Kinetic Systems, Inc. v. IPS-Integrated Project Services, LLC and Lonza Biologics, Inc.

2025 DNH 040
CourtDistrict Court, D. New Hampshire
DecidedMarch 24, 2025
Docket20-cv-1125-SM
StatusPublished
Cited by1 cases

This text of 2025 DNH 040 (Kinetic Systems, Inc. v. IPS-Integrated Project Services, LLC and Lonza Biologics, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinetic Systems, Inc. v. IPS-Integrated Project Services, LLC and Lonza Biologics, Inc., 2025 DNH 040 (D.N.H. 2025).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Kinetic Systems, Inc.

v. Case No. 20-cv-1125-SM Opinion No. 2025 DNH 040 IPS-Integrated Project Services, LLC and Lonza Biologics, Inc.

O R D E R

Following jury verdicts in favor of Kinetic Systems, Inc.

and Lonza Biologics, Inc., in this commercial construction

contract case, all three parties moved for an award of

attorneys’ fees under provisions in the Subcontracts. The

primary issue is which of them is a “prevailing party” within

the meaning of § 17.7 of the Subcontracts. For the reasons that

follow, Kinetics’s motion is granted in part, and IPS’s and

Lonza’s motions are denied.

Background

Kinetics filed suit in state court in October of 2020,

seeking to recover $13,973,898.26 that it claimed IPS and Lonza

owed it under the Subcontracts, or alternatively, through a

claim for quantum meruit/unjust enrichment. Doc. 1-2. The

defendants removed the case to this court and moved to dismiss

the claims. The court dismissed only the quantum meruit/unjust enrichment claim, based on the viability of the breach of

contract claim. Doc. no. 15.

The case proceeded through discovery (which included a

motion for a writ of replevin against Kinetics by Lonza to

recover turnover package documents and a challenge to Kinetics’s

expert witness). Kinetics voluntarily dismissed its claims

against Lonza. The trial scheduled in September of 2023 was

continued due to Kinetics’s counsel’s medical issue. Counsel

withdrew from representation, and new counsel filed an

appearance on behalf of Kinetics in December of 2023.

The court granted IPS’s partial motion for summary judgment

to the extent the breach of contract claim in Count I was based on

amounts that IPS failed to pay in response to change orders CP-10

and CP-24 and the Bulletin Change Proposals that were rejected as

untimely. The court reinstated the quantum meruit claim, but

allowed IPS to move for summary judgment, which was granted.

After those proceedings, Kinetics’s breach of contract claim,

Count I, remained as to claims for back charges, which totaled

$2,227,028.98, for Change Order 009 and a back charge invoice and

for reductions in amounts paid on the Process Subcontract, as

supported by Exhibits 1 and 2 to document no. 91. The court

dismissed four of Lonza’s counterclaims against Kinetics, leaving

Lonza’s breach of contract and violation of the New Hampshire

Consumer Protection Act claims.

2 The court held a six-day jury trial on Kinetics’s breach of

contract claim against IPS and Lonza’s breach of contract claim

against Kinetics. Following trial, the court dismissed the

Consumer Protection Act claim. The jury returned a verdict on

Kinetics’s breach of contract claim, finding that IPS improperly

back charged $444,875.53 against the amount Kinetics claimed. The

jury also found that Lonza proved that Kinetics breached one or

both Subcontracts, but awarded no damages to Lonza. Doc. no. 148.

Kinetics renewed its motion for judgment as a matter of law

under Federal Rule of Civil Procedure 50(b) post trial, which the

court denied. Doc. no. 163. Lonza moved to amend the judgment

entered by the clerk of court to show that the jury found in its

favor on the breach of contract claim but awarded no damages. The

court granted that motion, and an amended judgment was entered.

Doc. no. 165. Kinetics, IPS, and Lonza each moved for an award of

attorneys’ fees and costs.

Discussion

Under New Hampshire law, parties generally bear their own

litigation costs, but the court may award attorneys’ fees and costs

to a prevailing party when that recovery is authorized by an

agreement among the parties. In re J.P., 173 N.H. 453, 466, 242

A.3d 823, 834 (2020). All three motions seek fees and costs under

the following provision in the Subcontracts:

3 § 17.7 If any legal action, arbitration, or other proceeding is brought for the enforcement of this Agreement, or because of an alleged dispute, breach, default, or misrepresentation in connection with any of the provisions of this Agreement, successful or prevailing Party or Parties will be entitled to recover reasonable attorney fees and other costs authorized by Statute which are incurred in that action or proceeding, in addition to any other relief to which they may be entitled.

Doc. no. 57-8, at 43. In addition, IPS mentions § 6.10 to support

its request for fees and costs:

A. Section 6.10 – IPS

IPS argues briefly that it is entitled to an award of fees and

costs under § 6.10, 1 which provides as follows:

In the event the Subcontractor submits an adjustment request for a Change that has no merit or that is based in whole or in part upon materially inaccurate assertions, IPS shall be entitled to collect from Subcontractor by offset or otherwise any and all costs and expenses, including but not limited to reasonable attorney’s fees, incurred by IPS investigating, responding to, defending against and resolving such claim or request.

1 Given the lack of developed argument by IPS to support an award under § 6.10, that theory is likely waived. United States v. Zannino, 895 F.2d 1, 17 (1st Cir. 1990) (“It is not enough merely to mention a possible argument in the most skeletal way, leaving the court to do counsel's work, create the ossature for the argument, and put flesh on its bones.”); see also Wadsworth v. Nguyen, No. 23-1463, 2025 WL 547405, at *19 (1st Cir. Feb. 19, 2025); Higgins v. New Balance Athletic Shoe, Inc., 194 F.3d 252, 260 (1st Cir. 1999) (“The district court is free to disregard arguments that are not adequately developed.”).

4 Id., at 22. Taken in context and particularly in light of the

attorneys’ fees provision in § 17.7, § 6.10 only applies when a

subcontractor submits a change request that is frivolous or made in

bad faith. See Wescott v. Warden, New Hampshire State Prison, ---

A.3d ---, No. 2022-0562, 2024 NH 56, 2024 WL 4469345, at *2 (N.H.

Oct. 11, 2024) (“When interpreting a written agreement, we give the

language used by the parties its reasonable meaning, considering

the circumstances and the context in which the agreement was

negotiated, and reading the document as a whole.”). IPS has not

demonstrated that either of those circumstances occurred here. 2

Therefore, IPS’s motion for an award of fees and costs is

denied to the extent it is based on § 6.10.

2 Notably, IPS moved to dismiss Kinetics’s breach of contract claim for unapproved change requests on procedural grounds as premature, arguing that the parties were continuing to process the claims. Doc. no. 15, at 7. IPS did not assert that the change requests had no merit. Later, the court granted summary judgment in IPS’s favor on claims for unapproved change requests that were not timely submitted to IPS, but IPS did not establish that the unapproved change requests had no merit. Doc. no. 89. Before trial, IPS and Kinetic stipulated that IPS owed Kinetic certain amounts for approved change orders that it had not paid because it claimed back charges against those amounts. Doc. no. 131.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2025 DNH 040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinetic-systems-inc-v-ips-integrated-project-services-llc-and-lonza-nhd-2025.