope of Kinetics’s work on the project, including

changes to the time required and payments due, which are found

in Section 6 of each Subcontract, titled “Changes in the Work.”

Doc. no. 57-2, at 20-22; Doc. no. 57-8, at 20-22. Section 7

provides the procedures for payment, and Section 12 provides the

procedures for claims and disputes between IPS and its

subcontractors. Doc. no. 57-2, at 22-23 & 57-2, at 35-36; Doc.

no. 57-8, at 22-3 & 57-8, at 35-36.2

To make a change to the requirements in the Subcontracts,

IPS first is required to notify the subcontractor of the

2 The Subcontracts include the same language pertinent to changes in the work and related procedures. The court will cite to the Subcontract sections rather than the documents where the Subcontracts are filed. 3 proposed change. § 6.2. After receiving notice - but before

beginning the work - the subcontractor is required to submit “a

written proposal for the Change, which proposal shall include,

(a) the modification to the scope of Work to be performed under

the proposed Change, (b) Subcontractor’s good faith estimate of

the adjustment in the Subcontract Price payable as a result of

the proposed Change, and (c) Subcontractor’s estimate of the

adjustment, if any, to the Subcontract Time resulting from the

proposed Change.” § 6.4. IPS then decides whether to accept or

reject the subcontractor’s written proposal for an adjustment to

the subcontract. Id. If a subcontractor does not request a

time or cost adjustment through a timely proposal, the

subcontractor is deemed to represent that no adjustment is

required and waives its right to any adjustment for that Change.

§ 6.5.

The subcontractor is required to submit all claims for

adjustment due to a change in the work within the time provided

in the change notice. § 6.8. If no time is provided, then

claims are to be made within five business days of the date of

the notice “but in no event less than two (2) Business Days

prior to the date upon which IPS must respond with all such

claims under the Prime Contract, whichever period is shorter.”

Id. The parties expressly agree that the subcontractor waives

any claims for adjustment to the price and time provided in the

4 Subcontracts if a claim is not submitted to IPS within the time

allowed. Id.

A subcontractor can also make claims for increases in the

price or time for the work “[d]ue to acceleration, disruption,

inefficiency or for any other reason which may adversely impact

the Work or Subcontractor’s performance under the Agreement

within two (2) Business Days following the occurrence of the

event giving rise to the claim.” § 6.12.1. Such claims have to

be supported by “appropriate information and documentation.”

Id. The Subcontracts also provide that “Subcontractor’s timely

compliance with the notice requirements in section 6.12.1 shall

be a condition precedent to Subcontractor’s entitlement to a

Subcontract adjustment in either the time or price and

Subcontractor waives and releases any claim to additional

compensation or an extension of time in the event that

Subcontractor does not so comply.” § 6.12.4.

If the parties are unable to agree upon a price for

Kinetics’s additional work, the Subcontracts allow IPS to compel

Kinetics to perform the work through a “Change Directive,” after

which the parties were committed to agree upon an appropriate

adjustment to the price and time allowed. § 6.6. Importantly,

however, Anthony Malvone, IPS’s Operations Manager, states in

his declaration that IPS did not issue a Change Directive to

Kinetics for the Lonza project to compel Kinetics to perform

5 work outside the scope of the Subcontracts. Doc. no. 57-25, ¶

12. Kinetics does not dispute that statement.

The Subcontracts also provide a process for resolving

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D. M. Holden, Inc. v. Contractor's Crane Service, Inc.
435 A.2d 529 (Supreme Court of New Hampshire, 1981)
MacQuesten General Contracting, Inc. v. HCE, INC.
191 F. Supp. 2d 407 (S.D. New York, 2002)
City of Portsmouth v. Nash
493 A.2d 1163 (Supreme Court of New Hampshire, 1985)
Gianola v. Continental Casualty Co.
817 A.2d 306 (Supreme Court of New Hampshire, 2003)
Daniel v. Hawkeye Funding, Ltd. Partnership
843 A.2d 946 (Supreme Court of New Hampshire, 2004)
Axenics, Inc. v. Turner Construction Co.
62 A.3d 754 (Supreme Court of New Hampshire, 2013)
M.L. v. Concord School District
86 F.4th 501 (First Circuit, 2023)
Gibson Foundation, Inc. v. Norris
88 F.4th 1 (First Circuit, 2023)
Fraser Engineering v IPS-Integrated
2018 DNH 067 (D. New Hampshire, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2024 DNH 008, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinetic-systems-inc-v-ips-integrated-project-services-llc-and-lonza-nhd-2024.